Presentation is loading. Please wait.

Presentation is loading. Please wait.

Public Works Department Debarment Hearing Concrete Restoration Services Ltd. Bid Opportunity 524-2009.

Similar presentations


Presentation on theme: "Public Works Department Debarment Hearing Concrete Restoration Services Ltd. Bid Opportunity 524-2009."— Presentation transcript:

1 Public Works Department Debarment Hearing Concrete Restoration Services Ltd. Bid Opportunity 524-2009

2 Public Works Department Recommendation: Debar Concrete Restoration Services Ltd. (CRS) for a three year period from acting as contractor, sub-contractor, or supplier to any person who is awarded a contract with the City of Winnipeg.

3 Public Works Department Notice of Default issued on Sept. 21, 2012 Pursuant to C18.1(f) & C18.1(l) CRS failed to remedy defects or deficiencies and failed to comply with an order given by the Contract Administrator

4 Public Works Department C18.1 An event of default will have deemed to have occurred if the Contractor: (f) fails to remedy defects or deficiencies during the warranty period in the manner and within the time frames specified by the Contract Administrator; (l) refuses or neglects to comply with an order given by the Contract Administrator;

5 Public Works Department On Sept. 13, 2012 CRS acknowledged in writing they refused to undertake repairs during warranty period indicating: “CRS and Transpo Industries will not accept any liability to provide restorative or remedial action as has been requested by the Contract Administrator….”

6 Public Works Department Cannot allow Contractors to refuse to follow Contractual instructions.

7 Public Works Department Pursuant to C13.8 if the Contractor disagrees with a determination they shall nonetheless comply with the order and may appeal concurrently. Failure to comply resulted in an event of default and a serious breach of Contract.

8 Public Works Department Warranty Work pursuant to Clause C13.8: If a Contractor disagrees with the Contract Administrator’s determination under C13.6, he shall nonetheless comply with C13.7. The Contractor may concurrently appeal the determination of the Contract Administrator as provided in C21.

9 Public Works Department Event of Default resulted in the City taking control of the Work to correct unsafe conditions caused by the debonded overlay.

10 Public Works Department Overlay status: 19% debonded in 2012. Repaired by City in 2013 at a cost of $26,682.85. 48% debonded in 2014 and was removed by City forces. Remaining 33% has several areas where overlay has worn through to concrete.

11 Public Works Department Five Year Warranty

12 Public Works Department

13 Exceptions to the Warranty Agreement relate to the condition of the concrete deck. There is no evidence these exceptions exist on the concrete deck. The concrete deck is in good condition.

14 Public Works Department Onus is on Contractor to prove the exceptions exist. Due diligence would have required on-site visual assessment and extraction of cores to test concrete properties such as strength, hardened air void, permeability, and chloride content.

15 Public Works Department Observed Overlay Defects

16 Public Works Department Debonding occurred at the interface of the overlay and the concrete deck. Cracking has occurred within the overlay. No waterproof seal in other localized areas due to premature wear through overlay. Inadequate overlay thickness in localized areas. Specified thickness is 8 mm.

17 Public Works Department Widespread debonding the result of localized cracking/debonding followed by wet conditions and traffic causing larger areas to shear off and debond. Concrete residue identified on the debonded overlay is fraction of mm thick and the result of the shearing process or debris from the surface preparation process.

18 Public Works Department Cracking and premature wear the result of a resin rich overlay due to aggregate seeding deficiencies. Aggregate seeding deficiencies were identified at time of construction. During Appeal #1 CRS advised these areas would perform which is not the case.

19 Public Works Department Aggregate Seeding Deficiencies Black areas are resin rich. Aggregate did not have aggregate bond into the resin.

20 Public Works Department Typical Overlay Debonding Note original deck tyning still in tact.

21 Public Works Department Typical Overlay Debonding Note original deck tyning intact.

22 Public Works Department Debonding with bubbling Note straight debond line at interface of placement.

23 Public Works Department Typical Transverse Cracking Overlay was still bonded.

24 Public Works Department Typical Gauge Rake Gouging

25 Public Works Department Insufficient Overlay Thickness

26 Public Works Department Insufficient Overlay Thickness Possibly caused by premature wear.

27 Public Works Department Premature Overlay Wear Note overlay has worn through to the concrete.

28 Public Works Department Premature Overlay Wear Possibly caused by mechanical damage as a result of originally rough surface.

