AB/ATB-EA ML, le 30/03/071 MERIT INSTALLATION
2
AB/ATB-EA ML, le 30/03/072 MERIT INSTALLATION Total supported weight Solenoid: 5500 kg (12000 lbs) Hg System with 23liter Hg: 1800 kg (4000 lbs) Baseplate: 450 kg (1000 lbs) Maximum width of 1.3m (51") to meet CERN facility constraints
3
AB/ATB-EA ML, le 30/03/073 MERIT INSTALLATION Layout
4
AB/ATB-EA ML, le 30/03/074 MERIT INSTALLATION Cranes and shaft…
5
AB/ATB-EA ML, le 30/03/075 MERIT INSTALLATION Solenoid handling with “yellow” cross-bar
6
AB/ATB-EA ML, le 30/03/076 MERIT INSTALLATION Mercury loop
7
AB/ATB-EA ML, le 30/03/077 MERIT INSTALLATION Mercury loop handling
8
AB/ATB-EA ML, le 30/03/078 MERIT INSTALLATION Placing solenoid on the baseplate 1. Baseplate on wedge 2. Solenoid on baseplate 3. Baseplate towed up slope with tractor “VOLK” 4. Wedge removed, traverse down TT2
9
AB/ATB-EA ML, le 30/03/079 MERIT INSTALLATION Handling with “VOLK” (testing with a dummy in TT2)
10
AB/ATB-EA ML, le 30/03/0710 MERIT INSTALLATION TT2 to TT2A
11
AB/ATB-EA ML, le 30/03/0711 MERIT INSTALLATION Same handling procedure for mercury loop…
12
AB/ATB-EA ML, le 30/03/0712 MERIT INSTALLATION Transport Hg SystemRemove RollersTransport Baseplate Remove Rollers, Level MagnetRoll Hg System into MagnetAdd Rollers
13
AB/ATB-EA ML, le 30/03/0713 MERIT INSTALLATION Roll System into Beam LineRemove Rollers Elevate & Tilt