1 Building Use Study Plattsburgh City School District Advisory Committee Meeting November 20, 2013 Castallo and Silky- Education Consultants Bill Silky and Phil Martin, Consultants
2
Purpose of Study 1.Given the practical capacities of the existing schools and in light of future enrollment projections, is it feasible to reduce the number of operating school buildings and continue to maintain the quality of the educational program? If so, how might the buildings best be utilized and what might the fiscal implications be? If not, what building modifications, if any, should be made, and why? 2.Is it feasible to relocate district office functions to another school building? If so, what are the options for their relocation? 2 Castallo & Silky-Education Consultants
3
Enrollment History and Projections: Update 3 Castallo & Silky-Education Consultants
4
Updated Enrollment Projections 4 Castallo & Silky-Education Consultants
5
Facilities 5 Castallo & Silky-Education Consultants
6
2013 Building Conditions Survey: Elementary Schools 6 Castallo & Silky-Education Consultants
7
2012-13 Building Utility Costs 7 Castallo & Silky-Education Consultants
8
Space Utilization 8 Castallo & Silky-Education Consultants
9
High School Room Utilization 2013-14 9 Castallo & Silky-Education Consultants
10
10 Castallo & Silky-Education Consultants K-5 Enrollments and Sections
11
Projected Number of Elementary School Grade Sections 11 Castallo & Silky-Education Consultants
12
Findings Except for special education students, all students walk to school K-12 enrollment has declined by 1.6% over the past five years, from 1,833 to 1,804 K-12 enrollment is projected to increase by 3.4% over the next five years, to 1,865. K-5 enrollment has increased by 1.9% over the past five years, from 829 to 845. K-5 enrollment is projected to increase by 7.7% over the next five years to 910. 12 Castallo & Silky-Education Consultants
13
Findings Middle school enrollment has declined by 4.4% over the past five years, from 408 to 390. Middle school enrollment is projected to remain stable for three years, then increase to 420 (+7.7%) in five years and back to 414 in seven years. High school enrollment has declined by 4.5% over the past five years, from 596 to 569. High school enrollment is projected to decline by 6.0% in five years to 535, but then increase to 563 in seven years. 13 Castallo & Silky-Education Consultants
14
Findings There is potential for residential development in the city similar to the development 5-8 years ago, with about 40 lots being developed The elementary school instructional programs are very similar; however, student performance at Bailey/Oak is somewhat higher than Momot. This most likely is attributed to socio-economic differences in the attendance areas served. All buildings in the district need some structural improvement. 14 Castallo & Silky-Education Consultants
15
Findings Over the next five years the three elementary schools will need the same number of classrooms as this year, but no more than this year. Except for Stafford Middle School, school parking areas are adequate for current use. Relocating students to Bailey or Stafford would require additional parking. The boundaries of Stafford Middle School do not permit the construction of additional parking. 15 Castallo & Silky-Education Consultants
16
Findings Construction of additional classrooms at Bailey may require acquisition of park property from the City. The legality of acquiring park property from the City is uncertain, even if the City is willing to release the property. Additional classrooms at Bailey could present safety concerns regarding the increased influx of vehicles at the beginning and end of the school day. 16 Castallo & Silky-Education Consultants
17
Options: Advantages & Disadvantages 17 Castallo & Silky-Education Consultants
18
Options 18 Castallo & Silky-Education Consultants 1.Continue current grade and building configuration 2.Keep all classroom buildings open; relocate district office functions to middle/high schools; sell, lease, or maintain Duken building 3.Sell Duken or swap for city park property; close Oak; construct 20-classroom addition to Bailey; relocate district office functions to middle/high schools, or Oak, or Bailey; sell, lease, or maintain Oak 4. Construct 8-classroom addition to Bailey; close Oak; reconfigure grade alignment to PK-4, 5-8, 9-12; realign attendance zone with one-quarter of Bailey to Momot; relocate district office functions to Oak or Middle/High Schools
19
Option 1 Continue current grade and building configuration 19 Castallo & Silky-Education Consultants AdvantagesDisadvantages Keeps all classroom buildings open to accommodate possible enrollment increase Avoids any negative reaction to change Does not make efficient use of current building space Does not reduce operational costs
20
Option 2 Keep all classroom buildings open; relocate district office functions to middle/high schools; sell, lease, or maintain Duken building 20 Castallo & Silky-Education Consultants
21
Option 2 Keep all classroom buildings open; relocate district office functions to middle/high schools; sell, lease, or maintain Duken building 21 Castallo & Silky-Education Consultants AdvantagesDisadvantages Keeps all classroom buildings open to accommodate projected enrollment increase Increases efficiency of space utilization if Duken is sold or leased If Duken is sold, an annual operational savings of approximately $71,825 - $84,600 is generated (current assessed valuation of Duken is $1,879,200) Avoids any negative reaction to change in student building assignments Diminishes communication effectiveness among district office personnel Reduces available classroom space at the middle school and high school should student enrollment increase substantially
22
District Office Function Relocation 22 Castallo & Silky-Education Consultants
23
