Secondary Mirror Handling Paper Review June 8, 2011 Kyle Kinoshita Gloria Martin
2
May 26, 2011Secondary Mirror Handling Internal Review2 Introductions Internal WMKO Review Team Craig Nance, Operations Engineering Manager – mirror coating expertise and leadership, and mirror handling RE Mike Dahler, Infrastructure Lead Engineer – mirror handling leadership and ME expertise Sergey Panteleev, Optics Engineer – telescope optics engineering expertise and telescope throughput lead Dennis McBride, OID Principal Engineer – mirror support expertise and lead for the Segment Crack Repair Project George Wall, Optics Technician Assistant – mirror coating operations and mirror handling expertise
3
May 26, 2011Secondary Mirror Handling Internal Review3 Introductions Internal WMKO Review Team (continued) Steve Shimko, SHEA Officer – SHEA compliance expertise and operations oversight John Baldwin, Infrastructure Supervisor – summit day operations leadership and infrastructure expertise Gloria Martin, OID Administrative Assistant – Process and procedure configuration control, and logistics expertise Sky Hudek, Optics Assembly Technician – Mirror coating and handling expertise Kyle Kinoshita, TSD Sr. Manager – Telescope Mirror Handling Review Project Manager
4
May 26, 2011Secondary Mirror Handling Internal Review4 External Review Panel Mike DiVittorio, Engineering and Operations Manager, U.S. Naval Observatory, Flagstaff – Panel Chair – optics operations expertise and experience as Optics Engineer at Keck and External Review Panel Chair for Tertiary Handling Review Steve Bauman, Operations Mechanical Engineering Manager, CFHT – Mechanical engineering background, large optics experience and External Review Panel member for Segment and Tertiary Mirror Handling Reviews Dr. Rob Bernier, Senior Opto-mechanical Engineer, TMT Project – Possesses a thorough understanding of optics handling, and the principles of kinematic support and precision motion. Former Lead Metrologist for the JWST mirrors and the handling equipment Design Lead for the 1.5m beryllium mirrors.
5
May 26, 2011Secondary Mirror Handling Internal Review5 Paper Review Agenda 8:00 – 8:30External Review Panel Executive Session 8:30 – 8:50 Welcome, Introductions & Recap of Overall Review Objectives 8:50 –9:30Develop Understanding of Existing Handling Processes 9:30 – noonRecommendations for July Recoating and Review Noon – 12:45External Review Panel Executive Session (Kamuela) Internal Reviewer Lunch &Open Discussion (Hualalai) 12:45 – 1:30External Review Panel Preliminary Recommendation and Discussion 1:30 – 2:00Summary of Actions and Next Steps for On-site Review
6
May 26, 2011Secondary Mirror Handling Internal Review6 Review Protocol and Logistics Kyle Kinoshita as review facilitator Meeting all review objectives within time constraints Questions fielded during presentation Facilitator may elect to queue questions or discussion topics where appropriate We encourage the use of comment forms to express your less critical concerns, questions and suggestions Gloria Martin as timekeeper and scribe
7
May 26, 2011Secondary Mirror Handling Internal Review7 Overall Objectives of Telescope Mirror Handling Reviews To Ensure Safe Handling of Keck Telescope Mirrors (Primary segments, tertiary and secondary mirrors): Personnel safety Optics and equipment safety and optical throughput: Primary mirror axial and radial support cracks are propagating - We have minimized handling impact and mitigated medium to high catastrophic risks Tertiary mirrors are vital to each telescope Secondary mirrors are essential for nightly operations
8
May 26, 2011Secondary Mirror Handling Internal Review8 Overall Objectives of Secondary Mirror Handling Review To review Keck’s telescope secondary mirror handling practices (encompassing procedures, personnel resources, tooling and equipment) to identify areas where moderate to high risk to personnel, telescope optics and equipment safety are being encountered, and to provide recommendations to mitigate these risks.
9
May 26, 2011Secondary Mirror Handling Internal Review9 Timeline for Secondary Mirror Handling Review and Recoating 6/8Paper Review (5 weeks before on-site review) ~6/142nd Draft Procedures and Process Changes Complete ~6/21Dry Run (3 weeks before on site review) Equipment Check Out Complete 7/5On-site Review Materials Dist. (1 week before On-site Review) Procedures and Process Changes Complete 7/12 – 7/15On-site Review and Recoating At Summit7 /12 – 7/14 At HQ7/15 <8/1Mirror Handling Engineering and Leadership Team reviews recommendations from External Panel and makes collective recommendations for implementation to Directorate <10/1/11Process and minor equipment changes are implemented <10/1/12Major equipment changes are implemented as part of the FY12 Secondary Mirror Handling Project
10
May 26, 2011Secondary Mirror Handling Internal Review10 Desired Outcomes for Today’s Paper Review To understand the following: Existing and proposed practices, procedures and equipment used for handling our secondary mirrors. Where moderate to high risks to personnel, telescope optics and equipment safety have been or have a high probability of being encountered. To determine specific changes to our existing secondary mirror handling practices proposed for implementation prior to the on-site handling review and recoating.
11
May 26, 2011Secondary Mirror Handling Internal Review11 Develop Understanding of Existing Handling Processes 8:50 –9:30 Field Questions from External Reviewers Field Questions from All Reviewers
12
May 26, 2011Secondary Mirror Handling Internal Review12 Recommendations for July Recoating and Review 9:30 – noon Specific changes to our existing secondary mirror handling practices): Identify Highest Risks to Safety Recommendations to Mitigate Highest Risks
13
May 26, 2011Secondary Mirror Handling Internal Review13 Internal Reviewer Lunch & External Panel Exec. Session Noon – 12:45 External Review Panel Executive Session (Kamuela) Internal Reviewer Lunch and Open Discussion (Hualalai)
14
May 26, 2011Secondary Mirror Handling Internal Review14 External Panel Prelim. Recommendation 12:45 – 1:30 External Review Panel Preliminary Recommendation and Discussion
15
May 26, 2011Secondary Mirror Handling Internal Review15 Summary of Actions and Next Steps for On-site Review 1:30 – 2:00
16
May 26, 2011Secondary Mirror Handling Internal Review16 Mahalo Plenty! Thank you for your participation and contributions at this important Keck operations review which is our 2 nd out of 3 major review milestones enabling us to perform secondary mirror recoating safely and efficiently!