Download presentation
Presentation is loading. Please wait.
Published byAmelia Cross Modified over 9 years ago
1
Facilities Modernization Program Funded by Measure B Project Report April 16, 2012
2
PROJECT PROGRESS REPORT Student Services & Central Administration Project Team: Architect: Steinberg Architects Construction Manager: Parsons Brinckerhoff Contractor: Zovich Construction Project Update: Storefront installation is complete. Glazing is 75% installed in the Storefronts Curtainwall installation has started. Glazing to begin April 20 Interior framing continues on the first floor west side in the dining/kitchen area. Data cable has started being pulled on the second floor east side Sheetrock has started on one side of the walls. Elevators are delivered and awaiting installation. Mechanical units were delivered and installed on the roof. Occupancy: Spring 2013 LAS POSITAS COLLEGE April 16, 2012
3
PROJECT PROGRESS REPORT Science Building, Phase II Project Team: Architect: Kwan Hemni Construction Manager: Parsons Brinckerhoff Contractor: Broward Builders, Inc Project Update: Interior Casework, Lighting and Fume hoods continue to be installed. Ceiling Tiles being installed in all rooms, Power to building 95% complete, Elevator starts week of April 16, 2012 Stair Treads and Guardrails are completed. Greenhouse being installed. Exterior and Interior Painting is complete. Restrooms completed. 2 nd floor classrooms are completed. Storefront installation and Glazing Completed. Occupancy: 09/2012 LAS POSITAS COLLEGE April 16, 2012
4
PROJECT PROGRESS REPORT Campus Boulevard Phase I-III Project Team: Architect: Gates & Associates Construction Manager: Parsons Brinckerhoff Contractor: Suarez & Munoz Construction, Inc. Project Update: 100% Design review completed, final design was Approved by DSA February 2012. Project was Bid on March 13, 2012 and Contractor will be Board Approved April 17, 2012. Design Re-Start: 04/2011 DSA Permit Approval: 02/2012 Construction Start: 05/2012 Occupancy: 10/2012 LAS POSITAS COLLEGE April 16, 2012
5
PROJECT PROGRESS REPORT Photovoltaic System Phase II Project Team: Design Build Contractor: Cupertino Electric Inc. Construction Manager: Parsons Brinckerhoff Project Update: Fencing Completed. Racking System and Array installation is completed. Inverters and Transformer installed and completed. New Switchgear tie in May 19, 2012. Operational: February 2012 LAS POSITAS COLLEGE April 16, 2012
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.