Interior and Exterior Demo Continue Dust Control Measures for Air Quality Management Per LEED Construction Plan 4/16/12 – 4/20/12 Iconic Birdcage Removed from Structure
2
New Gas and Water Service Underground Started
3
Health Inspector Page Turn of CD Documents Exterior Continue Demo of Atrium Begin Removal of Stairwells Finish Gas and Water Line Utility Services Interior Complete all temporary walls for Phase 1 Saw Cut of Dining Level Slab for Removal Complete temporary office space in 1927 Wing Remove remaining ceilings and MEP Overhead PROJECT MEETINGS HELD NEXT WEEK LOOK AHEAD BIM Coordination Meeting