Download presentation
Presentation is loading. Please wait.
Published byNaomi Porter Modified over 9 years ago
1
SORCER Coordinators meeting. November 14, 2011
2
SORCER Stimulating Obtaining Results in Communities in relation to Energy- efficiency and Renewables Integrated Project Call FP6-2005-TREN-4 CONCERTO II Contract nr: TREN/07/FP6EN/S07.70576/038588 SORCER
3
SORCER consortium WV Univ. Wroclav AM Wonen Util. Hillerød Skoroszyce Rotij Mun. Apeldoorn COWI IVAM Plovdiv HREN Essent KEMA Weiss Mun. Hillerød DTU
4
Partner list (1) Particip ant. Role* Participa nt. Number Participant nameParticipant short name Country CO 1 KEMA Nederland B.V.KEMANL CR2 Waterschap VeluweWVNL CR3 Essent Warmte B.V.EssentNL CR4 Gemeente ApeldoornMun. Apeldoorn NL CR5 IVAM UvA B.V.IVAMNL CR6 Rotij Projecten B.V.RotijNL CR7 AM Wonen B.V.AMNL CR8 S.C. HREN Practic S.R.L.HRENRO
5
Partner list (2) CR9 Urzad Gminy SkoroszyceSkoroscycePL CR10 University of WroclavUWroclavPL CR11 Municipality of PlovdivPlovdivBU CR12 COWI A/SCOWIDK CR13 Municipality of HillerødMun.HillerødDK CR14 Hillerød Public UtilityUtil.HillerødDK CR15 Weiss A/SWeissDK CR16 Technical University of Denmark DTUDK
6
Consortium, geographic distribution
7
Sorcer content Apeldoorn Sewage digester, with poultry sludge (1.5 MWe) District heating Zuidbroek (2500 dwellings) EPC (shell based) of 0.8 2.65 GJ/dwelling*year additional energy saving (e.g. 400 Wp PV/dwelling) Woodchips peak boiler Hillerød Low temperature district heating Solar collectors 6000 m2 Class 1 Ecobuildings (-50%) 20000 m2 Class 2 Ecobuildings (-25%) Biomass gasifier Renovated buildings PV
8
Apeldoorn Zuidbroek
9
Zuidbroek energy system +PV + Energy efficient dwellings
10
Zuidbroek 54 months highlights About 800 dwellings delivered Biogas CHP complete PV grant setup for developers and house owners complete, about 50 kWp done, agreements on about 40 kWp, preliminary agreement on 135 kWp for housing corporations Successful congress in Apeldoorn Monitoring gives valuable results both for dwellings as for district heating system (Temporary) Permit for 2.8 MW woodchips boiler (construction can start)
11
Apeldoorn Zuidbroek energy system
12
Hillerød
13
Hillerød energy system
14
Hillerød 54 months highlights 3000 m2 solar thermal field complete Biomass boiler finished and in operation Class 1 buildings completed New buildings added to WP8. These include town hall, city college, office administration building, conference centre, dormitory 1500 m2 of low energy class 2 buildings reporting measurements PV plants on Town Hall, Klaverfabrikken, Hillerød Varme head quarter completed Gasifier under construction Control of low temperature district heating nearly implemented
15
Yet to do Complete PV plans in Zuidbroek and Hillerød Complete refurbishment activities in Hillerød Energy efficient street lighting Complete woodchips boiler and municipal building in Apeldoorn Monitoring Extension to 6 years has been asked
16
Progress summary
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.