Download presentation
1
Review of Helium Venting Analyses
Chris Tutt AMS-02 Project Manager Chris Tutt AMS-02 Phase II Safety Review
2
AMS-02 Phase II Safety Review
Review of Hazard Hazard to be addressed is release of asphyxiant gas into an occupied area. Three major helium reservoirs within AMS-02 payload and GSE. 2500-liter main helium dewar inside the payload. 1000-liter master dewar used for filling main dewar. 1000-liter transfer dewar used for filling master dewar. Venting analysis focused on main dewar as enveloping case, but results for all others are similar. Chris Tutt AMS-02 Phase II Safety Review
3
AMS-02 Phase II Safety Review
Main Helium Dewar Main Helium Dewar has two major components Helium Tank contains the cryogen itself Vacuum Case provides vacuum space around the tank. 3 bar burst disk on helium tank defines the Maximum Design Pressure for the system. Nominal operating pressure is ~16 mbar. All hardware will be extensively tested prior to arrival at KSC. Structural analysis shows high margins for MDP. All welds will be inspected per MSFC-STD-504C. Both items will be proof pressure tested. Both items will be vacuum leak tested. Chris Tutt AMS-02 Phase II Safety Review
4
AMS-02 Phase II Safety Review
Main Helium Tank Chris Tutt AMS-02 Phase II Safety Review
5
AMS-02 Phase II Safety Review
Vacuum Case Chris Tutt AMS-02 Phase II Safety Review
6
AMS-02 Phase II Safety Review
GSE Dewars Chris Tutt AMS-02 Phase II Safety Review
7
Tank Overpressurization
Two mechanisms for overpressurization of tank. Failure to remove nominal boil-off from tank. Large external heat source increases boil-off beyond pump’s capability to remove. First scenario requires weeks to reach burst pressure, so does not present safety hazard. Only possible heat source for second scenario is ambient atmosphere and requires air leak into the dewar vacuum space. Chris Tutt AMS-02 Phase II Safety Review
8
AMS-02 Phase II Safety Review
Cause of Leak Two leak scenarios were considered in analysis Loss of Vacuum (LOV) – Total loss of vacuum caused by large breach of Vacuum Case. Requires major accident: Forklift tine breaks through VC outer cylinder Payload dropped during lifting operations Large hardware falls on payload from significant height. Maximum Credible Leak (MCL) – 3” leak through the double O-Ring seals in the VC upper and lower support rings. Leak size defined by Payload Safety Review Panel and used for all payload bay leak analyses. LOV can be prevented operationally, so following discussion will focus on MCL. Chris Tutt AMS-02 Phase II Safety Review
9
AMS-02 Phase II Safety Review
VC O-Ring Seals Chris Tutt AMS-02 Phase II Safety Review
10
AMS-02 Phase II Safety Review
CONICAL FLANGE SUPPORT RING O-RING TEST PORT VACUUM SPACE INTERFACE PLATE Each sealing surface has double O-ring seals. In MCL, both seals are assumed to have failed in the same location. OUTER CYLINDER Chris Tutt AMS-02 Phase II Safety Review
11
AMS-02 Phase II Safety Review
MCL Defined Leak Size Chris Tutt AMS-02 Phase II Safety Review
12
Venting Analysis Overview
Venting Analysis consists of three basic steps Calculation of time required for tank to reach 3 bar burst pressure after leak begins. Calculation of mass rate of flow of helium leaving the main tank. Calculation of oxygen levels in surrounding external space. Only the third step is location dependent. Chris Tutt AMS-02 Phase II Safety Review
13
AMS-02 Phase II Safety Review
Time to Burst Pre-burst pressure rise modeled as isochoric heating. Heat flux from MCL calculated to be W. Helium thermodynamic properties from NIST handbook. Results driven by initial temperature and fill level. Calculated times range from 54 min (1.9K, 95% full) to 86 min (1.7K, 80% full). Chris Tutt AMS-02 Phase II Safety Review
14
Typical Pressure Rise Profile
Chris Tutt AMS-02 Phase II Safety Review
15
AMS-02 Phase II Safety Review
Time to Empty Tank Mass flow out of the tank modeled as isentropic expansion through choked nozzle. Results driven entirely by fill level. The more helium in the tank, the longer it takes to empty. Below 90% full, helium becomes two-phase prior to reaching 1 atm. Calculated times range from 131 min after burst (80% full) to 239 min (95% full). Chris Tutt AMS-02 Phase II Safety Review
16
Typical Mass Flow Profile
Chris Tutt AMS-02 Phase II Safety Review
17
AMS-02 Phase II Safety Review
Exterior Volume Analysis done for four KSC spaces Space Shuttle Processing Facility Canister Rotation Facility Canister Payload Changeout Room Results driven by three factors Volume of external space Air refreshment rate Gas diffusion model Chris Tutt AMS-02 Phase II Safety Review
18
Original Gas Diffusion Assumption
Original discussions assumed that helium vapor would rise to the ceiling of external volume. Chris Tutt AMS-02 Phase II Safety Review
19
Current Gas Diffusion Assumption
At GOWG in November, GSRP requested analysis be redone assuming gas spreads evenly throughout the room. Model used GSFC algorithm provided by SHOOT team. Based on helium sensors measurements from Tevatron accident at Fermilab. Venting memo describes results using second assumption. Chris Tutt AMS-02 Phase II Safety Review
20
AMS-02 Phase II Safety Review
GSFC Algorithm Incoming Air Ventilation Exhaust Incoming Helium Helium enters control volume at R m3/s. Ambient air removed by ventilation system at Q m3/s. Chris Tutt AMS-02 Phase II Safety Review
21
Oxygen Concentration Levels in PCR
Chris Tutt AMS-02 Phase II Safety Review
22
Oxygen Concentration Levels in Canister
Chris Tutt AMS-02 Phase II Safety Review
23
Oxygen Concentration Levels in SSPF
Chris Tutt AMS-02 Phase II Safety Review
24
Oxygen Concentration Levels in CRF
Chris Tutt AMS-02 Phase II Safety Review
25
AMS-02 Phase II Safety Review
Overall Trends PCR falls briefly below 19.5%, but high ventilation rate allows rapid return to safe levels. Canister’s small volume can be rapidly overwhelmed, but is not normally a manned volume when door is shut. SSPF/CRF volumes are large enough and ventilation rates are fast enough that oxygen level never falls below 19.5%. Chris Tutt AMS-02 Phase II Safety Review
26
Proposed Safety Controls
GSE should be monitored for signs of temperature or pressure rise while AMS-02 is in manned area. If leak observed, personnel should be removed from vulnerable areas. Entire PCR Elevated structures within SSPF and CRF Oxygen sensors should be used to determine safety of atmosphere prior to reentering any area after venting event or opening Canister in the PCR. Additonal vent lines and building modifications should not be necessary. Chris Tutt AMS-02 Phase II Safety Review
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.