Download presentation
Presentation is loading. Please wait.
Published byMadlyn Anissa Atkins Modified over 9 years ago
1
Steve Krebs, Bob Arndorfer, and Jed Peters – DTSD-Bureau of Technical Services April 29, 2013
2
Literature Review Current Design Practices Pavement Performance Observations Full Depth Shoulder (FDS) Construction and Cost Considerations FDS Life Cycle and Benefit-Cost Analyses Benefits Recommendations/Implementation Costs 2
3
Design Standards 1990 FHWA Advisory Mechanistic-Empirical Pavement Design Guide Wisconsin Highway Research Program (WHRP) Report FDS Benefits Construction Maintenance of Traffic Incidents/Events Emergency Evacuations Other State Practices 3
4
Geometry Thickness 4
5
Pavement Distress NE Region SE Region NW Region Preventative Measures 5
6
10 Projects Analyzed 8 Concrete Mainline 2 HMA Mainline As-built and Estimated FDS Costs 6
7
7
8
8
9
9
10
Concrete Mainline Projects As-built average (avg) cost: $182,920/mile FDS HMA avg cost: $346,430/mile FDS concrete avg cost: $265,000/mile HMA Mainline Projects As-built average (avg) cost: $123,320/mile FDS HMA avg cost: $171,600/mile 10
11
Costs/Impacts not Considered Maintenance Schedules Conventional FDS Time Value of Money 11
12
Concrete Mainline Projects As-built avg net present value (NPV) life-cycle 50 year cost: $276,720/mile FDS HMA avg NPV life-cycle 50 year cost : $428,310/mile FDS concrete avg NPV life-cycle 50 year cost : $345,140/mile HMA Mainline Projects As-built avg NPV life-cycle 50 year cost : $198,050/mile FDS HMA avg NPV life-cycle 50 year cost : $243,210/mile * NPV calculated with 3.5% discount rate 12
13
13 SplitAxisLCCA Cash Flow Split Axis LCCA Cash Flow
14
LCCA vs BCA Dissimilar Alternative: User Delay Conventional Shoulder User Delay NPV = $146,830/mile 14
15
Concrete Mainline Projects As-built avg NPV life-cycle 50 year cost: $423,550/mile FDS HMA avg NPV life-cycle 50 year cost : $428,310/mile FDS concrete avg NPV life-cycle 50 year cost : $345,140/mile HMA Mainline Projects As-built avg NPV life-cycle 50 year cost : $344,880/mile FDS HMA avg NPV life-cycle 50 year cost : $243,210/mile * NPV calculated with 3.5% discount rate 15
16
Non-Denominated IH-43 IH-94 Denominated IH-39 – Shoulder Replacement IH-94 – Shoulder Widening USH 41 – Shoulder Widening 16
17
Estimated As-Built Construction Cost/Mile $151,570/mile (1984 Dollars) $337,550/mile (2012 Dollars) Estimated 10” FDS Construction Cost/Mile $190,840/mile (1984 Dollars) $425,010/mile (2012 Dollars) LCCA Costs As-built NPV = $456,110/mile FDS NPV = $535,720/mile 2012 Project - 8” Shoulders Let Cost/Mile $333,850/mile 17
18
Adjusted LCCA Costs As-built NPV = $515,000/mile FDS NPV = $467,540/mile 18
19
19
20
20
21
21
22
Actual Widening Cost = $7.28 Million Estimated Widening Cost with Incorporation of FDS = $5.17 Million Cost Savings of $272,000/mile 22
23
Actual Widening Cost = $3.99 Million Estimated Widening Cost with Incorporation of FDS = $3.07 Million Cost Savings of $178,000/mile 23
24
Selective Application of FDS High Volume Arterial Corridors Mass Evacuation Routes Incorporate FDS (Existing and Future) into Emergency Planning 24
25
25 Volumes Estimated For Highest Direction in 30 th Highest Hour in 2013
26
Average Outside FDS Cost: $248,575/mile Average Inside FDS Cost: $165,480/mile HMA Conventional Shoulder to Concrete FDS Outside shoulder only: additional $108,100/mile Both shoulders: additional $164,000/mile Concrete Conventional Shoulder to Concrete FDS Outside shoulder only: savings of $28,800/mile Both shoulders: savings of $41,500/mile 26
27
Southeast N-S and Zoo Freeways Southwest IH-39 Corridor Reconstruction Northeast USH 41 (Winnebago and Brown Counties) 27
28
28
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.