Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012.

Similar presentations


Presentation on theme: "Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012."— Presentation transcript:

1 Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

2 What Happened Since February?  Sensors  Details by T.Tsuboyama  Micron delivered trapezoidal sensors with new atoll design  Construction database under development  Ladder assembly  Details by Y. Onuki  Double-origami ladder built at IPMU, Japan  4 construction sites for series production  Mechanics  Details by I.Gfall  Design completed for all layers  Cooling  Details by C.Niebuhr  Detail design converging  Mockup tests ongoing  Electronics  Readout details by myself, integration by K.Hara  DC/DC converters and other parts tested  FADC design completed, layout in progress 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule2 Concerns/recommendations In Feb 2012 BPAC report

3 SVD Schedule  In early 2012, a detailed schedule was worked out and is now maintained by C.Irmler (HEPHY Vienna)  More than 200 unique items (and growing) with dependencies, duration and responsible persons  MS Project & PDF versions are available at http://www.hephy.at/project/belle/belle2svd/schedule http://www.hephy.at/project/belle/belle2svd/schedule  SVD ready for installation in August 2015 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule3

4 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule4 Sensors Ladder Production Mechanics Cooling Electronics Summary

5 Sensors (1/2)  HPK  Large rectangular sensors:  130% of installed quantity delivered already  Will issue an extra order for ~15% more in 2013  Small rectangular sensors:  Design submission and order by November 2012  Delivery until June 2013  Construction database is being developed  First filled with sensor data (objects, measurements, transfers, …)  Then also other objects 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule5

6 Sensors (2/2)  Micron  Trapezoidal sensors:  3 wafers with new p-stop design delivered in August 2012, tested OK  Beam test + irradiation + beam test in October 2012  After analysis: series production order by December 2012  Delivery until August 2013 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule6

7 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule7 Sensors Ladder Production Mechanics Cooling Electronics Summary

8 Ladder Production Sites  Discussion among all parties during summer 2012 B2GM  Plan for sharing of production:  L3: Melbourne  L4: Tata (at CERN due to export restrictions)  L5: HEPHY Vienna  L6: IPMU  We also agreed that it is important to keep some flexibility in our plan, so that one site can help another if trouble/delay occurs 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule8

9 Origami Prototype Modules  Single Origami modules (HEPHY, 2010 and 2011)  Double Origami module (IPMU, 2012)  Both: collaborative effort of HEPHY, IPMU and Tata 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule9

10 Ladder Production Schedule  Full ladder prototypes (L5 & L6) by February 2013  Followed by final optimization of jigs  Series production for ~1 year starting summer/autumn 2013 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule10

11 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule11 Sensors Ladder Production Mechanics Cooling Electronics Summary

12 Mechanics  Detailed design for all layers (including L3) completed 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule12

13 Mechanics: Minor Open Issues  Ladder mount on end rings  Not finalized yet, but converging  Prototypes being prepared  Cooling for L3 hybrids  heat pipes look promising, now investigating 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule13 Acknowledging help from MPI & DESY engineers!

14 Mechanics Schedule  Overview:  Overall design is completed  Ladder mounts to be finalized by end of 2012  Carbon fiber rib prototypes now being produced  Support cone prototypes in August 2013  End flange prototype by March 2013  Detailed SVD mockup by March 2013  See slides from recent SVD-PXD meeting for more details: http://indico.mppmu.mpg.de/indico/getFile.py/access?contri bId=2&sessionId=2&resId=0&materialId=slides&confId=1877 http://indico.mppmu.mpg.de/indico/getFile.py/access?contri bId=2&sessionId=2&resId=0&materialId=slides&confId=1877 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule14

15 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule15 Sensors Ladder Production Mechanics Cooling Electronics Summary

16 Cooling  CO2 system in Belle II does not need inspection by Japanese government (capacity is too small)  Will be operated by the KEK cryogenics experts  Cooling Mockup at DESY  Operated with XFEL CO2 unit (similar to MARCO which will become available by the end of 2012)  Distribution & Routing of cooling pipes  Number of lines is defined  First design for manifolds and routing exists  2 options for transfer lines (3 pipes in larger one or pipe-in-pipe)  APV25 cooling contact is converging 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule16

17 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule17 Sensors Ladder Production Mechanics Cooling Electronics Summary

18 Front-End Electronics Schedule 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule18 prototypes successfully tested design submitted prototypes available designed but not yet ordered prototypes tested  ok design very similar to +z L4-6  soon!

19 Back-End Electronics Schedule  FADC: circuit design done, now to CAD & PCB layout  Then surrounding system components (controller, backplane, …)  Prototype system in Q1/2013  Firmware development in parallel 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule19

20 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule20 Sensors Ladder Production Mechanics Cooling Electronics Summary

21  Lots of progress in all fields  Detailed (and maintained) schedule available on the web  Sensors  all deliveries to be completed in 2013  Ladder assembly  Prototype ladder in early 2013, series production in late 2013  Mechanics  Overall geometry solved, now optimizing details  Cooling  Mockup tests at DESY  Electronics  FADC layout in progress 1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule21