1
The RPC Closed loop Gas System
2
Schedule for completion - update Status Supplier: ok Mixer: ok Humidifier: ok Purifiers: installed, but not completely commissioned Pre-distribution and pump: ok Final distribution:ok (minor detail to fix) Pressure Transmitter on the detector: few sensors are missing Status Supplier: ok Mixer: ok Humidifier: ok Purifiers: installed, but not completely commissioned Pre-distribution and pump: ok Final distribution:ok (minor detail to fix) Pressure Transmitter on the detector: few sensors are missing
3
Commissioning strategy Phase 0: leak test Leak test of the main pipes form SG to USC and from USC and UXC. Phase 1: debug of circuit In all racks, the two supply lines for the upper half-wheel and the bottom half-wheel are swapped. Same for the return line. Problem fixed for W+2 and W+1 (the pipe is flexible). For RE+1, RE+2, RE+3 the pipe are rigid and CRIOTEC will fix the problem this week. Also warn to CRIOTEC to avoid the same problem for the negative wheels and endcaps. Flushed for few days with argon the gas distribution racks for W+2, W+1. First check of the flow-cell calibration done. Phase 0: leak test Leak test of the main pipes form SG to USC and from USC and UXC. Phase 1: debug of circuit In all racks, the two supply lines for the upper half-wheel and the bottom half-wheel are swapped. Same for the return line. Problem fixed for W+2 and W+1 (the pipe is flexible). For RE+1, RE+2, RE+3 the pipe are rigid and CRIOTEC will fix the problem this week. Also warn to CRIOTEC to avoid the same problem for the negative wheels and endcaps. Flushed for few days with argon the gas distribution racks for W+2, W+1. First check of the flow-cell calibration done.
4
Phase 2: debug gas rack distribution System (up to purifiers, purifiers excluded) flushed with R134a and run in closed loop mode to check both the full system and the flow-cell calibration. At the moment only W+1 rack under test (W+2 and W0 in the the Global Run). As soon as the gas connection in RE+1,+2,+3 are ready we will proceed with these racks. The same will be for W+2 and W0 after the Global Run. Phase 3: final commissioning Inject the RPC mixture and start final commissioning (expected in two weeks). Still some work to be done: Electrical inspection in SGX5 Detection heads Close holes between rooms in SGX5 SGX5 Zone declaration and final ok Start heating of supply room Repairs of isobutane and Freon supply panels IR mixture analyzer still under test (almost ready to be installed) Finally, RPC operation with high percentage of fresh mixture (from 50% to 30%) Phase 2: debug gas rack distribution System (up to purifiers, purifiers excluded) flushed with R134a and run in closed loop mode to check both the full system and the flow-cell calibration. At the moment only W+1 rack under test (W+2 and W0 in the the Global Run). As soon as the gas connection in RE+1,+2,+3 are ready we will proceed with these racks. The same will be for W+2 and W0 after the Global Run. Phase 3: final commissioning Inject the RPC mixture and start final commissioning (expected in two weeks). Still some work to be done: Electrical inspection in SGX5 Detection heads Close holes between rooms in SGX5 SGX5 Zone declaration and final ok Start heating of supply room Repairs of isobutane and Freon supply panels IR mixture analyzer still under test (almost ready to be installed) Finally, RPC operation with high percentage of fresh mixture (from 50% to 30%) Commissioning strategy
5
The RPC gas system needs pressure sensors on the detector: Two sensors per wheel / disk They have to be in the highest point of each half-wheel / half disk RPC gas rack P sens. for bottom half-wheel P sens. for upper half-wheel upper half-wheel Bottom half-wheel Cables for P sens. Pressure sensors on the detector
6
ISR - Test in progress Open issues Purification cycle Effectiveness of the purification Fresh mixture percentage needed Stability of the system Open issues Purification cycle Effectiveness of the purification Fresh mixture percentage needed Stability of the system The ISR lab has been converted to a site for the closed loop study Few gaps equivalent to 5 RPCs under test with a closed loop prototype system. 10 new Single Gap will be connected this week All the detectors are inside a hut with temperature and humidity kept at controlled values The mixture composition and quality are continuously monitored by means of a gas chromatograph The new gas-chromatograph and mass-spectrometer (CERN Gas Group) will be connected to the pick-up lines this week. The ISR lab has been converted to a site for the closed loop study Few gaps equivalent to 5 RPCs under test with a closed loop prototype system. 10 new Single Gap will be connected this week All the detectors are inside a hut with temperature and humidity kept at controlled values The mixture composition and quality are continuously monitored by means of a gas chromatograph The new gas-chromatograph and mass-spectrometer (CERN Gas Group) will be connected to the pick-up lines this week.
