Science Research Laboratories (formerly PSL and LSL) 23,111 GSF $24 million Total Project Cost (PUF and RFS) November 2010 Completion 1.

Similar presentations


Presentation on theme: "Science Research Laboratories (formerly PSL and LSL) 23,111 GSF $24 million Total Project Cost (PUF and RFS) November 2010 Completion 1."— Presentation transcript:

1 Science Research Laboratories (formerly PSL and LSL) 23,111 GSF $24 million Total Project Cost (PUF and RFS) November 2010 Completion 1

2 2 Science Research Laboratories (formerly PSL and LSL) 23,111 GSF $24 million Total Project Cost (PUF and RFS) November 2010 Operational Occupancy

3 3 Science Research Laboratories

4 UTSA The University of Texas at San Antonio Office of Facilities North Paseo Office BuildingStudent Housing Sculpture & Ceramics East Garage 4 Science Research Labs

5 5 Science Research Laboratories

6 6

7 30 Science Research Laboratories

8 Graduate Sculpture and Ceramics Building 13,500 GSF $3.2 million Total Project Cost Spring 2011 Completion 8

9 Existing Campus Plan 9

10 10

11 Graduate Sculpture and Ceramics Building 11

12 North Paseo Building 76,000 GSF $15.25 million Total Project Cost Summer 2011 Completion 12

13 13 Vicinity Map Loop 1604 UTSA BOULEVARD PROJECT LOCATION BABCOCK ROAD TRUE NORTH VALERO WAY

14 Master Plan 14

15 North Paseo Building – Army & Air Force ROTC – Teacher Education Student Service – Vice Provost for Academic and Faculty Support – Vice Provost for Accountability and Institutional Effectiveness – Vice Provost for Undergraduate Studies – Vice Provost for Graduate College – Senior Associate Vice President for Research Development – Senior Associate Vice President for Research Administration – Writing Core Program – Library Technical Services – Internal Review Board – Research Integrity and Compliance – Contracts and Industrial Agreements – Sponsored Programs – McNair Scholars Program 15

16 16 Site Plan FRED COOK NORTH GARAGE NORTH PASEO PARKING LOT 2 NORTH THERMAL ENERGY PLANT LAUREL VILLAGE PARKING LOT 3 TRUE NORTH HUMANITIES & SOCIAL SCIENCES BUILDING FUTURE ROAD

17 17 Site Plan FRED COOK NORTH GARAGE NORTH PASEO PARKING LOT 2 NORTH THERMAL ENERGY PLANT LAUREL VILLAGE PARKING LOT 3 TRUE NORTH HUMANITIES & SOCIAL SCIENCES BUILDING FUTURE ROAD PEDESTRIAN AND VEHICLE SAFETY PLAN Fred Cook will be closed beginning Monday November 22 and re-opened December 30. NO ACCESS TUESDAY NOVEMBER 23. A Safety Plan has been developed and coordinated with affected departments. The Safety Plan and other project information was discussed at a Town Hall meeting Wednesday November 3.

18 18

19 19

20 20 View from Northwest

21 East Parking Garage 1200 Car Garage with Parking Office, Coffee Kiosk, and Spirit Shop $30 million Total Project Cost Begin Construction: March 1, 2011 Complete Construction: Summer 2012 21

22 Existing Campus Plan 22

23 Master Plan 23

24 24

25 25

26 03/11: Notice to proceed with construction issued John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. 2

27 03/11: North portion of Parking Lot 4 is closed for construction staging area 3 Construction Staging Area John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Staging Area

28 03/11: Road to provide construction access to project site is constructed Access to Lot 4 will be opened from the south 4 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South

29 05/11: An additional portion of Parking Lot 4 is closed through 08/11 for parking lot modifications 6 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South Parking Lot Modifications

30 06/11: Peace Boulevard is closed to the Main Building for utilities work through 07/11 7 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South Parking Lot Modifications Utility Work

31 08/11: Peace Boulevard is reopened to the Main Building 8 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Parking Lot Modifications Construction Access Road Construction Staging Area Access from South

32 09/11: Portion of Parking Lot 4 adjacent to the Main Building is reopened 9 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South

33 12/11 (?): Portion of Parking Lot 4 adjacent to the Main Building is closed to construct bridge to the Main Building 10 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South Bridge Construction

34 01/12 (?): Portion of Parking Lot 4 adjacent to the Main Building is reopened 11 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Construction Access Road Construction Staging Area Access from South

35 08/12: Garage and Campus Loop Road complete Garage, Parking Lot 4 and Campus Loop Road are operational. 12 John Peace Library North Garage Business Building Main Building Humanities & Social Sciences North Paseo East Garage Tobin Ave. 1604 Peace Peace Blvd. Campus Loop Road Parking Lot 4

36 During Construction Green = Reserved Spaces Gray = F/S A Spaces Yellow = F/S B Spaces Orange = Commuter Spaces Blue = Disabled Spaces 18

37 37 East Parking Garage

38 38 East Parking Garage

39 Student Housing 600 Bed (approximately) $40 million Total Project Cost Begin Construction: August 1, 2011 Complete Construction: Summer 2013 UTSA Facilities Planning and Development Conceptual Representation 39

40 Existing Campus Plan 40

41 Master Plan 41

42

43

44

45 Athletics Complex Phase 1 Soccer, Track, Utilities, Road, Parking $22 million Total Project Cost Summer 2013 Completion 45

46 46

47 Institutionally-Managed Projects Student Affairs (27)$7,192,644 Academic Affairs (36)$10,052,638 Business Affairs (34)$8,249,142 Community Services (18)$3,059,824 Research (5)$536,460 Projects in planning and closeout are not included above 120 PROJECTS TOTALING:$29,090,708 47

48 Questions? 48


Download ppt "Science Research Laboratories (formerly PSL and LSL) 23,111 GSF $24 million Total Project Cost (PUF and RFS) November 2010 Completion 1."