Aw Team - summary of LS1 activities CMI Section Meeting, 16th September 2014 Anna Chrul (HNINP/CERN)

Similar presentations


Presentation on theme: "Aw Team - summary of LS1 activities CMI Section Meeting, 16th September 2014 Anna Chrul (HNINP/CERN)"— Presentation transcript:

1 aw Team - summary of LS1 activities CMI Section Meeting, 16th September 2014
Anna Chrul (HNINP/CERN)

2 II. 18th June 2014 and later… I. Short summary of LS1 activities
The Team Openings/Closures of W-bellows Safety Relief Valves (DN200) Installation Thermal Screens Upgrade M-bellows Protections Consolidation Other Activities during LS1 II. 18th June 2014 and later… 18th June 2014 – last closure Re-openings/closures of interconnections for NC treatment Other activities (June-August 2014) 2014/09/16 CMI Section Meeting

3 Short summary of LS1 activities
2014/09/16 CMI Section Meeting

4 Current status (since 1st September 2014): 2 Staff, 9 Collaborators
The Team Max. during LS1: 36 persons (4 Staff, 2 FSU, 30 Collaborators) Current status (since 1st September 2014): 2 Staff, 9 Collaborators 2014/09/16 CMI Section Meeting

5 Jose Manuel Gomes De Faria Thermal Shields Upgrade
The Team Andrea Musso Anna Chrul Jose Manuel Gomes De Faria SRV Activity Leader DUBNA Alexander Ivanov (Andrei Bazanov) DN200 Team Lali Glonti (PH-UAT) Photo Archive Alain Bastard W Opening & Closure NTUA Dimitrios Damianoglou (Kostantinos Razakias) Team 1 Team 2 Team 3 WUT Michal Strychalski (Jacek Muszynski) Graeme Barlow Thermal Shields Upgrade Adel Tebigui (FSU) Benjamin Pellet (FSU) 2014/09/16 CMI Section Meeting

6 W-bellows openings The task: 1695 ICs to open
regular openings for the train and performed in parallel special openings “on request” + additional re-openings for NC treatment Before: preparation of procedures and dedicated tooling, training on mock up in Bld.180. Andrea Musso - LSC May 17th, 2013 The team: Collaborators from NTUA, Athens, Greece Collaborators from WUT, Wroclaw, Poland Collaborators from JINR, Dubna, Russia + support of PAEC Team Activity responsible: Alain Bastard 2014/09/16 CMI Section Meeting

7 + 118 ICs to close after re-opening for NC treatment (WISH)
W-bellows closures The task: 1695 ICs to close + 118 ICs to close after re-opening for NC treatment (WISH) Quality improvement (additional check list) Quality: in total (based on opened NCR) 22 leaks on W-bellows (1.2%)! 2014/09/16 CMI Section Meeting

8 Safety Relief Valves (DN200) installation
612 missing DN200 installed (sec.23, sec.45 - partially, sec.78, sec.81) 17 DN200 installed on cryo-magnets exchanged during LS1 2 additional DN200 installed for CryoBLM (sec.45 and sec.78) The team: Collaborators from JINR Dubna, Russia; Activity responsible: Jose Manuel Gomes de Faria 2014/09/16 CMI Section Meeting

9 Thermal Screens Upgrade
In the dedicated workshop in Bld.183 ~1900 thermal screens sets were upgraded (a clamp installed instead of the welded lyra; hinge, aluminum bride and snap fasteners were added between the upper and lower shield) The team: 2 FSU + support of Dubna Team Activity responsible: Graeme Barlow In the tunnel ~8500 holes were punched in the cryostat’s thermal screens to prepare the installation of upgraded shields. M-bellows Protections Consolidation ~5000 pcs modified in Workshop (SMI2) ~100 pcs considered as radioactive – modified in Workshop Bld.109 ~40800 inserts installed! The team: Collaborators from JINR Dubna, Russia; supervisor: Alain Bastard 2014/09/16 CMI Section Meeting

10 Other activities during LS1
Non-standard openings: undulators QBUI.5L4 and QUBI.5R4; QBQM.4R2; (NTUA, WUT) Support for CryoBLM installation: QBBI.9R7 and QQBI.9L5 (WUT) ELQA support (NTUA, WUT) Helium Spill Test in sec.45 (WUT) CRG Group support at Bld.180 (NTUA) Support for RP samples removal in sec.45 (HNINP) 2014/09/16 CMI Section Meeting

11 18th June 2014 and later… 2014/09/16 CMI Section Meeting

12 The last closure of LS1 (sec.45)
Photograph: Maximilien Brice 18th June 2014 2014/09/16 CMI Section Meeting

13 Re-openings/closures of interconnections for NC treatment
Since 18th June 2014 86 ICs were opened for NC treatment 69 ICs re-opened for leak detection 14 ICs re-opened for CryoTT fixing 3 ICs re-opened for ELQA Future activities: 20 ICs to close (sec.34 and sec.45) ? ICs to re-open 2014/09/16 CMI Section Meeting

14 Other activities (June-August 2014)
DN200 cryostats painting Production of spare thermal screens (Bld.183) sec.78 – 2 vacuum sub-sectors (21 ICs) sec.45 – all DN200 installed during LS1) sec.34 – 1 IC sec.12 – 1 IC 166 sets of spare upgraded TS stored in SMS18 Activity was finished 17th July Activity was finished 30th June Re-organization of Bld.189 (the storage area for cryo-magnets components) Support for TE-MPE - installation of already manufactured protective metal covers over the nQPS racks; - manufacture of new covers for all DYPB and DYPQ racks in sector 34; - assembly of crates for containing of the 600A remove test system for the EE systems installed in the tunnel. courtesy Michal Strychalski Activity in progress (~80% done) Activity in progress 2014/09/16 CMI Section Meeting

15 Important Events Last Closure BBQ Moussaka Lunch Greek Fondue
courtesy Alain Bastard Photos: Thomas Mantzafinis Moussaka Lunch Greek Fondue Bigos Party CMI Section BBQ 2014/09/16 CMI Section Meeting

16 Important Events GAB Champions 2013-2014 (Groupe Autonome du Basket)
in Geneva CERN Relay Race 2014, The best Team, Category: Open Football Cup 2014, First Place 2014/09/16 CMI Section Meeting

17 Thank you! 2014/09/16 CMI Section Meeting