1
DoE Review June 6-7, 2000 Current Detector Configuration June 6, 2000 Solenoid, Central Preshower installed in central bore A-layer MDTs installed on inner faces of end irons Central muon system installed, being commissioned South end calorimeter, end irons on sidewalk North and south trusses in Hi Bay, being prepped for move to sidewalk Central iron, north calorimeter in open positions to allow access Shield wall up
2
DoE Review June 6-7, 2000 Current Detector Configuration June 6, 2000 South end calorimeter, end irons on sidewalk A-layer MDTs installed on faces of end irons Commissioning Level 1 trigger, muon system, online, silicon front-end, solenoid
3
DoE Review June 6-7, 2000 Install Fiber Tracker in Solenoid June 16-29, 2000 Fiber Tracker being installed in central bore North A-layer pixel sheet mounted on shield wall Commissioning of DAQ, online, central muon system, etc. continues
4
DoE Review June 6-7, 2000 Move Platform West, Pick Up End Irons July 11-28, 2000 Fiber Tracker installed, south end calorimeter back in place on platform Platform moves west to pick up two end irons Detector buttoned up for move Commissioning interrupted until platform returns east (services disconnected)
5
DoE Review June 6-7, 2000 Move Platform West, Pick Up End Irons July 11-28, 2000 Platform moves west to pick up two end irons Movable Counting House moves with detector during pick up Assembled north A-layer pixel plane remains on shield wall
6
DoE Review June 6-7, 2000 North & South Trusses Move to Sidewalk July 31 – August 25, 2000 Platform returns to east position with end irons installed North & south trusses, shielding brought down to sidewalks from Hi Bay, assembled Detector remains buttoned up until trusses are down Cabling of Fiber Tracker begins after south truss is in place Platform services reconnected, commissioning resumes
7
DoE Review June 6-7, 2000 North & South Trusses Move to Sidewalk July 31 – August 25, 2000 Platform returns to east position with end irons installed North & south trusses brought down to sidewalks South calorimeter, end iron opens to allow cabling of Fiber Tracker A-layer north pixel sheet mounted on shield wall, awaits installation
8
DoE Review June 6-7, 2000 A- & C-layer Pixels & MDTs Installed November 10, 2000 A- and C-layer detectors mounted SMT-S installed, hooked up – SMT-N being installed Trusses ready to install in Collision Hall South calorimeter, end irons open to allow access to inter-cryostat region Commissioning of CFT, SMT, Forward and Central Muon, attendant readout
9
DoE Review June 6-7, 2000 Trusses Installed in Collision Hall Nov 20 – Dec 11, 2000 North & south ends of shield wall removed, blocks stacked in Hi Bay Loaded trusses rolled into Collision Hall, surveyed Platform remains in Assembly Hall, rolled in after trusses in place Commissioning of detectors on platform continues
10
DoE Review June 6-7, 2000 Trusses Installed in Collision Hall Nov 20 – Dec 11, 2000 Mounting of B-layer MDTs on outer faces of end irons near completion North B-layer pixel plane assembled on shield wall End cryostats/irons open as logistics allow Cosmic ray commissioning & triggering using SMT, CFT, and muon
11
DoE Review June 6-7, 2000 Detector Rolled in and Hooked Up February 16, 2001 Platform rolled in to meet trusses Full detector in final closed position: hooked up, ready for beam Shield wall back up Movable Counting House travels with detector, cable bridge down Commissioning with cosmic rays continues until beam is delivered (March 1, 2001)
12
DoE Review June 6-7, 2000 Access to Detector in Collision Hall Closed Position - Data-TakingOpen Position - Detector Access Shielding retracted South calorimeter open North B-layer pixels open South end iron open North end iron closed
13
DoE Review June 6-7, 2000 Forward Muon B-Layer Installation May, 2000 End irons moved toward center of Assembly Pit to allow access for B-layer installation/surveying Commissioning continues
