Department of Public Works Public Hearing January 9, 2012 Proposed wireless telecommunications facility at intersection of Grand Avenue at California Boulevard.

Similar presentations


Presentation on theme: "Department of Public Works Public Hearing January 9, 2012 Proposed wireless telecommunications facility at intersection of Grand Avenue at California Boulevard."— Presentation transcript:

1 Department of Public Works Public Hearing January 9, 2012 Proposed wireless telecommunications facility at intersection of Grand Avenue at California Boulevard

2 Department of Public Works 2 PROCESS Approved by Public Works – May 2, 2011 Appeal filed – May 16, 2011 Public hearing – July 11, 2011 Field meeting – July 18, 2011 Community meeting – July 27, 2011 Public hearing – November 14, 2011 Field meeting – November 19, 2011 Public hearing - December 5, 2011 Conference call with Mr. Kramer – Dec 7, 2011

3 Department of Public Works 3 COMMUNICATIONS December 7, 2011 Conference Call  Jonathan Kramer, interested public, city staff  Answered questions about Alternative 2, Alternative 7, and combination thereof  Discussed costs associated with planning/installation of facilities

4 Department of Public Works 4 SUBJECT SITE Facing north on Grand Ave. at California Blvd. 7.9” diameter by 74.1” tall Existing wood utility pole serves as guy pole No overhead power conflicts Standard radome painted to match pole

5 Department of Public Works 5 SUBJECT SITE Facing south on Grand Ave. at California Blvd. Proposed Mitigations Replace existing wood utility pole Flush mounted riser rather than standoff riser Rotated riser assembly Remove GPS unit from view

6 Department of Public Works 6 UPDATED PHOTO SIM

7 Department of Public Works 7 COVERAGE MAP - SUBJECT SITE Approximately 1,000 residences within coverage gap

8 Department of Public Works 8 TWO-SITE EVALUATION Alternative 2 - Replacement traffic signal pole at Orange Grove Boulevard and California Boulevard Alternative 7 – Replacement streetlight pole at Arroyo Boulevard and La Loma Road Alternative 2 and 7 combined

9 Department of Public Works 9 ALTERNATIVE 2 Orange Grove Blvd. and California Blvd. Existing traffic signal pole with overhead streetlight on northwest corner of intersection Requires larger radome and larger traffic signal pole

10 Department of Public Works 10 ALTERNATIVE 2 PHOTO SIM

11 Department of Public Works 11 ALTERNATIVE 7 Arroyo Boulevard and La Loma Road Existing streetlight pole on the southeast corner of the intersection. Low elevation

12 Department of Public Works 12 COVERAGE MAP (TWO-SITE) Orange Grove Blvd. at California Blvd. - 35 foot replacement traffic signal pole and non-standard radome Arroyo Blvd. at La Loma Rd. - 55 foot replacement streetlight pole with a non-standard radome

13 Department of Public Works 13 COVERAGE MAP (TWO-SITE) Orange Grove Blvd. at California Blvd. - 35 foot replacement traffic signal pole with non-standard radome Arroyo Blvd. at La Loma Rd. - 30 foot replacement streetlight pole with standard radome

14 Department of Public Works 14 STAFF FINDINGS Based on staff’s review concurred by Jonathan Kramer, it was determined that Alternate 2 would require a larger non-standard radome assembly and larger replacement traffic signal pole at Orange Grove Boulevard and California Boulevard even if two antennas were utilized Therefore, the Grand Avenue and California Boulevard location (a single-site solution) is the least intrusive means to provide improved cell service in the coverage gap

15 Department of Public Works 15 STAFF RECOMMENDATIONS Deny appeal and approve application to allow installation of a wireless telecommunications facility on top of wood utility pole at northeast corner of Grand Avenue and California Boulevard with following mitigations:  T-Mobile will replace existing utility pole at its expense with a new pole in same location installed by Pasadena Water and Power  Rotating and flush mounting riser assembly and eliminating global positioning system unit to reduce visual impact


Download ppt "Department of Public Works Public Hearing January 9, 2012 Proposed wireless telecommunications facility at intersection of Grand Avenue at California Boulevard."