1 Nevada Department of Transportation Research Program Ken Chambers

2 Nevada 2.8 million people (2 million in Clark Co.; 430,000 in Washoe Co.) 5,380 NDOT-maintained centerline miles (654 Urban; 4,726 Rural) 17 counties 4 MPOs

3 Nevada Constitutionally protected State Highway Fund Driver’s license & registration fees Fuel tax – 18.455¢ per gallon (27.75¢ for diesel) – 6.35¢ county mandatory tax – Up to 9¢ county optional tax – Washoe County indexing since 2003 State Highway Fund revenue: about $1 Billion

4 Nevada DOT Board oversight (Governor, Lt. Gov., Controller, 4 Appointees) 1,800 employees (200 admin.; 400 pre-const.; 400 const.; 800 maintenance) Three “Districts” 259 fatalities (2012)

5 NDOT Research

6 RDT annual apportionment: $1.7 million UTC participation: $250,000 Good department support Excellent support from administration!!

7 NDOT Research Expenditures

8 Project Selection Process (Through Federal Fiscal 2014) Followed our 2003 Research Manual An annual process Relied on two interdisciplinary groups of professionals within the Department: – The Research Advisory Committee – The Research Management Committee

9 Research Project Selection Process (Through Federal Fiscal 2014) DecemberJanuary February March April May June July November October September August Mar 1 – 15: RAC Evaluates and Prioritizes Problem Statements Jan 1 - 31: Develop/Prepare Problem Statements Feb 1 – 28: Sort, Screen and Clarify New Problem Statements Mar 16 -June 15: Proposal Development/Submission Oct 16 – Dec 31: Conduct Meetings/Brainstorm Sessions to Identify Research Needs Oct 1-15: Solicitation Begins; Distribute Problem Statement Form Sep 1-30: Agreement Drafting / Develop SPR Work Program Jun 15 – July 31: RAC Meets to Evaluate and Prioritize New Proposals Aug 1 – 31: RMC Meets to Approve New Research Priorities Research Timetable

10 Project Selection Process (Beginning Federal Fiscal 2015) Quarterly – Problem Statements – Proposals Eight Expert Task Groups SPR Task: Strategic Research Plan Update our Research Manual

11 Thank You! Ken Chambers Research Chief Nevada DOT 1263 South Stewart St. Carson City, NV 89712 (775) 888-7220 kchambers@dot.state.nv.us