Distributed IT Infrastructure for U.S. ATLAS Rob Gardner Indiana University DOE/NSF Review of U.S. ATLAS and CMS Computing Projects Brookhaven National Laboratory NOVEMBER 14-17, 2000
2
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 2 Outline Requirements Approach Organization Resource Requirements Schedule Fallback Issues
3
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 3 Distributed IT Infrastructure A wide area computational infrastructure for U.S. ATLAS A network of distributed computing devices A network of distributed data caches & stores Connectivity Physicists with data (laptop scale sources: LOD) Computers with data (at all scales) Physicists with each other (collaboration) Distributed information, portals Efforts Data Grid R&D Strategic “remote” sites (Tier 2s) Distributed IT support at the Tier 1 center
4
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 4 Requirements Access Efficient access to resources at the Tier 1 facility Data distribution to remote computing devices Information A secure infrastructure to locate, monitor and manage collections of distributed resources Analysis planning framework Resource estimation “Matchmaker” tools to optimally connect physicist+CPU+data+etc… Scalable Add arbitrary large numbers of computing devices as they become available Add arbitrarily large numbers of data sources as they become available
5
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 5 Approach ~5 strategic remote sites (Tier 2s) Scale of each facility: MONARC estimates ATLAS NCB/WWC (World Wide Computing Group) National Tier 1 facility 209 Spec95 365 Online disk 2 PB tertiary Tier 2 = Tier 1 * 20%
6
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 6 Role of Tier 2 Centers User Analysis Standard configuration optimized for analysis at the AOD level ESD objects required for some analysis Primary Resource for Monte Carlo Simulation “Spontaneous” production level ESD skims (autonomy) Data distribution caches Remote data stores HSM serve to archive AODs MC data of all types (GEN, RAW, ESD, AOD, LOD) from all Tier 2’s & users
7
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 7 Typical Tier 2 CPU: 50K SpecInt95 (t1: 209K) Commodity Pentium/Linux Estimated 144 Dual Processor Nodes (t1: 640) Online Storage: 70 TB Disk (t1: 365) High Performance Storage Area Network Baseline: Fiber Channel Raid Array
8
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 8 ‘Remote’ Data Stores Exploit existing infrastructure mass store infrastructure at 2 of the 5 Tier 2 centers Assume existing HPSS or equivalent license, tape silo, robot Augment with drives, media, mover nodes, and disk cache Each site contributes 0.3-0.5 PB store AOD archival, MC ESD+AOD archival
9
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 9 Organization Facilities Subproject 2.3.2
10
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 10 Personnel MANPOWER ESTIMATE SUMMARY IN FTEs WBSNo:2Funding Type:Infrastructure11/13/00 8:08:38 PM Description:US ATLAS ComputingInstitutions:AllFunding Source :All FY 01FY 02FY 03FY 04FY 05FY 06Total IT I1.04.06.010.010.07.038.0 IT II.01.02.02.05.05.015.0 Physicist1.01.01.01.01.0.05.0 TOTAL LABOR 2.06.09.013.016.012.058.0
11
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 11 Tier 2 Costs
12
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 12 Schedule R&D Tier 2’s – FY ‘01 & FY ‘02 Initial Development & Test, 1% to 2% scale Start Grid testbed: ATLAS-GriPhyN Data Challenges – FY ‘03 & FY ‘04 Production Tier 2’s – FY ‘04 & FY ‘05 Operation – FY ‘05, FY ‘06 & beyond Full Scale System Operation, 20% (‘05) to 100% (‘06) (as for Tier 1)
13
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 13 Calren Esnet, Abilene, Nton Abilene Esnet, Mren UC Berkeley LBNL-NERSC Esnet NPACI, Abilene Brookhaven National Laboratory Indiana University Boston University Argonne National Laboratory HPSS sites U Michigan University of Texas at Arlington Testbed ‘01
14
November 14-17, 2000 Rob Gardner Tier 2 Plan for U.S. ATLAS 14 Fallback Issues Impact of limited support for a planned distributed infrastructure? Several scenarios of course are possible US ATLAS will face a serious shortfall in analysis capability Shortfall in simulation capacity Analysis groups will have less autonomy University groups likely augment their facilities through supplemental requests, and large scale proposals to establish multidisciplinary “centers” We could end up with 1 Tier 1 and 32 “Tier 2” centers An incoherent, messy infrastructure, difficult to manage Not the best way to optimize physics discovery