Download presentation
Published byMeghan Banks Modified over 9 years ago
1
2. What is the NPV of the above project? The firm’s WACC is 5.8%
MGT 326 HW 5 Solution 1. What is the Discounted Payback Period of a project with the cash flows depicted below? The firm’s WACC is 5.8% $170k $145k $130k $89k $94k 1 2 3 4 5 6 $50k $370k Period 1 2 3 4 5 6 CF -$370.00 -$50.00 $89.00 $130.00 $145.00 $170.00 $94.00 PV0 -$47.26 $79.51 $109.77 $115.72 $128.24 $67.02 Net Cum CFs -$417.26 -$337.75 -$227.98 -$112.25 $15.98 Discounted Payback: 4 + 0.875 = 4.875 / 2. What is the NPV of the above project? The firm’s WACC is 5.8% CF, 2nd, CLR WORK (Clears Cash Flow Registers) -370, ENTER ↓, -50, ENTER ↓, ↓, 89, ENTER ↓, ↓, 130, ENTER ↓, ↓, 145, ENTER ↓, ↓, 170, ENTER ↓, ↓, 94, ENTER NPV, 5.8, ENTER ↓, CPT; NPV = $83.01 1 1
2
Proj B (Must use the common life approach)
MGT 326 HW 5 Solution 3. A firm is considering two mutually exclusive projects that have the annual cash flows shown below. Based on NPV analysis, which project should be accepted? The required rate of return is % Year 1 2 3 4 5 6 Project A CFs -$60.00 $18.00 Project B -$45.00 $30.00 NPVA = $25.80 Accept Project A; highest NPV NPVB = $24.36 Proj A $18 $18 $18 $18 $18 $18 4 5 6 1 2 3 $60 NPV = [N=6, I/Y=7, PMT=18; CPT, PV] - $60 = $ $60 = $25.80 Proj B (Must use the common life approach) $30 $30 $30 $30 $30 $30 4 5 6 1 2 3 $45 $45 $45 CF, 2nd, CLR WORK (Clears Cash Flow Registers) -45, ENTER ↓, 30, ENTER ↓, ↓, -15, ENTER ↓, ↓, 30, ENTER NPV, 7, ENTER ↓, CPT; NPV = $24.36
3
4 A firm is considering two mutually exclusive projects that have the annual cash flows shown below. Project A is a moderately risky project while Project B is considered to have a high degree of risk. The firm’s WACC is 7.34%. The firm uses the risk-adjusted discount rate method to account for project risk. Projects posing minimal risk are evaluated using WACC for the discount rate. Using the WACC as a base, 1.25% is added for moderately risky projects and 2.50% is added for significantly risky projects. The NPV of Project A is: -$13.86 The NPV of Project B is: -$32.18 Year Proj A Proj B -$215.00 -$295.00 1 $65.00 $57.00 2 $63.00 $75.00 3 $60.00 $97.00 4 $110.00 Which project should be adopted? Project A: (Moderate Risk) CF, 2nd, CLR WORK (Clears Cash Flow Registers) -215, ENTER, ↓, 65, ENTER ↓, ↓, 63, ENTER ↓, ↓, 60, ENTER ↓, ↓, 57, ENTER NPV, 8.59, ENTER (radjusted = 7.34% % = %) ↓, CPT: NPV = -$13.86 Project B: (High Risk) -295, ENTER, ↓, 57, ENTER ↓, ↓, 75, ENTER ↓, ↓, 97, ENTER ↓, ↓, 110, ENTER NPV, , ENTER (radjusted = 7.34% + 2.5% = 9.84%) ↓, CPT: NPV = -$32.18 Adopt neither project Homework 5
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.