1 January 30, 2014 Luke Lortie, EIT 651.266.7123 Jerry Auge, PE 651.266.7117

2  Project Overview  Alley Way Access  Storm Water Treatment  Right-of-Way Acquisition Update  Arlington Hills Park Impacts  Future of Vacant Parcels  Project Schedule/Estimated Cost Update  Project Phasing

3  Received HSIP Funds to Address Safety Concern  44 Foot Roadway Width (55 Feet at Intersection)  4 Lanes  11 Foot Lane Width  Left Turn Lanes on Maryland Avenue  30 mph Speed Limit  Sidewalks  Alley Way Closures

4  Current Alley Ways Pose a Safety Concern o Currently Located Very Close to Signalized Intersections o Sight Distance Issues  5 Accesses to be Closed  Closure Design Options o Chain Link Fence; 5-Foot Boulevard; Hazard Marker o Planted Shrubs; 5-Foot Boulevard; Hazard Marker o Ballards; No Greenspace Boulevard; Hazard Marker

5

6

7

8  County Recommends Ballard Option

9  Required to Maintain At Least 2 Accesses to Passable Streets  Southwest Quadrant Contains Only 1 Access After Proposed Closures  2 Proposed Mid-Block Alley Way Locations

10

11

12 *Current Alley Way Slope: 6% to 13%

13  By Moving the Alley Way East, Slope Can Be Drastically Reduced.  More Moderate Slope Allows for a Safer Alley Way o Easier to Navigate During Winter Months o Easier to Collect and Retain Storm Water Runoff  County Recommends East Alley Option

14  Treatment Required for Watershed Dist. Permit  County Discussing Designs with Capitol Region Watershed District  Watershed Requires Volume Reduction of 1” Per Acre Impervious Surface o Proposed Impervious: 2.25 Acres o Volume Reduction of ~8,200 Cubic Feet

15  Design Options o Infiltration o Biofiltration o Ponding o Tree Boxes  County Looking at Linear Underground Filtration Along Vacated Parcels

16

17

18

19  33 Properties Impacted o 1 Church o 1 Park Property o 2 Private Commercial Properties o 1 Parking Lot o 2 Vacant Lots o 26 Residential Properties

20

21  Temporary Easements o 22 Settled  Property Acquisition o 8 Signed Agreements o 2 Tentative Settlements o 1 Residential Not Settled

22  8 Properties o 7-Prior to Construction o 1-During Construction  County in Process of Letting Demo Contract o As Properties Are Acquired o Demolition February – April 2014

23  Federal Funding Requires 4(F) Approval o Section 4(F) Regulates the Use of Publicly Owned Parks, Refuges, and Historic Sites for Federal Highway Projects o County, City, and Parks Require Separate Approval Processes

24

25  4(F) De Minimis Process o Road Project Impact to Features, Attributes, or Activities in Park o 30-Day Public Comment Period Advertised in the Ramsey Review January 8 & 15, 2014

26  Public Comments – Added to Project Memorandum (Federal Funding Requirement)  FHWA Findings o Reviews Public Comments o Issues De Minimis Impact Finding o Requests City of St. Paul Approval

27  Parcels Will Be Demoed and Graded o Current Parcels Do Not Meet City Requirements o Parcel Zoning to Be Determined by City of St. Paul  Sewer & Water Utilities Will Be Constructed to Vacant Parcels During Road Reconstruction

28  What’s the Future????  Residential/Commercial???  Water Services  Sewer Service  Prevent the Excavation of Newly Constructed Roadway

29  10 Vacated Parcels = ?? New Parcels

30 ROW Purchase AgreementsJan 2014-Mar 2014 Design Plans at 90%January 2014 CondemnationMarch 5, 2014 Design ApprovalMarch 30, 2014 Right-of-Way Certificate #1March 17, 2014 Advertise for BidsApril 2014 Bid AwardingMay 2014 Start of ConstructionJune 2014 Completion of ConstructionAugust 2014

31 Federal $1,498,000 County State Aid Highway$1,600,000 Municipal State Aid$1,580,000 Total$4,688,000

32  To be Determined o Private/Public Utility Work o Community Input o Project Duration  MnDOT 35E MNPass Project o Potential Closures Affect Maryland Traffic Volume?  Future Open House Meeting

33  For the most up-to-date project information and to receive project updates regularly throughout the duration of the project, visit the Ramsey County website at: http://www.co.ramsey.mn.us/pw/index.htm http://www.co.ramsey.mn.us/pw/index.htm Click on ‘Subscribe to Maryland and Payne Email Updates’ to receive future email updates on the status of the project

34 January 30, 2014 Luke Lortie, EIT 651.266.7123 lucas.lortie@co.ramsey.mn.us Jerry Auge, PE 651.266.7117 jerry.auge@co.ramsey.mn.us