Harlingen 100 Revitalization Task Force Annual Progress Report Meeting December 9, 2008
2
Revitalization Projects: 1.Relocate Switchyards – Target completion by 12/31/10 2.Streetscape Improvements - Deferred until Heart of Harlingen completed 3.Discovery Center Business Plan – Deferred until Blaska Tower redevelopment completed 4.Downtown Visitor Center & Office – Plan developed, $ from CIB approved to incorporate with Blaska redevelopment
3
Revitalization Projects: 5.Create Catalytic Development Corporation – Articles of Incorporation completed, waiting for Commission approval. 6.Address Deteriorated Properties - Ongoing 7.Enhance Downtown Security – Security Enhancement Grant Implemented. 8.Public Art Program - Underway
4
Revitalization Projects: 9.Heritage Manor – HHA accepted bids on 8/20; negotiations underway. 10.Sidewalk Cafes/Galleries/Spas - Ongoing 11.Centennial Park Phase I – To be completed 2009. 12.Centennial Park Phase II – Plan developed, seeking $ from CIB. 13.Grande Theatre – Not feasible at this time, building for sale. 14.Upgrade Parking Lots – designs completed, seeking funds.
5
Revitalization Projects: 15. Artists Alley – Not feasible at this time. 16.New Image for La Placita – Palm Trees installed on Jackson and Van Buren. 17.Downtown Housing – Identifying opportunities in existing buildings/redevelopment opportunities. 18.Area North of Downtown District – Design Completed. 19.New Street Signs – Completed. 20.Landscape Design/Maintenance – Met with Landscape Architects, project ongoing.
6
Revitalization Projects: 21.Remove Parking Meter Poles - Completed 22.Parking Garage – Long Term Project dependent upon redevelopment of Heritage Manor & other buildings.
7
Two Areas I.Revitalization of Public Space II. Redevelopment of Private Property
8
I. Revitalization of Public Space
9
Removed 456 Old Parking Poles
10
Installed 73 New Palm Trees
11
Improving Sidewalks
13
New Sidewalks Installed
15
New Sidewalks Underway
16
Replaced Deteriorated Street Signs
17
New Street Signs
18
Parking Lot Improvements
19
Harry E. Day Memorial Parking Lot
20
First & Van Buren
21
First & Van Buren Plan
22
Harrison & West
23
Harrison & West Plan
24
First & Jefferson
25
First & Jefferson Plan
26
Second & Madison
27
Second & Madison Plan
28
Third & Jefferson
29
Third & Jefferson Plan
30
Creation of Centennial Park
31
Phase 1: Basic Infrastructure
32
Phase 2: Install Amenities
33
II. Redevelopment of Private Property
34
Catalytic Development Corporation: Articles of Incorporation Done Commission to approve & make appointments Priority list for redevelopment Acquire 1-2 properties in next year Adapt properties for new use Sell & return proceeds to CDC Acquire additional properties, redevelop, sell
35
Priority 1: Blaschka Tower
36
Blaschka Tower Redevelopment Plan: Mixed Use: Office & Residential Visitor Center (1 st Floor) Downtown Office (2 nd Floor) Condominiums (Floors 3-9)
37
Priority 2: Deteriorated Warehouses
38
Warehouse Redevelopment Plan: Work through Code Enforcement Tear Down Redevelop Select Locations
39
Envision New Development
40
Build Density & Connect Assets
41
Harlingen 100 Plan Revitalization Task Force