Lyme Regis No longer Slip-sliding Away September 1, 2006
2
Introduction
3
Location England Southwest Coast Dorset Jurassic Coast World Heritage Site Exposed to severe winter storms
4
West, 2006
5
Stormy Weather Undated, 1970’s storm Source: West, 2006
6
Calm Weather
7
The Geology of Lyme Regis Greensand Clay Shale Blue Lias
8
Steep slope
9
The Beginnings of a Landslip Charmouth Road Car Park Asphalt is contributing to landslip Work underway to improve drainage system
10
The Black Venn Between Lyme Regis and Charmouth Mostly Clay and Shales with Beef Prone to landslides Rich source of fossils
11
The Blue Lias West of Lyme Regis at Monmouth Bay Greensand Clay Limestone
12
Landslides 1962 Langmoor Gardens Caused by construction activities The area was re- graded and Langmoor gardens were established
13
The Spittles East of Lyme Regis The whole system was reactivated in 1986
14
Long-shore drift interrupted Beach buildup Monmouth beach Increased protection Beach depletion Shingle supply interrupted This results in depletion
15
The depleted beach(1960’s) and breached seawall (1974)
16
Coastal Defenses - The Cobb
17
Coastal Reinforcements Beacon Rocks extended by 110 meters North wall rockery realigned Added rock armor at Cobb Gate New jetties at Lister Gardens and Cobb Gate Beach replenishments Sand and shingle Raised beach level by 2 meters
18
Beacon Rocks
19
Armor rocks: 11,000 tonnes core rock, 2 - 5 tonnes each 26,500 tonnes armor, 9 - 18 tonnes each Source: Norwegian granite Byproduct of granite counter top industry Shingle (pebbles): 72,000 tonnes Source: Isle of Wight Sand: 37,000 tonnes Source: northern France Precast concrete: Source: UK Limestone facing Source: China
20
Rock Armor at Cobb Gate Jetty
21
Finishing up at Cobb Gate Jetty
22
Reinforcements at Cobb Gate
23
Lyme Harbor beach restored
24
Work continues at Langmoor Gardens
25
Slope stabilization Began in 2005, scheduled completion 2007 Major engineering effort involved considerations for seismic stability Only small equipment allowed until slope was sufficiently stabilized Gradual increase in machinery size based on monitoring
26
1,150 auger-cast piling Drilled holes thru clay into bedrock Filled with concrete and reinforcement Act as dowels to hold slope Soil nails Similar to piling but horizontal 2,300 meters drainage Counterforts - at base Drilled drains -in hill French drains - below car park
27
Conclusion Phase II construction is nearly complete Coastal defenses Slope stabilization Increased security for town Increased income due to tourism Cost to maintain will be less than the cost of emergency repairs