ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’
2
The purpose of this project is to show that I can complete a construction project using all aspects of the construction process. This project will exercise the skills and abilities learned from the Construction Engineering Technology program.
3
Preliminary Drawings Rough Estimate Economic Feasibility Report Site Assessment and Selection Decision on Building Layout Building Codes
4
Wood Framed Concrete Foundation Estimated 3,826 sq. ft. for each building Estimated 957 sq. ft. for each unit.
5
Drawings will be used for a rough estimate and budget. One story layout. Two story layout. Each building will have 4 units. Three bedrooms Two Bathrooms Kitchen Utility Living and Dining Room
9
Cost/Benefits Analysis Do the Benefits outweigh the Costs for the owner? Will it be a profitable business ? How long will it take for the business to pay itself off?
10
Location will be in the Hammond area. The owner would like a site big enough for future expansion, if desired. Once the land is chosen it will be surveyed. Building codes will be acquired. The location, size, and cost of property will determine: The building layout that will be used. The number of buildings that can be built on the property.
11
The completion of the activities this semester will allow the full completion of the pre-construction documents for next semester.
12
The construction documents will include: Final Drawings (using AutoCad): Floor plan Electrical Plumbing Elevations Schedules and Details of Construction Overall Site Drawing (parking included)
13
Building specifications Building Permits Project budget and financing A complete estimation of labor, costs, and materials Detailed materials and equipment list Planning and scheduling of the project using Primavera Project Planner.
14
Aug-20-Aug 22Meet with advisor to discuss topic Aug 25 - Aug 29Cont. Sept1 - Sept 5Cont. Sept 8 - Sept 12Select a Project Sept 15 – Sept 19Begin Research Sept 22 – Sept 26Prepare Proposal and Presention Sept 29 – Oct 3Preliminary Drawings Oct 6 – Oct 10Cont.
15
Oct 13 – Oct 17Economic feasibility assessment of Costs and Benefits Oct 20 – Oct 24Cont. Oct 27 – Oct 31Rough Estimate and Budget Nov 3 – Nov 7Site Assessment and Selection Nov 10 – Nov 14Cont. Nov 17 – Nov 21Decide on Building Layout Nov 24 – Nov 28Building Codes Dec 2 – Dec 5Begin Final Drawings/ End of Classes
16
Jan 20 – Jan 23Construction Documents: Floor plan/ Electrical/ Plumbing/ Elevations/ Overall site plans/ Jan 26 – Jan 30Cont. Feb 2 – Feb 6Cont. Feb 9 - Feb 13Cont. Feb 16 - Feb 20Project Budget and Financing Feb 23 - Feb 27Cont. Mar 2 – Mar 6Building Specifications Mar 9 – Mar 13Cont.
17
Mar 16- Mar 20Estimation of materials, costs, and labor Mar 23 – Mar 27Cont. Mar 30 - Apr 3Building Permits Apr 6 – Apr 10Planning and scheduling using Primavera Apr 13 - Apr 17Cont. Apr 20 – Apr 24Cont. Apr 27- May 1Prepare for final presentations May 4 – May 8Present Project
18
QUESTIONS??????