1 ACCA Legislative Conference Underground Storage Tank Compliance
December 4, 2014 Lee Davis, UST Compliance adem.alabama.gov

2 UST Compliance Program Outline
UST Program Overview Regulatory Requirements 2005 Energy Act adem.alabama.gov

3 Definition of UST Tanks and Piping Contains Regulated Substances
10% or More Underground adem.alabama.gov

4 USTs adem.alabama.gov

5 Regulated Universe Regulated Facilities ~ 5,600
Regulated Tanks ~ 15,300 Number of Tank Owners ~ 3,100 adem.alabama.gov

6 Inspectors 9 UST Inspectors in 4 Field Offices
Approximately 400 inspections per inspector, per year adem.alabama.gov

7 Performance Standards USTs and Piping
Fiberglass-Plastic Construction, or Steel and Protected from Corrosion Piping Nonmetallic, or adem.alabama.gov

8 UST adem.alabama.gov

9 Piping adem.alabama.gov

10 Performance Standards Spill Prevention
To contain the volume of the delivery hose after disconnecting adem.alabama.gov

11 Spill Catchment Basin adem.alabama.gov

12 Performance Standards Overfill Prevention
Activated by product level to prevent tank overfills adem.alabama.gov

13 Overfill Prevention Flapper Valve
4 1 2 3 2 3

14 Overfill Prevention Ball Float Valve
3 2 1

15 Regulatory Requirements Testing and Reporting
Corrosion Protection Leak Detection Spill Catchment Basin Closure Suspected Releases adem.alabama.gov

16 Testing CP Test Cathodic protection test required once every three years adem.alabama.gov

17 Cathodic Protection System
adem.alabama.gov

18 Impressed Current Anode
adem.alabama.gov

19 Rectifier adem.alabama.gov

20 Galvanic Cathodic Protection System
adem.alabama.gov

21 Release Detection Tanks – must have monthly method of monitoring for releases Pressurized Piping - must have annual line test or monthly monitoring Suction Piping – No monitoring required if “safe suction” adem.alabama.gov

22 Automatic Tank Gauge adem.alabama.gov

23 Testing Leak Detection
Leak Detectors - equipment that will shut off or restrict flow of product if a leak is detected – Annual test Sump Sensors – Annual test adem.alabama.gov

24 Testing & Reporting SIR Annual Summary Report
Line Tightness Tests Annual Line Leak Detector Tests Annual Cathodic Protection Tests 3 Year Spill Catchment Basins 3 Year adem.alabama.gov

25 Reporting Closure and Releases
Permanent Closure of a UST System Suspected releases must be reported within 24 hours. Investigation and Corrective Action adem.alabama.gov

26 Suspected Release adem.alabama.gov

27 Secondary Containment Delivery Prohibition Operator Training
2005 Energy Act Secondary Containment Delivery Prohibition Operator Training adem.alabama.gov

28 Secondary Containment Effective August 6, 2007
Tank and Piping Manufactured with Inner and Outer Wall and Interstitial Space Interstitial Monitoring Only Acceptable Form of Leak Detection adem.alabama.gov

29 Submersible Pumps Effective August 6, 2007
USTs installed with submersible pumps on August 6, 2007 and thereafter, must have submersible pump containment sumps. adem.alabama.gov

30 Sub Pump Sump adem.alabama.gov

31 Under Dispenser Containment Effective August 6, 2007
New Dispenser System Includes Equipment Necessary to Connect to UST System adem.alabama.gov

32 Under Dispenser Containment
adem.alabama.gov

33 Delivery Prohibition 2005 Energy Act
Prohibition of delivery or acceptance of product for non-compliant UST facilities Penalty for owner and deliverer Regulations Effective April 25, 2008 adem.alabama.gov

34 Delivery Prohibition adem.alabama.gov

35 Delivery Prohibition Reasons
Delivery prohibition may be imposed for failure of an owner to: Install, operate and/or maintain cathodic protection, leak detection, under dispenser containment, or spill or overfill controls Ensure compatibility of UST with product Perform required testing Pay regulatory fees Take corrective action for releases adem.alabama.gov

36 Delivery Prohibition ADEM Steps
How will ADEM notify owners they are subject to delivery prohibition? Notice of Delinquency Notice of Violation Notice of Delivery Prohibition Opportunity to meet with Department adem.alabama.gov

37 Delivery Prohibition DP List
How will ADEM notify fuel delivery companies that a facility is prohibited from delivery? Delivery Prohibition List on ADEM web site Delivery Prohibition List updated every Wednesday at 12:00 a.m. adem.alabama.gov

38 Delivery Prohibition Owner Response
How can owners be removed from the Delivery Prohibition List? Return to Compliance Submittal of documentation ADEM will remove facility from list ADEM will send letter adem.alabama.gov

39 Operator Training adem.alabama.gov

40 Operator Training 2005 Energy Act
Operators must be trained by August 8, 2012. Three classes of operator adem.alabama.gov

41 UST Trust Fund Registration Motor Fuel Substantial Compliance Orders
Spill Prevention Overfill Prevention Corrosion Protection Release Detection adem.alabama.gov

42 AST Trust Fund Registration Motor Fuel SPCC Plan NPDES Permit
adem.alabama.gov

43 UST Compliance Program
I Can Answer Any Questions You May Have Now. adem.alabama.gov

44 Chief, UST Compliance Unit (334) 271-7759 mld@adem.state.al.us
Contact Information – Lee Davis Lee Davis Chief, UST Compliance Unit (334) UST Switchboard (334) adem.alabama.gov