Science Research Laboratories (formerly PSL and LSL) 23,111 GSF $24 million Total Project Cost (PUF and RFS) November 2010 Completion 1
2
2 Science Research Laboratories (formerly PSL and LSL) 23,111 GSF $24 million Total Project Cost (PUF and RFS) November 2010 Operational Occupancy
3
3 Science Research Laboratories
4
UTSA The University of Texas at San Antonio Office of Facilities North Paseo Office BuildingStudent Housing Sculpture & Ceramics East Garage 4 Science Research Labs
5
5 Science Research Laboratories
6
6
7
30 Science Research Laboratories
8
Graduate Sculpture and Ceramics Building 13,500 GSF $3.2 million Total Project Cost Spring 2011 Completion 8
9
Existing Campus Plan 9
10
10
11
Graduate Sculpture and Ceramics Building 11
12
North Paseo Building 76,000 GSF $15.25 million Total Project Cost Summer 2011 Completion 12
13
13 Vicinity Map Loop 1604 UTSA BOULEVARD PROJECT LOCATION BABCOCK ROAD TRUE NORTH VALERO WAY
14
Master Plan 14
15
North Paseo Building – Army & Air Force ROTC – Teacher Education Student Service – Vice Provost for Academic and Faculty Support – Vice Provost for Accountability and Institutional Effectiveness – Vice Provost for Undergraduate Studies – Vice Provost for Graduate College – Senior Associate Vice President for Research Development – Senior Associate Vice President for Research Administration – Writing Core Program – Library Technical Services – Internal Review Board – Research Integrity and Compliance – Contracts and Industrial Agreements – Sponsored Programs – McNair Scholars Program 15
16
16 Site Plan FRED COOK NORTH GARAGE NORTH PASEO PARKING LOT 2 NORTH THERMAL ENERGY PLANT LAUREL VILLAGE PARKING LOT 3 TRUE NORTH HUMANITIES & SOCIAL SCIENCES BUILDING FUTURE ROAD
17
17 Site Plan FRED COOK NORTH GARAGE NORTH PASEO PARKING LOT 2 NORTH THERMAL ENERGY PLANT LAUREL VILLAGE PARKING LOT 3 TRUE NORTH HUMANITIES & SOCIAL SCIENCES BUILDING FUTURE ROAD PEDESTRIAN AND VEHICLE SAFETY PLAN Fred Cook will be closed beginning Monday November 22 and re-opened December 30. NO ACCESS TUESDAY NOVEMBER 23. A Safety Plan has been developed and coordinated with affected departments. The Safety Plan and other project information was discussed at a Town Hall meeting Wednesday November 3.
18
18
19
19
20
20 View from Northwest
21
East Parking Garage 1200 Car Garage with Parking Office, Coffee Kiosk, and Spirit Shop $30 million Total Project Cost Begin Construction: March 1, 2011 Complete Construction: Summer 2012 21
22
Existing Campus Plan 22
23
Master Plan 23
24
24
25
25
26
03/11: Notice to proceed with construction issued John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. 2
27
03/11: North portion of Parking Lot 4 is closed for construction staging area 3 Construction Staging Area John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Staging Area
28
03/11: Road to provide construction access to project site is constructed Access to Lot 4 will be opened from the south 4 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South
29
05/11: An additional portion of Parking Lot 4 is closed through 08/11 for parking lot modifications 6 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South Parking Lot Modifications
30
06/11: Peace Boulevard is closed to the Main Building for utilities work through 07/11 7 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South Parking Lot Modifications Utility Work
31
08/11: Peace Boulevard is reopened to the Main Building 8 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Parking Lot Modifications Construction Access Road Construction Staging Area Access from South
32
09/11: Portion of Parking Lot 4 adjacent to the Main Building is reopened 9 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South
33
12/11 (?): Portion of Parking Lot 4 adjacent to the Main Building is closed to construct bridge to the Main Building 10 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South Bridge Construction
34
01/12 (?): Portion of Parking Lot 4 adjacent to the Main Building is reopened 11 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South
35
08/12: Garage and Campus Loop Road complete Garage, Parking Lot 4 and Campus Loop Road are operational. 12 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Campus Loop Road Parking Lot 4
36
During Construction Green = Reserved Spaces Gray = F/S A Spaces Yellow = F/S B Spaces Orange = Commuter Spaces Blue = Disabled Spaces 18
37
37 East Parking Garage
38
38 East Parking Garage
39
Student Housing 600 Bed (approximately) $40 million Total Project Cost Begin Construction: August 1, 2011 Complete Construction: Summer 2013 UTSA Facilities Planning and Development Conceptual Representation 39
40
Existing Campus Plan 40
41
Master Plan 41
45
Athletics Complex Phase 1 Soccer, Track, Utilities, Road, Parking $22 million Total Project Cost Summer 2013 Completion 45
46
46
47
Institutionally-Managed Projects Student Affairs (27)$7,192,644 Academic Affairs (36)$10,052,638 Business Affairs (34)$8,249,142 Community Services (18)$3,059,824 Research (5)$536,460 Projects in planning and closeout are not included above 120 PROJECTS TOTALING:$29,090,708 47