Download presentation
Presentation is loading. Please wait.
Published byPhillip Bradford Modified over 9 years ago
1
Janet Update GridPP – 22 Aug 2014 - Ambleside David Salmon
2
Topics Jisc / Janet status Janet6 GriddPP Networking forward look Test networks E-Infrastructure & industry – Janet Reach… Cloud & datacentre comments
3
Jisc / Janet Two companies – Jisc - now a charity – the holding company – Jisc Collections and Janet – a wholly owned subsidiary Governance – Universities UK, Guild HE, Association of Colleges (AoC) - 30% each – Institutional - 10% Janet network charge / Jisc subscription model – Jisc wrote to all organisations connected to Janet – Charging model changed – commencing this August (14/15) – Details on Jisc web site Some rationalisation taking place – See Jisc web site – “Front of House”
4
Janet 6 Optical 40/100G Long term – 10+ years for fibre leases Transmission equipment refresh after ~7+ years Roadmap to next capacity increment per wavelength (400G ?) More flexible optical architecture Direct management of optical infrastructure Huge capability for additional capacity Continued integration of Regions
6
Janet6 and e-Infrastructure fibre
7
GridPP Networking forward look Paper from GridPP management board – Very helpful – thanks ! Discussions with Janet operations colleagues to incorporate into planning
8
Site connectivity to Janet Current Janet policy - provide IP capacity according to need NO special arrangements for any T2 site - all Janet capacity provided to organisations – some sites have local arrangements permitting PP groups to route traffic selectively over site connections to Janet Janet Network inherently very capable – enormous latent capacity – does cost money to enable this (and take time) light extra 40/100 Gbit/s wavelengths Procure extra access circuits
9
London Brunel - * Imperial - * QM - * RHUL - * UCL - * Key: * means connected to Janet fibre
10
NorthGRID Lancaster - * Liverpool – NNW fibre, should remain on fibre following regional reprocurement Manchester - * Sheffield – subject to YHMAN reprocurement
11
ScotGRID Edinburgh (ECDF - ACF) - * Glasgow - * Durham – regional re-procurement - looking into fibre options
12
SouthGRID Birmingham -* Bristol -* Cambridge -* (Culham) -* Oxford -* RAL -* Sussex – Janet fibre to Hove – University has Dark Fibre to connect
13
Ones to watch – no specific concerns though (Liverpool) Sheffield Durham NB – not on fibre doesn’t mean poor service ! – But, access circuits needed to provide connection – Extra capacity implies eithe rupgrades or additional circuits
14
Janet Testbed facilities Aurora2 / NDFIS SDN overlay
15
NDFIS Topology
16
NPL Harwell Oxford Campus – Satellite applications Broader collaboration – NPL & Europe
17
SDNs / Openflow Strong theme at the conference (other talks) Desire to collaborate Broader UK discussions Maybe 10+ UK Universities interested in some way Janet will help – modest Openflow overlay to interconnect/interact Research Council funded projects – TOUCAN – EPSRC Programme Grant Bristol, Edinburgh, Lancaster £12M (£6M+£6M) – 5 Years Photonic – Layer2 – Access (Wireless +??) – Other smaller individual projects Connecting “Testbeds”
18
Four node topology London Bristol North Edinburgh Lancaster Bristol GEANT…Wor ld Midlands Maybe 2 physical 10G paths per node Others would be VPNs/logical paths Not determined precise configuration yet NOT Exclusive, but only TOUCAN lead sites shown
19
SDN Overlay & Aurora2 Janet service components Layer 3 (IP) – Tunnels/VPNs Layer 2 – Janet “Lightpaths” Ethernet / MPLS – committed capacity – VPNs – uncommitted capacity - future Layer 1 – Optical: whole wavelengths – 40G / 100G in core Londo n Bristol North Edinburgh Lancaster Bristol GEANT …Worl d
20
Janet - e-Infrastructure & Industry Outreach with moonshot pilot (AAI) Connecting to Janet – Janet Reach – State aid compliant scheme – Industry organisation must apply Innovative project Meet state aid funding proportionalities – Janet connection value / total project value Should be a high-capacity need – Scheme operating on 2 monthly cycles until around April 2015 (perhaps a little longer)
21
Datacentres Slough – Procurement & contracting complete – Janet Network provision in progress – Major centre on Janet – Very open - Tenants install their own racks & equipment Anchor tenants – QM, Kings, LSE, UCL, Crick, Sanger – Open to all Strong interest, probably more to come…
22
Cloud Building on brokerage work in past Looking a central procurement of cloud “capacity/capability” Cost savings through economies of scale ? Soliciting requirements – what do people want ? – c.f. yesterdays discussions – Is there a requirement for elastic expansion into commercial capacity ? – Very interested in peoples views here
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.