Southern Natural Gas Company 2013 Outage Review Meeting Customer con call and Webex July 17, 2013 1
2
Welcome 2
3
Agenda Review Unscheduled Outages Review of Upcoming Outages – July/August and September North System South System South Louisiana – Outages for the remainder of 2013 North System South System South Louisiana Contacts 3
4
Disclaimers Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time). Scheduled dates are subject to change. Projects may be added, altered, delayed or cancelled. SNG will provide notice of such additions or changes via SoNet Premier postings. Dates as posted on SoNet should be deemed correct in the event of conflicts between SoNet posted dates and dates within this presentation. 4
5
Color Key for Maps Green – No Impact Anticipated Yellow – Restrictions are possible – With extended duration, restrictions could be necessary from time to time – Meter(s) affected are denoted with (M) Red – Restrictions are probable 5
6
Southern Natural Gas Pipeline LA MS AL GA FL Enterprise White Castle Bear Creek Muldon Chattanooga Atlanta Thomaston Albany Elba SC Aiken Elba Express North System South Louisiana South System 6 Compressor Station Storage Field LNG Compressor Station Storage Field LNG Pearl River Franklinton Gwinville
7
Southern Natural Gas Pipeline Unscheduled Outage Update LA MS AL GA FL Enterprise White Castle Bear Creek Muldon Chattanooga Atlanta Thomaston Albany Elba SC Aiken Elba Express 7 Compressor Station Storage Field LNG Compressor Station Storage Field LNG Pearl River Franklinton Gwinville 20” Duck Lake – Franklinton Line Anomaly repairs under way return to service unknown Cap reduced up 65 MMcf/d
8
SNG North System Maintenance Review July/August & Sept LA MS AL GA Logansport Bienville Bear Creek Storage Onward Pickens Rankin Louisville Muldon Storage Reform McConnells Providence Tarrant Pell City DeArmanville Bell Mills Rome Compressor Station Storage Field Compressor Station Storage Field Huntsville Chattanooga Atlanta 8 Southern will be conducting other general maintenance during this period Bear Creek 1 unit down until mid August Muldon field outage starting 7/22/13 to 7/26/13 and 7/29/13 to 8/2/13 Storage restrictions Receipt cuts on North system possible Pressure Test 2 nd North Main East of Louisville 9/12/13 thru 10/8/13 North system receipts may be reduced Muldon inj & w/d may be limited
9
SNG South System Maintenance Review July/August and Sept MS AL GA Enterprise Gwinville Selma Auburn Ellerslie Thomaston Ocmulgee Hallgate Wrens Elmore York Gallion Bay Springs Compressor Station Storage Field LNG Compressor Station Storage Field LNG Atlanta Elba Hartwell Elba Express Aiken Holy Trinity Albany Pavo 9 Brookman Riceboro Pressure Test on the 24” 2 nd South Main Loop thru 7/31/13 Cap reduced up to 125 MMcf/d Southern will be conducting other general maintenance during this period Maintenance on the 8” Demopolis Line thru 7/25/13 (M) 801400 Demopolis #1 (M) 801900 Citadel Cement Auburn unit maintenance thru 8/7/13 Enterprise Station Outage until sometime in October Rose Hill (M) 504002 Cap reduced up to 400 MMcf/d Rose Hill (504001 and 504002) Station shut-in 7/29/13 until early September. Pipeline relocation work related to DOT highway relocation 7-29-13 thru 8-13-13 10-25-13 thru 11-9-13 Capacity reductions may occur Anomaly digs on the 10” mainline Pavo C/S to end of line 7/22 thru the end of August Pressure reduction could impact capacity Selma unit maintenance thru 8/7/13
10
SNG South Louisiana System Maintenance Review July/August & Sept Shadyside White Castle Franklinton Toca Gwinville LA MS Compressor Station Storage Field Compressor Station Storage Field West Leg East Leg 10 Pearl River Southern will be conducting other general maintenance during this period 20” Duck Lake – Franklinton Line Anomaly repairs under way return to service unknown Cap reduced up 65 MMcf/d
11
SNG North System Maintenance Review remainder of 2013 LA MS AL GA Logansport Bienville Bear Creek Storage Onward Pickens Rankin Louisville Muldon Storage Reform McConnells Providence Tarrant Pell City DeArmanville Bell Mills Rome Compressor Station Storage Field Compressor Station Storage Field Huntsville Chattanooga Atlanta Bear Creek Fall Shut-in Test 10/15/13 thru 10/21/13 DIQ and DWQ allocated 64% Muldon Fall Shut-in Test 10/01/13 thru 10/07/13 DIQ and DWQ allocated 36% 11 Southern will be conducting other general maintenance during this period Pressure Test 2 nd North Main East of Reform 10/13 thru 11/13 Capacity reduced significantly Impact being evaluated Pipe replacement North Main Loop Line west of Dearmanville October No Capacity reductions anticipated
12
SNG South System Maintenance Review remainder of 2013 MS AL GA Enterprise Gwinville Selma Auburn Ellerslie Thomaston Ocmulgee Hallgate Wrens Elmore York Gallion Bay Springs Compressor Station Storage Field LNG Compressor Station Storage Field LNG Atlanta Elba Hartwell Elba Express Aiken Holy Trinity Albany Pavo Enterprise Station Outage until sometime in October Rose Hill (M) 504002 Cap reduced up to 400 MMcf/d 12 Brookman Riceboro Maintenance on the 16” South Main Loop 4 weeks in October Cap reduced up to 50 MMcf/d Southern will be conducting other general maintenance during this period Selma unit maintenance In October Auburn unit maintenance In November
13
SNG South Louisiana System Maintenance Review remainder of 2013 Shadyside White Castle Franklinton Toca Gwinville LA MS Compressor Station Storage Field Compressor Station Storage Field West Leg East Leg 13 Pearl River White Castle, Shadyside Unit Maintenance Mid September - mid October Southern will be conducting other general maintenance during this period
14
Gas Control Contacts Nancy Barton – Manager (713) – 420 – 6191 (office) (713) – 204 – 4815 (cell) nancy_barton@kindermorgan.com Kalman (Kal) Dankovich – Outage Coordinator (713) – 420 – 7522 (office) (205) – 325 – 7305 (Gas Control) kalman_dankovich@kindermorgan.com Jerry Peterson – Operations Analyst (205) – 325 – 7345 (office) (205) – 325 – 7305 (Gas Control) jerry_peterson@kindermorgan.com Paul Reed – Operations Analyst (205) – 325 – 7655 (office) (205) – 325 – 7305 (Gas Control) paulr_reed@kindermorgan.com 14
15
Questions? 15