Mechanisms Shilling, Tim Lowrey, Anthony McArthur, Grayson
2
Colorado Space Grant Consortium
Introduction Mechanisms includes restraints and release for: Aerofins FITS thin film solar arrays Gravity gradient tether The mechanisms will release the deployables in a predetermined order Gravity Gradient Tether FITs The restraint mechanisms are based around Planetary Systems’ Lightband, Starsys’ HOP (High Output Paraffin Actuator) and TiNi Aerospace’s Frangibolt Colorado Space Grant Consortium
3
Subsystem Requirements Imposed on Structures
Must retain mechanisms in a failsafe manner Must release the deployables in a reliable fashion Must release the deployables in the order discussed on the previous slide Must meet power and thermal requirements Colorado Space Grant Consortium
4
Subsystem Requirements Imposing on Others
5-7 Hi/Low lines to signal different stages of deployment Aerofins Released: 2 Aerofins Final Deployed Position: 2 FITS Released: 2 (?) Tether Released: 1 1 HOP requiring 18W at 28V for minutes Aerofins Release Lightband separator requiring 12V for 1 minute (May Change) Tip Mass Release 2 Frangibolts 28V for 30 Sec FITS 4 composite hinges requiring 28V for 1 minute Two per Aerofin Two Aerofins Thermal control of composite hinges (maintain hinge temperature between 88 and 92 deg. Celsius by cycling power to hinges) Minimum of two controls, one per aerofin Requires data lines for two thermal couple (Sampling once per second) Colorado Space Grant Consortium
5
Gravity Gradient Tether (GGT)
Anthony Colorado Space Grant Consortium
6
Flow Chart - GGT Input and Control Lightband
10 12V for 1 minute High/Low output (Switch signaling final released position) Colorado Space Grant Consortium
7
Thin Film Solar Array (FITS)
Responsibility Microsat FITS Restraint Panel Deployment Hinges CSGC Restraint/release system hardware General Provided by Microsat Released with the in-house release system (IRS) Preloaded to 100lb Upon Release deployment is almost instantaneous Colorado Space Grant Consortium
8
Flow Chart - FITS Input and Control Frangibolt 1 25 watts @ 28V
High/Low output (Switch signaling final released position) High/Low output (Switch signaling final released position) Colorado Space Grant Consortium
9
Solar Array Subsystem Overview - Stowed
Stowed Solar Array Envelope (0.318 x x m) Volume = m3 / Wing (0.067 ft3) / Wing Deployment Hinge Separation Device Restraint Panel Colorado Space Grant Consortium
10
Solar Array Subsystem Overview - Deployed
Deployed driving requirements - Power - 13 Vdc and 60 Deployed Solar Array 1.10 m2 / Wing Fold Integrated Thin Film Stiffener (FITS) Stainless Steel CIGS Array 85 Watts BOL - AMO Deployed Solar Array Meets All Requirements Colorado Space Grant Consortium
11
Colorado Space Grant Consortium
Frangibolt Colorado Space Grant Consortium
12
Colorado Space Grant Consortium
Specifications Colorado Space Grant Consortium
13
Colorado Space Grant Consortium
Aerofins General 2 Composite panels Solar Arrays mounted to Panels Deployed with 4 composite hinges from CTD Held down for launch with an in-house release system (IRS) based on Starsys’ HOP Will be released concurrently with the FITS, but activated after the FITS are deployed. May be deployed simultaneously or separately Responsibility CTD Composite aerofins Composite Hinges (With Mounts) Ability to interface with Restraint/release system hardware CSGC Restraint/release system hardware Colorado Space Grant Consortium
14
Flow Chart - Aerofins Input and Control Aerofins H.O.P 18 watts @ 28V
for 1.5 minutes High/Low output (Switch signaling final released position) Composite Hinges 10 28V per Hinge for 1 minute 2-4 Hinges required High/Low output (Switch signaling final deployed position) Colorado Space Grant Consortium
15
Colorado Space Grant Consortium
Composite Hinges Provided by Composite Technology Development (CTD) Rigid in cooled State When Heated returns to Original Shape 4 composite hinges requiring 28V for 1 minute Colorado Space Grant Consortium
16
Colorado Space Grant Consortium
Aerofins Mounting Cups Cones Colorado Space Grant Consortium
17
Colorado Space Grant Consortium
Cup Cones Colorado Space Grant Consortium
18
Complete Aerofin Assembly
Cup Aerofin To HOP Release IRS Cone Side Panel Colorado Space Grant Consortium
19
Colorado Space Grant Consortium
Release System - HOP Pin Puller Less then 120g 50 lbs of force One HOP releases 4 Deployables Total travel of HOP release Pin: .3in Activated with 28V at 18 watts for 2 minutes, which heats up the wax inside the piston, expanding it and causing the pin puller to move HOP releases rings that attach to the release system via steel cable Simultaneous release of FITs and then simultaneous release of Aerofins Colorado Space Grant Consortium
20
Colorado Space Grant Consortium
Release System - Latch Multiple springs to ensure failsafe Stainless steel construction (Chemically treated to reduce Friction) Aluminum 6061 Case All moving components are of the same material to ensure against thermal expansion issues Colorado Space Grant Consortium
21
Release System - Pin Stainless Steel Construction .25in stroke
.175in opening Stowed Released Opening PIN Colorado Space Grant Consortium
22
Colorado Space Grant Consortium
HOP Puller FITS Attachment Aerofin Attachment Bracket Posts HOP Colorado Space Grant Consortium
23
Pulleys and Cables - All cables will be steel and run - through piping or eye hooks Colorado Space Grant Consortium
24
FITs Solar Array Release
Colorado Space Grant Consortium
25
Colorado Space Grant Consortium
Aerofin Release Colorado Space Grant Consortium
26
Colorado Space Grant Consortium
HOP Release Ring Forces (lb) Coefficent of Static Friction Coefficient of Kinetic Friction Factor of Safety Min Stowed Pull Force (lb) Min Deployed Pull Force (lb) 12 0.2 0.15 2 41.6 31.2 40 Total (lb) Stroke Length (in) 104 0.31 Colorado Space Grant Consortium
27
Colorado Space Grant Consortium
Testing Plan, GGT Short length deployments on an air table < 2ft Tests Lightband separation kickoff Medium length deployment on a KC-135 < 6ft Tests Coulomb damper Test tip off parameters Long length deployment using a vertical test > 10ft Test kickoff with damping Colorado Space Grant Consortium
28
Colorado Space Grant Consortium
Testing Plan, Aerofins CTD Hinge Aerofin Structure Structure Air table Sled Sled Air table Colorado Space Grant Consortium
29
Testing Plan, Release System
Gravity Colorado Space Grant Consortium
30
Colorado Space Grant Consortium
Parts List In-House IRS Aluminium: < $50 Steel Cable: < $10 Springs: < $10 Pulley system: <$20 Mounting brackets Testing equipment FITS Aerofins Tip mass Coulomb damper Guides Outsourced Aerofins: Free HOP: Free FITS: Free Arrays Hinges 2 Fringebolt: Free Actuator 6 bolts: $20 each Reset Tool: TBD Tip mass Lightband Tether Colorado Space Grant Consortium
31
Issues and Concerns (Things to be done)
Run Finite Element Analysis on Mechanisms Research material chemical treatments and coatings that will reduce friction Procure suitable steel cabling Reduce size and mass of components Coefficients of friction Colorado Space Grant Consortium