ASHRAE Guideline 0-2005 The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP
2
Purpose of Guideline 0-2005 Describe the Cx Process to verify a facility meets the Owner’s Project Requirements
3
Utilization Guideline Describes the “Process” Technical Guidelines Detail Technical Requirements
4
Guideline 0-2005 The Cx Process ASHRAE Guideline 1-200X HVACR Cx Process (Tech Requirements) NIBS Guidelines 2-200X through 14-200X Requirements Other Technical Cx Volumes Roofing, Lighting, Plumbing, Life Safety, Etc.
5
Pre Design Phase Develop Owner’s Project Requirements (OPR) Cx Scope & Budget Develop Initial Cx Plan
6
Owner’s Project Requirements Forms the basis from which all decisions are made… Design Construction Acceptance Operational Decisions
7
Owner’s Project Requirements Primary Tool for Benchmarking Success and Quality At all Phases of Project Delivery Throughout the Life of Facility
8
Owner’s Project Requirements Owner’s Objectives for a New Facility Guidance for Design Team & Others Not developed by Design Team
9
OPR Should Include… Schedule & Budget Cx Scope & Budget User Requirements Energy Efficiency Goals Applicable Codes & Standards Etc.
10
An OPR is Dynamic… Evolves through each Phase Updated to Reflect Current Project Requirements Feasibility Budget Limitations
11
Design Phase Cx Tasks Verify Basis of Design (BoD) with OPR Update Cx Plan Defining Training Requirements Perform Focused Design Reviews Developed by Design Team CxA Verifies BoD Conforms to OPR Systems Manual
12
Basis of Design Basis of Design (BoD) Conveys Design Assumptions that Fulfill OPR Intent Developed by Design Team Updated throughout Design Phase
13
Basis of Design Includes System Selection Reasoning Assumptions Narrative of System Selection & Reasoning Environmental Conditions Load Calcs & Sizing Codes Operations
14
Systems Manual Information Needed to… Understand Systems Operate Maintain
15
Systems Manual Includes Index of Systems Manual Executive Summary OPR BoD O&M Manuals Cx Process Report
16
Construction Phase Verify Systems & Assemblies Conform to OPR Submittal Review (Spot Check) Develop Test Docs Witness Tests Verify Training Update Systems Manual (OPR, BoD, Etc.)
17
Occupancy & Operations Phase Begins at Substantial Completion Continue through end of Contractual/Warranty Period Ideally, Continues through Life of the Facility
18
Occupancy & Operations Phase CxA Assists in Problem Solving Guidance on O&M to Achieve OPR Seasonal Testing Verify Training Systems Manual Update Cx Report