7
Recent results New cycle started on July 25 th Gas flow: 1 volume/2.5 h Gas quality checked every day with a GC Mixture recycle % injection vs time System stable for about two month, but now some sign of a small increase in the currents for the gaps operated in closed loop mode New cycle started on July 25 th Gas flow: 1 volume/2.5 h Gas quality checked every day with a GC Mixture recycle % injection vs time System stable for about two month, but now some sign of a small increase in the currents for the gaps operated in closed loop mode
8
(I(t)-I(0))/I(0) open (I(t)-I(0))/I(0) closed Recent results Abnormal “air” level in the mixture (due to R134a cylinder impurity) RPCs switched off The “up” gaps are mainly affected by the small increase in the currents. Final check (10-15 days in open mode). Then switch again in closed mode with the “old” used purifiers to be sure that the increase is due the their saturation. Then regenerate the purifiers and we will start a new cycle (most probably in January). The “up” gaps are mainly affected by the small increase in the currents. Final check (10-15 days in open mode). Then switch again in closed mode with the “old” used purifiers to be sure that the increase is due the their saturation. Then regenerate the purifiers and we will start a new cycle (most probably in January).
9
More than 13 R134a cylinders analyzed since July 15 th with the Gas Chromatograph: 6 cylinders < 500 ppm vol “air” 3 cylinders ~ 4000 ppm vol “air” 4 cylinders >> 30000 ppm vol “air” (plus an unknown component) Some example (Gas chromatogram only): More than 13 R134a cylinders analyzed since July 15 th with the Gas Chromatograph: 6 cylinders < 500 ppm vol “air” 3 cylinders ~ 4000 ppm vol “air” 4 cylinders >> 30000 ppm vol “air” (plus an unknown component) Some example (Gas chromatogram only): R134a cylinder impurities “good” cylinder Very “bad” cylinder
10
Further analyses will be performed in the next weeks with the GC-MS in order to identify the unknown component (most probably an other kind of freon) R134a cylinder impurities Purged volume: “good” cylinderVery “bad” cylinder 0 m 3 ~1 m 3 Unknown component: ~3 mV ~40 mV
11
The commissioning of the final gas system is going on As usual we had/have many problems, but we are confident to start with the final mixture in 1-2 weeks In the mean time the CMS-RPC gas chromatograph will arrive and will be installed in SG5. Therefore, at the beginning of January, we will start the final commissioning of the purifiers In the closed loop test at ISR, after about two month of stability the detector currents has shown a small increase. The study is in progress in order to understand if the increase is due to the saturation of the purifiers. The new GC-MS (CERN Gas Group) will be installed at the ISR this week. It will help a lot in the understanding of the purifiers effectiveness. In one month also the new pH + Fluorine electrode station will be installed first at ISR and then in SG5. The commissioning of the final gas system is going on As usual we had/have many problems, but we are confident to start with the final mixture in 1-2 weeks In the mean time the CMS-RPC gas chromatograph will arrive and will be installed in SG5. Therefore, at the beginning of January, we will start the final commissioning of the purifiers In the closed loop test at ISR, after about two month of stability the detector currents has shown a small increase. The study is in progress in order to understand if the increase is due to the saturation of the purifiers. The new GC-MS (CERN Gas Group) will be installed at the ISR this week. It will help a lot in the understanding of the purifiers effectiveness. In one month also the new pH + Fluorine electrode station will be installed first at ISR and then in SG5. Final remarks
12
