1
A Stellar Community NORTH VERNON, INDIANA Mayor receives news that North Vernon has been selected!
2
A Stellar Community NORTH VERNON, INDIANA Grant awarded in March 2011.
3
A Stellar Community NORTH VERNON, INDIANA Stellarbration!
4
A Stellar Community NORTH VERNON, INDIANA Stellarbration!
5
A Stellar Community NORTH VERNON, INDIANA Stellarbration!
6
A Stellar Community NORTH VERNON, INDIANA To date, $9,427,000 dollars in grant funds have been formally awarded to North Vernon for Stellar Projects.
7
A Stellar Community NORTH VERNON, INDIANA Stellar “After Hours” for the Façade project.
8
A Stellar Community NORTH VERNON, INDIANA North Vernon has awarded construction contracts to date, totaling over $288,000 dollars in work.
9
A Stellar Community NORTH VERNON, INDIANA Over ten public meetings have already been held during the Stellar Program thus far.
10
A Stellar Community NORTH VERNON, INDIANA Discussion at a public meeting.
11
A Stellar Community NORTH VERNON, INDIANA Answering questions at a public hearing.
12
A Stellar Community NORTH VERNON, INDIANA Work on the Carnegie Library will begin in 30-45 days.
13
A Stellar Community NORTH VERNON, INDIANA Irish Hill Housing Informational Meeting
14
A Stellar Community NORTH VERNON, INDIANA Groundbreaking for the first Stellar Project - Irish Hill Housing Project
15
A Stellar Community NORTH VERNON, INDIANA Groundbreaking for Irish Hill Housing Project
16
A Stellar Community NORTH VERNON, INDIANA Construction on the first 8 houses for Irish Hill is substantially complete.
17
A Stellar Community NORTH VERNON, INDIANA 624 Hoosier Street BEFORE AFTER
18
A Stellar Community NORTH VERNON, INDIANA 526 Hoosier Street BEFORE AFTER
19
A Stellar Community NORTH VERNON, INDIANA 614 East O&M Street BEFORE AFTER
20
A Stellar Community NORTH VERNON, INDIANA 804 Hoosier Street BEFORE AFTER
21
A Stellar Community NORTH VERNON, INDIANA Construction on the next 4 houses in Irish Hill will begin in 35-45 days.
22
A Stellar Community NORTH VERNON, INDIANA Design of the Irish Hill Streets and Sidewalks project will begin in early February.
23
A Stellar Community NORTH VERNON, INDIANA Stellar Committee Presentation at City Council
24
A Stellar Community NORTH VERNON, INDIANA Design of the Downtown Streetscape work is underway— Phase I construction should occur in 2012, and Phase II is scheduled for 2013.
25
A Stellar Community NORTH VERNON, INDIANA Downtown Merchant Stakeholder Meetings
26
A Stellar Community NORTH VERNON, INDIANA Downtown Merchant Stakeholder Meetings
27
A Stellar Community NORTH VERNON, INDIANA Downtown Merchant Stakeholder Meetings
28
A Stellar Community NORTH VERNON, INDIANA Downtown Merchant Stakeholder Meetings
29
A Stellar Community NORTH VERNON, INDIANA Design of the Muscatatuck Trail is underway—construction should occur in 2013.
30
A Stellar Community NORTH VERNON, INDIANA Youth Stakeholder Meeting
31
A Stellar Community NORTH VERNON, INDIANA Youth Stakeholder Meeting
32
A Stellar Community NORTH VERNON, INDIANA Youth Stakeholder Meeting
33
A Stellar Community NORTH VERNON, INDIANA Residents can get more information on the Stellar Communities projects at www.northvernonstellar.comwww.northvernonstellar.com
34
A Stellar Community NORTH VERNON, INDIANA Residents can provide comments via the comment cards provided, or “Contact Us” page on the www.northvernonstellar.com website. www.northvernonstellar.com