Presentation is loading. Please wait.

Presentation is loading. Please wait.

Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and.

Similar presentations


Presentation on theme: "Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and."— Presentation transcript:

1 Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and Coordination Janet Starnes, Principal Project Manager Office of Everglades Policy and Coordination Big Cypress Basin Board Meeting February 17, 2012

2 Picayune Strand Restoration Project Background, Issues and Needs  279 miles of roads and 48 miles of canals constructed on 55,000 acres by private developer in late ’60s  Resulted in over-drainage of northern and southern Golden Gate Estates  Caused extreme flows to estuaries, affecting salinity and marine habitat  Resulted in drier conditions inland  Expansion of invasive plant species such as Cabbage Palm and Brazilian Pepper  Loss of Cypress forests  Plant species changed, quality of animal habitat declined

3 Historic Flowways

4 Missing Piece of the Puzzle Collier Seminole State Park Everglades National Park Big Cypress National Preserve Urban Development Southern Golden Gate Estates Rookery Bay National Estuarine Research Preserve Fakahatchee Strand State Preserve Picayune Strand State Forrest Florida Panther National Wildlife Refuge 10,000 Islands National Wildlife Refuge  Restores ecological connectivity between publicly owned lands

5 Alternatives Considered  20+ alternatives initially formulated  Three alternatives warranted further evaluation  Alternative #6  Alternative #12  Alternative #3D  “No Action” alternative also considered

6 U.S 41 6L Boundary Restoration Plan 3 Spreader Canals 3 Pump Stations Canal Plugs Primary Roads Secondary Roads Private Lands Boundaries Berm N I-75 Management Roads 810 cfs 2650 cfs Private Lands Boundary POI Boundary MILLER CANAL FAKA UNION CANAL MERRITT CANAL PRAIRIE CANAL 1250 cfs U.S. 41 Drainage Enhancement Tie-Back Levee Elements

7 Summary of Benefits  Restores freshwater flows to estuaries  Restores upland/wetland habitat in watershed  Restores pre-drainage watershed flow pattern to a sheet flow condition  Increases groundwater levels  Restores habitat for endangered/threatened species (Florida panther, woodstork, etc.)  Provides for better fire management

8 Picayune Strand - Phase 1  Seven miles of Prairie Canal filled  65 miles of roadway removed  17 culverts constructed to restore natural sheet flow  More than 13,000 acres of restored and enhanced habitat  U. S. Army Corps of Engineers constructing remaining features

9 Prairie Canal Plugging – Phase I One year after plugging of Prairie Canal

10 Phase I - Road Removal Extent of vegetation removal and road degrading Natural regeneration two years after degrading

11 Prairie Canal Plugging – Phase I January 2009 Summer 2008

12 Merritt Pump Station  810 cubic feet per second capacity  Smallest of the three PSRP pump stations  Located approximately two miles south of I-75

13 Merritt Pump Station (Cont.) October 2010September 2011

14 Phase II - Road Removal  Area of construction is from the eastern bank of the Faka Union Canal to the western bank of the Merritt Canal  Degrade ~95 miles of roads

15 Phase II – Road Removal Example of Degraded Road

16 Faka Union Pump Station  2625 cubic feet per second capacity  Largest of the three PSRP pump stations  Located approximately three miles south of I-75

17 Faka Union Pump Station (cont.) Faka Union Pump Station Foundation January 2012

18 Phase III - Road Removal  Area of construction is from the eastern bank of the Miller Canal to the western bank of the Faka Union Canal  Degrade ~100 miles of roads

19 Remaining Work To Be Contracted  Miller Pump Station and Phase IV Road Removal  Construction scheduled to begin in Fall 2013  Three year construction time frame  Includes protection features for “Private Lands”  Protection Features  Port of the Islands - Construction scheduled to begin in Fall 2013  6Ls/US41 - Construction scheduled to begin in Fall 2015

20 Questions?


Download ppt "Comprehensive Everglades Restoration Plan Picayune Strand Restoration Project Janet Starnes, Principal Project Manager Office of Everglades Policy and."

Similar presentations


Ads by Google