810 Mission Avenue 3 rd Floor Refurbishment October 17, 2013 Related to Agenda Item 14
2
2 Background Minor Renovation of 3 rd Floor Accommodate current and anticipated space needs for next five years Work Summary Replace carpet Repair damaged walls and ceiling tiles Add two walls and repaint all walls Repair lighting lens and tubes Purchase needed furniture after exhausting current inventory
3
3 Project Budget Engineer’s estimate for 3 rd Floor Renovation –$250,000 ($228,00 + $22,000 contingency) Estimate for furniture –$200,000 Total Cost $450,000
4
4 Milestones IFB SolicitationOct 2013 Order FurnitureOct 2013 Begin constructionNov 2013 End constructionJan 2014 Furniture installFeb 2014 Move staffMar 2014
5
5 Staff Recommendation Staff recommends that the Board authorize the Executive Director to make contract awards for two IFB’s not-to- exceed a combined total of $450,000 for: 1) construction contract for the refurbishment of the 810 Mission Avenue third floor and 2) purchase of office furniture to meet the District’s furniture needs.
6
6 Questions?