1
Skeleton: Hardware Alignment for EMU meeting James N Bellinger 15-Mar-2009
2
Things to add Time estimates for repeating the work in May (and August) Time estimates for work TBD: –Transfer Lines –Barrel –Barrel to Endcap Pix from Barrel progress Stuff I’ve forgotten in the skeleton
3
What we Have Now Link on Plus side Some Link on Minus (serious disk misalignment!) Link to MABs Z for ME+2,3,4, ME-2,3,4, ME+1/2 Z for ME+1/3 about to be blessed Some barrel numbers
4
Want pix of Marcus’ chamber tilts, updated w/ ME+1/3 –Check Illustrative barrel Z variation w/ field Fit plots for ME+1 –Check Fit plots for ME+2 –Check
5
5 Muon Endcap Hardware Alignment Preliminary z global r global CMS Side view Nominal CSC position x = 0 Nominal CSC position Not to scale Pink: Aligned by Tracker-Muon Link system Blue: Aligned by Muon Endcap Optical System Red: Not aligned yet x = 0 : 3.9mrad ME+1/3,2/2,3/2: Δz:- 5 mm to IP globally : -17.57 mm : 16.73 mm nom. : -5.04 mm x > 1.3mrad : 5.94 mm : 13.18 mm : 12.60 mm : 12.89 mm : -12.58 mm : -12.35 mm : -12.46 mm : 3.7mrad : 3.4mrad : 3.9mrad : 4.7mrad : 3.6mrad : 4.2mrad : 3.4mrad : 3.4mrad : 3.5mrad nom. : 4.4mrad : 4.4mrad ← Muon Endcap stations → ME+1 ME+2ME+3ME+4ME-1ME-2ME-4ME-3 ME-1/3,2/2,3/2: Δz:+ 5 mm to IP globally : -2.2 mm Green: Not blessed yet
6
ME+2 SLM 2-5 in Z with 10 measurements at B=0T
7
Laser hits on CCDs ME+2 SLM 2-5 in Z at B=0T
8
Chamber surface estimates Red=Real Green=Sim MAB ASPD ME12 ASPD ASPD P4 Distancemeter and dists IR target DCOPS dowels Animated
9
In the pipeline 1.Some X/Y information for ME+/- separately 2.Barrel muon 3.ME-1 4.Refit Endcap using relative X/Y info from step 1 5.Proof of principle linking MAB with Endcaps via Transfer Lines
10
Hardware-dependant Minus side Link –Disks so badly assembled that components couldn’t talk to each other! MAB DCOPS X/Y End-to-end X/Y –Better care assembling disks –Requires some adjusting of the lasers
11
Order of Tasks for Endcap Independent validation of data quality in all detectors Stand-alone reconstruction of SLMs and Transfer Lines When Link results are available: Big Bang
12
Close CMS Bi weekly MWGR weekly MWGR CRUZET S w & w/o tracker CRAFTS Adjust LD- LHC dev. collisions DT StandAlone align Alignment Work Plan Alignment Work Plan Mar Apr May Jun Jul Aug Sep Oct Nov Dec Barrel HW Geom Endcap HW Geom Full Link @ B=3.8T AR vs. TK survey+tracks r correction CSC align w/cosmics DT align with collision tracks CSC align with collision tracks Full Barrel HW Geom @ B=3.8T Full Endcap HW Geom @ B=3.8T Integrated HW Geom @ 3.8T Integrated HW + track-based Geom Full Link Geom @ 0T Full Barrel HW Geom @ 0T Full Endcap HW Geom @ 0T Integrated HW Geom @ 0T DT align with CRAFT2 cosmics CSC align with CRAFT2 cosmics
13
Time Estimates IFF –the disks were assembled with reasonable accuracy AND –there were no major hardware failures THEN repeating the work with fresh data in May should be quick—order of a week or two (?) Doing it again in August should be very much easier
14
But Some tasks will be done for the first time in May: Transfer Line inclusion, for example.