Background Ni sources: sulfide and oxide ores Ni oxide (laterite) ores found mainly in tropical and subtropical regions (70% of Ni) Depleting Ni sulfide ores Four HPAL plants were built in the last 15 years and others are under construction Vale Inco is building a large plant in New Caledonia (Goro)
4
Autoclave Leaching Primary Neutralization S/L SeparationTailing Neutralization Secondary Neutralization S/L Separation MHP or MSP S/L Separation Lime PLS Barren Solution U/F Intermediate Product CaCO 3 Air Solids to PN Tailings Feed CaCO 3 SO 2 Air Conc. Sulfuric Acid Typical HPAL Flowsheet 240-270 C 250-500 kg acid/t ore
5
Goro Autoclave Circuit H 2 SO 4 92°C 150°C 200°C 92°C 67°C Steam 200°C 270°C Ore slurry Leached slurry Feed Slurry Recycling hot water
6
Goro HPAL Autoclave
7
Goro HPAL Heat Recovery
8
Simplified Autoclave Chemistry MeO + 2 H 2 SO 4 Me 2+ + 2 HSO 4 - + H 2 O H 2 SO 4 = H + + HSO 4 - Goethite Hematite Conversion 2 FeOOH + 6 H + 2 Fe 3+ + 4 H 2 O 2 Fe 3+ + 3 H 2 O Fe 2 O 3 + 6 H + Net: 2 FeOOH Fe 2 O 3 + H 2 O Alunite Formation 6 AlOOH + 9 H 2 SO 4 3 Al 2 (SO 4 ) 3 + 12 H 2 O 3 Al 2 (SO 4 ) 3 + 14 H 2 O 2 (H 3 O)Al 3 (SO 4 ) 2 (OH) 6 + 5 H 2 SO 4 Net: 6 AlOOH + 4 H 2 SO 4 + 2 H 2 O 2 (H 3 O)Al 3 (SO 4 ) 2 (OH) 6 Cr(VI) Formation 3 MnO 2 + 2 Cr 3+ + 2 H 2 O 3 Mn 2+ + 2 HCrO 4 - + 2 H +
9
Sulfate Distribution % Feed Comp 2.0 Ni 0.15 Co 2.1 Al 1.9 Cr 0.99 Mn 39.8 Fe 11.9 SiO 2 2.8 MgO
10
MOC Challenges Harsh service environment High temperature and pressure Jets of high-pressure acidic slurry Abrasive particles Hot acidic slurry for downstream circuits Solution may contain chloride anions
11
MOC Challenges: Autoclave Circuit Ti clad steel for pressure vessels using explosion cladding Base steel: ASTM A516 Gr 70 Cladding Ti material: Gr 1, Gr 11, Gr 17 100-mm steel thickness with 8-mm Ti clad Acid injection into autoclave: Teflon or tantalum lining on titanium dip tubes Block vales
12
Autoclave Valve Erosion M. King JOM, July 2005
13
MOC Challenges: Autoclave Feed Pumps Diaphragm pumps to handle abrasive slurry Temperature limitation on pump 200 C “Drop leg” design for diaphragm protection Specialty elastomers seats for check valves Pulp dilution and implication for downstream circuits
14
Concluding Remarks An overview of a challenging high T process in the mining industry Proper selection of MOC is critical Interactions with universities and other R&D centers have been valuable