29 Public Works Department Premature Overlay Wear 2014 Note several locations where overlay has worn through to concrete.

30 Public Works Department Premature Overlay Wear 2014 Up close view of worn through area.

31 Public Works Department Localized Deck Condition 2014 Curb lane in area of debonded overlay.

32 Public Works Department Typical Underside of Debonded Overlay Black areas are clear resin. Grey areas are concrete residue.

33 Public Works Department Typical Underside of Debonded Overlay Closer view

34 Public Works Department Typical Side View of Debonded Overlay Note thin residue thickness.

35 Public Works Department Concrete Deck Constructed in 2002 Initial set retarded but 28 day strength exceeded design requirements Initial scaling in the first winter resulted in extensive testing and inspection for 5 years.

36 Public Works Department Concrete Deck (cont’d) Testing included compressive strength, air voids analysis, chloride content, permeability, petrographic examination, and chemical analysis. Annual visual inspections for five years. Concluded concrete was in the normal range.

37 Public Works Department Concrete Deck (Cont’d) To date there is no evidence of concrete disintegration, spalling, or cracking as a result of structural movements. No cores or relevant concrete testing has been undertaken to determine that a Warranty exception exists.

38 Public Works Department Bond Testing Surface preparation measure according to : –B.O. 524-2009 –Transpo T-18 Technical Data Sheets –Every other reference we could find. Not a method for determining the quality of the concrete.

39 Public Works Department E3.3.1 Surface Preparation (f)The acceptability of the surface preparation will be determined by a vertical axis pull bond test. This test involves the bonding of a 64 mm diameter steel disk to the prepared substrate, using a fast- setting epoxy, and it’s removal from the substrate by applying a vertical pull. (g)Substrate preparation will be approved if at least 75% of the bonded steel disk surface is covered with substrate concrete exceeding 3mm in depth. The frequency of this test is at the discretion of the Contract Administrator…

40 Public Works Department CRS states bond test value must be ≥1.7 MPa This is not supported by: BO 524-2009 Transpo T-18 Technical Data Sheets ACI-503R ACI-548.8-07 ACI-548.9-08M3 ACI-548.10-10 ASTM C1853

41 Public Works Department Previous documents identify a minimum value for the resin not the substrate. Basic Engineering Premise: The adhesive should be stronger than the substrate it is bonding.

42 Public Works Department AASHTO-AGC-ARTBA – Task Force 34 1995 Guide Indicates 1.7 MPa or failure at a depth of 6mm. Similar to Contract specifications in that a significant matrix of concrete needs to be pulled for the test to pass; not just residue to have a failure in the concrete.

43 Public Works Department

44 Eng-Tech Bond Test/Report CRS indicated areas were shot-blasted prior to testing. No evidence to support this claim. Only 2 tests were directly on concrete both of which met specification/guideline criteria. Tests 1, 2, & 6 identify failure in concrete but no failure depth identified nor is it support by photos of the core locations.

45 Public Works Department Bond Test 3 = 1.8 MPa On Concrete. Note depth of failure. Debris in hole.

46 Public Works Department Bond Test 4 = 1.0 MPa On concrete. Meets all specifications & guidelines. Note the rough fracture surface.

47 Public Works Department Bond Test 5 = 0.88 MPa On overlay. Clear failure in overlay.

48 Public Works Department Bond Test 1 = 1.3 MPa Reported as 75% failure in concrete substrate. Fracture surface does not support report finding.

49 Public Works Department Bond Test 2 = 0.82 MPa Reported as 75% failure in concrete substrate. Fracture surface does not support report finding.

50 Public Works Department Bond Test 6 = 0.54 MPa Reported as 100% failure in concrete substrate. Clear error. Tyned surface still visible.

51 Public Works Department END


Download ppt "Public Works Department Debarment Hearing Concrete Restoration Services Ltd. Bid Opportunity 524-2009."

Similar presentations


Ads by Google