14
DoE Review June 6-7, 2000 D0 Commissioning Timeline Commissioning/Integration Goals 2000 2001 J F M A M J J A S O N D J F M D Run II begins: Mar 1, 2001 Roll in No LHe LAr Beam- ready #1 #3 #2 DAQ/online system running in user mode Integration Goal #1: dual muon crates, initial muon triggering/filtering, ship data to farm, run reconstruction, online event display Begin full central muon system, integrate Level 2 muon trigger at DAB test stand Silicon front-end installed/commissioned Forward muon C-layer MDTs/pixels installed/commissioned #6 #5 Forward muon A&B layer MDTs/pixels installed/commissioned Integration Goal #2: Initial triggering on L1 CFT/CPS, begin linking tracks in CFT/CPS/CMuon, begin Level 2 trigger integration Half of CFT, CPS hooked up, checked out #4 #9 #10 #11 Integration Goal #4: Full detector in steady- state Cosmic Ray Commissioning SMT, CAL fully added to commissioning chain, exercise full triggering with all major systems Integration Goal #3: Add Central Calorimeter to commissioning stream, most major systems being commissioned #8 #7
15
DoE Review June 6-7, 2000 Trusses Assembled on North & South Sidewalks July 21 – August 25, 2000 Detector returns to east position with end irons installed Trusses brought down from Hi Bay to sidewalks Central irons, calorimeters remain closed for movement of trusses Hookup of Fiber Tracker begins after south truss is in position Commissioning resumes, begin integration of CFT
16
DoE Review June 6-7, 2000 Current Detector Configuration Phase I A-layer MDTs, Pixels being mounted, surveyed onto faces of end irons C-layer truss and shielding has arrived in Hi-Bay, being dressed Remainder of detector remains open for access
17
DoE Review June 6-7, 2000 Current Detector Configuration Commissioning continues, using Central Muon as prototype system: u Multi-crate readout of full central muon system u Event monitoring, crate control, steady DAQ running, filtering u Exercise reconstruction, online event display (on cosmic ray muons)
18
DoE Review June 6-7, 2000 Forward Muon B-Layer Installation May-June, 2000 A-layer planes installed B-layer MDTs, Pixels being mounted, surveyed onto faces of end irons C-layer trusses and shielding continue to be dressed in Hi-Bay
19
DoE Review June 6-7, 2000 Install Fiber Tracker in Solenoid May, 2000 Fiber Tracker + Cart/I-Beam system lowered into gap between South End Calorimeter and Central Calorimeter Rolled into solenoid bore along I-Beam Fiber Tracker Cart System
20
DoE Review June 6-7, 2000 EMCs Installed in Collision Hall December 11, 2000 - January 11, 2001 Shield wall is broken down, moved to now free space in Hi-Bay North and South C-layer trusses/shields, having been assembled on sidewalk, rolled into Collision Hall - surveyed into place Detector will be rolled into place to meet trusses
21
DoE Review June 6-7, 2000 EMCs Installed in Collision Hall Full Cosmic Ray Commissioning of all systems continues during most of this period End irons, calorimeters can be opened for access
22
DoE Review June 6-7, 2000 Detector Rolled In, Hooked Up Phase III Detector installed in compact space Access to internal tracking detectors, end muon detector planes must be carefully coordinated
23
DoE Review June 6-7, 2000 South EMC Truss Moves to South Sidewalk November 29- December 5, 1999 South C-layer truss moves to south sidewalk EMCs, shielding re-assembled on sidewalk to prepare for rolling in
24
DoE Review June 6-7, 2000 South EMC Truss Moves to South Sidewalk November 29- December 5, 1999 South C-layer truss moves to south sidewalk in two pieces, reassembled Preparing to take down shield wall for roll in
25
DoE Review June 6-7, 2000 The DØ Upgrade Tracking System Charged Particle Momentum Resolution p T /p T ~ 5% @ p T = 10 GeV/c