23 Castallo & Silky-Education Consultants District Offices At High School
24
Option 3 24 Castallo & Silky-Education Consultants a. Sell Duken or swap for city park property; close Oak; construct 20-classroom addition to Bailey; relocate district office functions to high school and middle school; sell, lease, or maintain Oak b. Sell Duken or swap for city park property; close Oak; construct 20-classroom addition to Bailey; relocate district office functions to Oak; lease or maintain remaining space at Oak c. Sell Duken or swap for city park property; close Oak; construct 20 plus classroom addition to Bailey; relocate some district office functions to Bailey, and some to high school and middle school; sell, lease or maintain Oak
25
25 Castallo & Silky-Education Consultants Additional Classrooms at Bailey Should Oak Close
26
26 Castallo & Silky-Education Consultants Cost Estimate for Addition to Bailey
27
27 Castallo & Silky-Education Consultants K-5 Staffing and Estimated Cost Saving Should Oak Close
28
Option 3a Sell Duken or swap for city park property; close Oak; construct 20-classroom addition to Bailey; relocate district office functions to high school/middle school; sell, lease, or maintain Oak 28 Castallo & Silky-Education Consultants
29
Option 3a Sell Duken or swap for city park property; close Oak; construct 20-classroom addition to Bailey; relocate district office functions to high school/middle school; sell, lease, or maintain Oak 29 Castallo & Silky-Education Consultants AdvantagesDisadvantages Increases staffing efficiency Provides annual cost saving of at least $212,820 Reduces the number of building transitions for students Enhances parent involvement (B/O) Enhances curriculum articulation (B/O) Increases total district student capacity if Oak not sold Provides possible revenue generation from sale/lease of Oak and/or Duken If Oak is leased or maintained, provides margin of safety for location of district offices if enrollment increases Legality of property swap or sale with City & interest of City is uncertain Approval of 20-classroom addition by S.E.D. is uncertain Some staff would lose jobs Increases debt service approximately$100,000/year for 20 years Vehicular traffic at Bailey would increase substantially Parking lot at Bailey could need expansion Could generate negative reaction to change Diminishes communication effectiveness among district office personnel
30
Option 3b Sell Duken or swap for city park property; close Oak; construct 20-classroom addition to Bailey; relocate district office functions to Oak; lease remaining space at Oak 30 Castallo & Silky-Education Consultants
31
Option 3b Sell Duken or swap for city park property; close Oak; construct 20-classroom addition to Bailey; relocate district office functions to Oak; lease remaining space at Oak 31 Castallo & Silky-Education Consultants AdvantagesDisadvantages Increases staffing efficiency Provides annual cost savings of at least $132,800 Reduces the number of building transitions for students Enhances parent involvement Enhances curriculum articulation Increases district’s total student capacity if Oak is not sold Provides possible revenue generation from sale or lease of Duken and lease of space at Oak Maintains communication efficiency among district office personnel Legality of property swap or sale with City & interest of City is uncertain Approval of 20-classroom addition by S.E.D. is uncertain Some staff would lose their jobs Increases debt service approximately$100,000/year for 20 years Vehicular traffic at Bailey would increase substantially Parking lot at Bailey could need expansion Could generate negative reaction to change Does not take advantage of revenue from sale of Oak
32
Option 3c Sell Duken or swap for city park property; close Oak; construct 26-classroom addition to Bailey; relocate some district office functions to Bailey and some to high school and middle school; sell, lease, or maintain Oak 32 Castallo & Silky-Education Consultants
33
Option 3c Sell Duken or swap for city park property; construct 20- classroom addition to Bailey; close Oak Street; lease, sell, or maintain Oak; relocate district office functions to Bailey. 33 Castallo & Silky-Education Consultants AdvantagesDisadvantages Increases staffing efficiency Provides annual cost saving of at least $185,300 Reduces the number of building transitions for students Enhances parent involvement (B/O) Enhance curriculum articulation (B/O) Increases district’s total student capacity if Oak is not sold Provides possible revenue generation from Oak and/or Duken Legality of property swap or sale with City & interest of City is uncertain Approval of 20 plus classroom addition by S. E. D. at Bailey is uncertain Increases debt service approximately$125,000/year for 20 years Vehicular traffic at Bailey would increase substantially Parking lot at Bailey could need expansion Requires minimal initial cost to relocate district office functions Could generate negative reaction to change Diminishes communication effectiveness among district office personnel
34
Option 4 Construct 8-classroom addition to Bailey; close Oak; reconfigure grade alignment to PK-4, 5-8, 9-12; realign attendance zone with one-quarter of Bailey to Momot; relocate district office functions to Oak or Middle/High Schools This option is not feasible because: 1- A lack of instructional classroom space for additional grade and lack of parking space. Assessment of possible space availability at Stafford finds that a maximum of six classrooms could be made available. Over the next seven years a minimum of seven to eight classrooms would be necessary for the building to serve grades 5-8. 2- The parking lot is inadequate to accommodate staff currently, with no room for expansion. Accordingly, the lot could not accommodate increased staff for a 5-8 middle school. 34 Castallo & Silky-Education Consultants
35
Questions???? 35 Castallo & Silky-Education Consultants