Trigger Top Up Trigger Top Down Clean Mix Up Clean Mix Down Before Mix Up Before Mix Middle Before Mix Down After Mix Down After Mix Up After Mix Middle Trigger Bottom Up STAR T IN CAEN Power Supply SY1527 System DAQ CAEN V965 16Channel Dual Range Multievent QDC 80ns delay each channel Front end electronics Low Threshold Discriminators 20ns Delay Slow Control Veto TRIGGER 3/4 Gas gain monitor Working at ISR
13
Gas gain monitor Pedestal Avalanche Streamer counts
14
Wheelstationsectorleak (ml/h)P(0) mbarP(end) mbarDt (min)leak(mbar/min) W+2RB3S0340063190.158 RB2S1133006321.500 RB3S11>14000 n.a. RB4S11>14000 n.a. W+1RB3S05>14000 n.a. RB1S09>14000 n.a. RB1S102006.53.5390.077 RB4S1053006.51.722.400 RB2S11>14000 n.a. W0RB1S013504.033.5100.050 RB3S0214004280.250 RB3S08>14000 n.a W-1RB2S10>14000 n.a. RB3S10>14000 n.a. W-2 System cannot handle the red cases (chamber does not keep any pressure). For the black cases it is possible to compensate the leak with higher flow. System cannot handle the red cases (chamber does not keep any pressure). For the black cases it is possible to compensate the leak with higher flow. The “leak” issue: summary
15
Wrong operation of gas system: W+2, W+1 chambers have high input pressure due to old impedances valves. To deal with this, the gas rack safety bubbler was changed with a safety valve set to 70 mbar (instead of 10 mbar). Possible source of incident: output of the chamber not properly connected to the rack. However this would not explain cases in W0 Gas pipe damage inside the chamber In one case (chamber already substituted in W-1 due to a large leak), found a damage pipe inside the chamber. The chambers in W-1 have broken connectors (visible from outside). Gas pipe aging Very unlikely. Polyethylene pipe used. Aging cases never reported. Wrong operation of gas system: W+2, W+1 chambers have high input pressure due to old impedances valves. To deal with this, the gas rack safety bubbler was changed with a safety valve set to 70 mbar (instead of 10 mbar). Possible source of incident: output of the chamber not properly connected to the rack. However this would not explain cases in W0 Gas pipe damage inside the chamber In one case (chamber already substituted in W-1 due to a large leak), found a damage pipe inside the chamber. The chambers in W-1 have broken connectors (visible from outside). Gas pipe aging Very unlikely. Polyethylene pipe used. Aging cases never reported. The “leak” issue: possible causes
16
Leak tests have been performed in all chambers during construction phase, after coupling to DT, before and after installation. A difference between input and output flow in some cells already observed during MTCC. However the precision of the calibration does not allow to draw conclusions. Also good performance of the chambers during MTCC and commissioning. This could lead to the conclusion that the leak is at the output. Leak tests have been performed in all chambers during construction phase, after coupling to DT, before and after installation. A difference between input and output flow in some cells already observed during MTCC. However the precision of the calibration does not allow to draw conclusions. Also good performance of the chambers during MTCC and commissioning. This could lead to the conclusion that the leak is at the output. The “leak” issue: comments and actions W+1, W+2 problematic chambers to be opened as soon as possible and replaced with new ones. All chambers ready to be replaced. W0 one chamber has a serious leak but we try to operate in open mode since no access possible to replace the chamber now. W+1, W+2 problematic chambers to be opened as soon as possible and replaced with new ones. All chambers ready to be replaced. W0 one chamber has a serious leak but we try to operate in open mode since no access possible to replace the chamber now.