3-Dimensional Views Existing spillway construction
2
3-Dimensional Views First concrete pour inside spillway (summer 2013)
3
3-Dimensional Views New concrete pier extensions (summer 2014) This work takes place “in the dry” behind a sheet pile cofferdam
4
3-Dimensional Views Stoplogs are placed between piers & rest on new concrete sills Once stoplogs are in place water levels can be returned to normal
5
3-Dimensional Views Construction work taking place between 2015 and 2016 More concrete is poured in the base of the spillway Existing gate and bridge are removed
6
3-Dimensional Views Construction work taking place between 2015 and 2016 Concrete rollaway slabs and most of upstream barrel arches are removed
7
3-Dimensional Views Construction work taking place between 2015 and 2016 New concrete crest is poured
8
3-Dimensional Views Construction work taking place between 2015 and 2016 Concrete overlay is placed over entire pier structure
9
3-Dimensional Views Construction work taking place between 2015 and 2016 New bridge is constructed
10
3-Dimensional Views Tobacco Spillway to be completed in 2016 New gate is installed and stoplogs are removed
11
3-Dimensional Comparison Existing spillway Modified spillway