1 The Application of WorkFace Planning
ty

2 The Application of WorkFace Planning
Geoff Ryan PMP WorkFace Planning Specialist Insight-wfp

3 Conference Theme The turbulence of the current extraordinary business environment demands leaders with exceptional perspective. Navigating a perfect storm requires timely, actionable insights beyond conventional wisdom. This year’s conference will address the amplification of risk and change in capital projects and provide tools and strategies to navigate our industry toward success.

4 Conference Theme The turbulence of the current extraordinary business environment demands leaders with exceptional perspective. Navigating a perfect storm requires timely, actionable insights beyond conventional wisdom. This year’s conference will address the amplification of risk and change in capital projects and provide tools and strategies to navigate our industry toward success.

5 Conference Theme Turbulence creates Leaders with Perspective, Insights and Wisdom The need for Risk and Change demands new strategies for success.

6 WorkFace Planning is: The systemic application of proven construction practices that enable productive activity. Detailed Work Plans Qualified Planners Removal of Constraints So What is different? This logic is not new, but it is also not common

7 WorkFace Planning gives you:
Improved Construction Productivity Reduced Schedule Up to 10% reduction in TIC Predictability

8 There will be a Rainbow after this storm
The Perfect Storm There will be a Rainbow after this storm

9 The new industry leaders will have a new strategy for success
The Perfect Storm The new industry leaders will have a new strategy for success

10 Highly productive construction will be the distinguishing feature
The Perfect Storm Highly productive construction will be the distinguishing feature

11 WorkFace Planning: Well Planned Well Executed
The Perfect Storm WorkFace Planning: Well Planned Well Executed

12 WorkFace Planning Components Conference Theme
Turbulence creates Leaders with Perspective, Insights and Wisdom The need for Risk and Change demands new strategies for success. WorkFace Planning Components

13 History 2000 2001 2001-5 2005 2006 2008 2009 Fast track mega project - Results Construction Owners Association of Alberta Industry research COAA Model Industry acceptance Lesson learned WorkFace Planning Institute Schedule for Sale

14 FIWP FIWP ITP – Q/A Requirements Safety Requirements
Construction Equipment Scaffold Builds Planned Value - Manhours Timesheet Cost Code FIWP System Designation Material Status IFC Drawings Activity ID & dates Let’s now have a look at the base elements of WorkFace Planning: Plans and Planners This first slide shows us the core elements of the Field Installation Work Package. The criteria for this content was developed by analyzing exactly what did the Foreman in the field need to execute work. All of the components listed here have to be in place before the work can get done. We can either give it to the foremen or let them to figure it out. Next slide 3D snap shots of work FIWP Field Installation Work Package GR

15 Traditional Best Practice Plan The Work Plan the Work Work Work the
Workface Planner Plan The Work Best Practice Construction Mgr General Foreman Superintendent Foreman Construction Mgr Superintendent Crew -10 Work the Plan General Foreman Crew -10 Work the Plan Foreman Foreman The other core element of WorkFace Planning is the WorkFace Planner. On the left side we have a traditional model for Planning and doing the work. The Superintendent , General Foreman and Forman plan the work and then the Foremen and tradesmen execute the work. During our research we found organisations that had an extra person in this loop. Most often it was an apprentice or a tradesman on light duty. This person would be an assistant for the general foreman. In the model for WorkFace Planning we developed this position with job descriptions and a training program that took former trade supervisors and gave then planning and computer skills. The process of creating this new demographic of planners is one area where we have been very successful. Next slide Foreman Foreman Foreman GR

16 GR

17 3-D Model Administrator
WorkFace Planning Installation Rates Progress Reports Progress Rules of Progress Level 3 Project Schedule COAA Model 3D Model Workface Planner WFP Software Drawings 3-D Model Administrator Field Installation Work Package Turnover Systems Work Breakdown Structure So now we have our Planners and our plans and the COAA model is realized. The problem now is how do we feed these guys information? And this is where we migrate across the fuzzy boarder between WorkFace Planning and Lean Construction. All of this stuff on the left are the streams of information that we need to feed to the planners. On our most successful projects we did this by using 3D WorkFace Planning software, like Bentley’s ConstructSim, Intergraph’s construction or the Aveva product. We then hired computer geeks to clean up the data so that it could be meaningful to the planners. In the world of information management we now understand that information needs to progress from Data to Information to Knowledge and finally to Understanding . This is not a natural evolution and it takes design and effort to make it happen. Next slide Construction Work Packages Progress Material Received Insight-WFP © Insight-wfp.inc 2009

18 Conference Theme Turbulence creates Leaders with Perspective, Insights and Wisdom The need for Risk and Change demands new strategies for success.

19 Conference Theme Turbulence creates Leaders with Perspective, Insights and Wisdom The need for Risk and Change demands new strategies for success.

20 Conference Theme Turbulence creates Leaders with Perspective, Insights and Wisdom The need for Risk and Change demands new strategies for success.

21 1 Rotation of Work (10 days) for 1 crew
Conference Theme 1 Rotation of Work (10 days) for 1 crew Turbulence creates Leaders with Perspective, Insights and Wisdom The need for Risk and Change demands new strategies for success. Level 5 Schedule Activity 1,000 Work Hours

22 WorkFace Planning Results
Conference Theme WorkFace Planning Results Turbulence creates Leaders with Perspective, Insights and Wisdom The need for Risk and Change demands new strategies for success. Before After Pipe: 4 man-hours per foot 2.6 man-hours per foot Steel: 38 man-hours per ton 27 man-hours per ton

23 Conference Theme Turbulence creates Leaders with Perspective, Insights and Wisdom The need for Risk and Change demands new strategies for success. More information: COAA website: WorkFace Planning Institute: Insight-wfp : ASI: Schedule for Sale :