Large Platforms For Push-pull Hitoshi Yamamoto 18-Sep-2007 IRENG07
2
Push-pull Experts seem to agree that, for a quick switch, detector, E-hut, and cryogenic system should be on a single platform. Detector needs space to move things (end caps, loading place to platform, etc.) around. Minimum disconnections in order for ‘commissioning/calibration’ to move in. Edges of platform = dead area → A large platform with full width of exp. hall. Service caverns are desirable for each detector.
3
beamline service cavern shaft Left detector on beamline Right detector is assembled as if non-pushpull detector E-hut
4
beamline service cavern shaft
5
beamline service cavern shaft Removable plug Support
6
beamline service cavern shaft Right detector on beamline
7
beamline service cavern shaft Both detectors being serviced
8
beamline service cavern shaft Another possibility for the shield design Half shields on air pads
9
Expensive design (Beijing ACFA07) Full exp. hall area is usable always
11
Some comments Installation more or less a la non-push-pull Connections from outside to platform are kept to minimum: powers mostly (no cold He). Separate platform helps isolation of vibration between two experiments. Thickness of platform ~ 2m : needs some protection at the edges (fences) + ladders.