Bridgewater Canal Construction Update Bridgewater Canal Community Stakeholder meeting 3 December 2014
2
Bridgewater Canal construction sites
3
Construction packages 24 345 4 4 1 6
4
Package 1 Nasmyth’s Steam Hammer
5
Built in 1851 for Elsecar Colliery, Yorkshire At an advanced state of disrepair Contractors appointed: Landscaping – Casserly Property Management Restoration works – Calibre Metalwork Limited Protective canopy – Canal Engineering Limited Landscaping works nearing completion Conservation and canopy works to complete by February 2015
6
Nasmyth’s Steam Hammer
7
Package 2 Worsley Green Monument
8
Built in 1905 as a monument to the Duke of Bridgewater In a poor state of repair Recclesia Ltd appointed as contractor Works in two stages: Vegetation removal – complete by 4 th Dec 2014 (1 day) Conservation works – start on site in March 2015, complete by 30 th April 2015 (8 weeks)
9
Package 3 Worsley Delph
11
Worsley Delph - visualisation
12
Worsley Delph visualisation
13
Worsley Delph - visualisation
14
Progress to date Design work progressing and expected to be finalised by February 2015 Site investigations ongoing: - Ecology surveys – ongoing - Archaeological trial pits – complete - Laser survey and trial pits in workshops – complete - Silt stabilisation trials – complete - Excavations of sluice gate – contractor appointed - Boreholes / trial pits – to be provided to contractor as part of tender package Procurement - Tendering – Feb 2015 – April 2015 Timescales (anticipated) - Contractor appointment – June 2015 - De-silting design / regulatory approvals – Sept 2015 - Construction phase – Sept 2015 – July 2016 (36 weeks)
15
Work package 4 Civil Engineering
16
Towpath improvements
17
Boothstown towpath Design work progressing - Alignment agreed with Bridgewater Canal Company - Liaising with Environment Agency / Viridor re: outstanding design issues Timescales (anticipated) - Contractor appointment – Jun 2015 - Construction phase – Jan – May 2016 (18 weeks)
18
Barton towpath Design work progressing well - Cross sections to be agreed with Bridgewater Canal Company - Advance tree removal works may need to take place prior to works starting Timescales (anticipated) - Contractor appointment – Jun 2015 - Construction phase – Aug – Nov 2015 (12 weeks)
19
Barton Aqueduct Design work to be complete by Dec 2014 - layout agreed with Peel Ports Site investigations / pre-treatment - Japanese Knotweed stem injection treatment undertaken - Ivy removed from Brindley’s aqueduct Timescales (anticipated) - Contractor appointment – Jun 2015 - Construction phase – Aug – Dec 2015 (16 weeks)
20
Barton Aqueduct - visualisation
22
Barton Aqueduct – ivy removal
23
Dukes Drive Design work nearing completion Timescales (anticipated) - Contractor appointment – Jun 2015 - Construction phase – Jul – Aug 2015 (6 weeks)
24
Patricroft Canalside – Hall Bank Draft options produced Ongoing liaison with Network Rail and Urban Vision Highways Work closely aligned to Port Salford Greenway Timescales (anticipated) - Contractor appointment – Jun 2015 - Construction phase – August 2015 (4 weeks)
25
Work package 5 Bridgewater Park
26
Proposed transfer of site from Peel Holdings to city council Funding package needs to be sourced Procurement: - to be procured seperately
27
Overarching package Interpretation
28
Interpreting the canal – some ideas!
29
Timetable
31
Questions?