Presentation is loading. Please wait.

Presentation is loading. Please wait.

Reconstruction of the Eads Bridge Highway Deck

Similar presentations


Presentation on theme: "Reconstruction of the Eads Bridge Highway Deck"— Presentation transcript:

1 Reconstruction of the Eads Bridge Highway Deck
Michael J. Cronin, PE, SE

2 Eads Bridge History Opened to traffic July 4, 1874
Designed and planned by James Buchanan Eads Underwater salvage expert Shipbuilder No formal education Hired by the St. Louis and Illinois Bridge Company as engineer-in-chief for this project

3 Eads Bridge History Design and construction innovations
deep pressurized caisson construction

4

5 Eads Bridge History Design and construction innovations
deep pressurized caisson construction high strength cast steel

6

7

8 Eads Bridge History Design and construction innovations
deep pressurized caisson construction high strength cast steel design of components to permit ease of replacement

9

10 Eads Bridge History Design and construction innovations
deep pressurized caisson construction high strength cast steel design of components to permit ease of replacement cantilever construction of main arch spans

11

12 Eads Bridge History Design and construction innovations
Deep pressurized caisson construction high strength cast steel design of components to permit ease of replacement cantilever construction of main arch spans 500 ft spans were 200 ft longer than any built previously

13 Bridge Ownership History
Illinois and St Louis Bridge Company Missouri Pacific Railroad Company Terminal Railroad Association City of St. Louis / Bi-State Development Agency

14 Rehabilitation Challenges
Preserve historically important aesthetic elements Use existing substructure to support new highway deck Maintain light rail traffic during construction

15 New Cross Section Four 11 ft lanes designed for HS-20 loading
1 ft offset between outside lanes and the Jersey barriers 5 ft sidewalk on south side of roadway

16

17 Bridge Sections West Approach West Arcade Main Spans East Arcade
East Approach

18

19 West Approach & East Arcade
Substructure: 3 longitudinal walls Outside walls of stone or brick masonry, original construction Center wall of minimally reinforce concrete, constructed in the 1920’s Substructure repairs Tuckpointing Crack repair Reinforced concrete pads

20

21

22

23

24 West Approach & East Arcade
Longitudinal concrete beams over First and Second Streets Spalled and cracked Some section loss in reinforcing Capacity found to be marginally acceptable Repairs fiber composite wrap total replacement

25

26

27 West Approach & East Arcade
Existing superstructure: transverse concrete floorbeams with distinctive sloped ends Replaced with prestressed concrete I girders with special ends designed as 2 span continuous to maintain distribution to supporting walls Precast SIP form panels utilized

28

29

30

31 West Arcade Substructure: 2 longitudinal walls
East portion - stone masonry arches in fairly good condition concrete infill used to strengthen arches West portion - reinforced concrete open arches in poor condition total replacement with new reinforced concrete arches

32

33

34 West Arcade Existing superstructure
non-composite rolled beams at 4 ft spacing deck replaced in early 1980’s design called for cleaning & painting beams, scarifying & overlaying deck Change order proposed by contractor total replacement of superstructure with composite rolled beams at 8.5 ft spacing

35

36

37 Main Spans Existing substructure - 2 piers and 2 abutments founded on bedrock Good condition Top surfaces of piers and abutments required crack repair and resurfacing

38

39

40 Main Spans Arch truss superstructure
no retrofit required if dead load from new floor system and deck is held < 116 psf

41 Main Span Floor System Existing floor system: half-filled grid deck on floorbeams at 6 ft spacing New floor system eliminated floorbeams between columns - 12 ft spacing Exodermic™ Deck specified to span the 12 ft between floorbeams 74 psf using standard weight aggregate

42 Main Span Floor System The Exodermic™ deck, or an “unfilled steel grid deck composite with a ±4.5” reinforced concrete slab” provides: Light weight Structural efficiency Protection of Light Rail operating below

43 ExodermicTM Bridge Deck

44

45

46 Special Main Span Features
Overlook areas at piers and abutments Bridge can be closed to traffic for special weekend events Electrical outlets built into north barrier

47

48 East Approach 10 spans of new steel superstructure on new concrete substructure ft Highway deck starts above MetroLink track and end below Highway deck had to be built around MetroLink bridge and elevated station as well as abandoned foundations

49 East Approach Drilled shaft construction one shaft per pier
up to 7 ft in diameter utilized to minimize footprint and to avoid vibrating adjacent MetroLink foundation

50

51

52

53 East Approach Steel straddle bents transverse beams
support the highway deck over the MetroLink tracks and elevated station platform where traditional supports cannot be used

54

55

56 Connection to MetroLink
Handicap accessible ramp built to connect sidewalk to East Riverfront Station

57

58 Reopening - July 4, 2003

59 THANK YOU


Download ppt "Reconstruction of the Eads Bridge Highway Deck"

Similar presentations


Ads by Google