Madison Elementary School District Bond Project Update August 2013
2
Solar Update Madison #1
3
Solar Update Rose Lane Elementary
4
Solar Update Park Elementary
5
Solar - Schedule of Completion Structural and panel set- 8/22/13 Broken sidewalk replacement- 8/26/13 Installation of turf and DG- 9/16/13 Substantial completion- 9/23/13 First day of generation- 9/26/13 Final Completion- 10/14/13
6
The Next Step in Solar Site evaluations later this week Preliminary design by 8/29 Submitting applications to APS for rebates by 8/30
7
Rose Lane Café Remodel
8
Madison Heights Café Remodel
9
Madison Meadows Site Work
10
Upcoming Projects Madison Heights kitchen remodel Madison Meadows front office remodel Non-skid surfacing on exterior stairs Roof replacement at Heights Daylighting in dining areas at Heights, Park and Rose Lane Questions: