Golden Triangle Blvd. Progress Report March 27, 2007
2
City ………………$7.3 Million County……………$7.3 Million Federal……………$11.0 Million $25.6 Million Funding
3
Current
4
2004 2007
5
+ - Proposed Urban Design Median/Left Turn Lanes Curb & Gutter Sidewalks Drainage Improvement $18.3 Million 50+ Year (permanent fix) Alternative Rural Road Barrow Ditches Federal Strings (6-8 months) 5-10 Year (Band-Aid) Re-prioritization
6
Current Maintenance/Improvements Constructing Beach St. at Alta Vista Left Turn Lanes Re-timing Traffic Signals Major Surface Repair (500 tons) Re-stripe Roadway Drainage west of SH 377 Keller-Hicks at Alta Vista
7
http//www.fortworthgov.org/tpw Project Status Link
8
$7.3M PLAN Two New Lanes (Approx. Life 10 Years) Rehabilitate Existing Roadway (Approx. Life 5 Years) Ditch Ditch Ditch
9
$25.6M PLAN 4-Lane Divided Arterial with Curb and Gutter Raised Median Underground Drainage Traffic Signals Left & Right Turn Lanes
10
FEDERAL FUNDING REQUIREMENTS Environmental Assessment –Coordination with multiple agencies –Public Involvement TxDOT / FHWA Review and Approval Processes –30%, 60%, 90%, 100% Reviews –Bridge Design Review in Austin –Plan Review in Austin (6 months)
11
200520062007200820092010 1234 1234 1234123412341234 Schematic Development (Survey, Traffic Studies, Funding Sources) Environmental Study Design TxDOT (Austin) Review UPRR Coordination ROW Acquisition Utility Relocations Construction TIMELINE (URBAN ROADWAY)
12
TIMELINE (RURAL ROADWAY) 200520062007200820092010 1234 1234 1234123412341234 Schematic Development (Survey, Traffic Studies) Design UPRR Coordination ROW Acquisition Utility Relocations Construction
14
CONCLUSION - Councilman Espino Is 8 months worth $18.3 million?