Presentation is loading. Please wait.

Presentation is loading. Please wait.

Los Angeles Interoperable Regional Communications System © Copyright 2015, LA-RICS Authority. All Rights Reserved. CPRA Update January 15, 2015.

Similar presentations


Presentation on theme: "Los Angeles Interoperable Regional Communications System © Copyright 2015, LA-RICS Authority. All Rights Reserved. CPRA Update January 15, 2015."— Presentation transcript:

1 Los Angeles Interoperable Regional Communications System © Copyright 2015, LA-RICS Authority. All Rights Reserved. CPRA Update January 15, 2015

2 LA-RICS LMR System Project Progress

3 © Copyright 2014, LA-RICS Authority. All Rights Reserved. Early Equipment Deployment – UHF and 700 MHz. – User equipment dispersed to Member Agencies – Redundant cores energized and operating Site on Wheels System Design – System Design is complete pending final frequency plan Technical Progress

4 © Copyright 2014, LA-RICS Authority. All Rights Reserved. CEQA – Environmental Impact Report (EIR) Scoping meetings concluded 3 rd Quarter 2014 Data collection is on-going and documentation has begun. CEQA Exemption National Environmental Protection Act (NEPA) – On-going discussions with FEMA to clear sites for construction. Site Access Agreements Environmental Progress

5 © Copyright 2014, LA-RICS Authority. All Rights Reserved. Install and operate 80 – 90 LMR facilities at sites located primarily in L.A. County. – One in both San Bernardino and Orange County Approximately 115 sites being considered – 74 required to meet coverage and capacity requirements of the contract – 15 additional sites required to meet Bounded Area Coverage and Train requirements of the contract – Remaining 26 intended as alternate locations if sites become unavailable. LMR Sites

6 LARICS LTE PSBN Project Progress

7 © Copyright 2015, LA-RICS Authority. All Rights Reserved. Site Build Progress DOC FONSI and Supplemental EA Permit submissions and CUP processes Incomplete Construction Drawings – No Power – No Transmission Sites dropping out – impacting the anticipated site pipeline – Lack of SAA/Denial by Host Cities Construction timeframe shrinkage Per Site Construction timing Number of crews required to make Build Site, System and Optimization test plans and timing

8 © Copyright 2015, LA-RICS Authority. All Rights Reserved. Transmission/Backhaul Progress Lock down design for Microwave and Fixed Fiber services with least cost Operations Expense mix Trenching and connection from Site to Carrier POP not in Construction Designs Satellite interim solution not verified as viable backhaul solution – Testing required to pass Satellite RFI questions – Verify MVPN operability with Satellite solution

9 © Copyright 2015, LA-RICS Authority. All Rights Reserved. Devices Progress Device and UICC RFSQ issuance, vendor selection and current product availability & breadth UICC logistics management, procurement and provisioning UE device ordering, warehousing, distribution and installation management Device service provisioning process and roles Asset system and provisioning system synchronization Longer term – new device evaluation & acceptance

10 © Copyright 2015, LA-RICS Authority. All Rights Reserved. Operational Considerations NOC placement, sizing and staffing NOC roles and responsibilities after warranty period Field support roles before, during and after warranty period for microwave, and site maintenance Network Issue Notifications to LARICS and Agencies Operations Daily Weekly and Monthly Reports covering Core, Transmission and Sites operational health Operations Governance structure for managing Motorola to meet agreed to SLA and KPI performance requirements Change Management Structure to ensure network and agency changes (established & new) are managed and do not unintentionally disrupt ongoing operations

11 © Copyright 2015, LA-RICS Authority. All Rights Reserved. Special Operations Test (SOT) Install and Deploy 25 In-Vehicle Routers Create workflows Create test plans Identify personnel for test Provide and complete training for systems and tests Set Test start date (based on current construction schedule) Create Criteria for Success and Measure for SOT – Expected performance in the field – Measurement and Assessment of Actual Performance – Identify steps to fix areas of deficiencies as needed


Download ppt "Los Angeles Interoperable Regional Communications System © Copyright 2015, LA-RICS Authority. All Rights Reserved. CPRA Update January 15, 2015."

Similar presentations


Ads by Google