Louisiana Community & Technical College System April 2013 Jan Jackson, Sr. Vice President for Finance & Administration PROGRESS of ACT 391 Construction Projects River Parishes Community College Ground Breaking Ceremony March 21, 2013
2
Campus : Westside Campus - Plaquemine Project: New Campus Const. Dates : Began March 2012 Substantial Completion Dec. 2012 Occupancy Jan. 4, 2013 Final 30 days following substantial completion Status: 100 % Complete ACT 391 – Capital Area Technical College
3
Campus : Project : Const. Dates : Began Substantially Completed Occupied Status : Ferriday Major renovations & additions April 2011 February 26, 2012 March 25, 2012 100% Complete Ribbon Cutting occurred on October 30, 2012 ACT 391 – Central LA Technical Community College
4
ACT 391 – Central LA Technical Community College Ferriday Campus Ribbon Cutting Ceremony October 30, 2012
5
Campus : Project : Const. Dates : Began Substantially Completed Occupied Status : Huey P. Long Campus - Winnfield New campus August 18, 2010 March 21, 2012 May 18, 2012 100% Complete Ribbon Cutting occurred on October 15, 2012 ACT 391 – Central LA Technical Community College
6
ACT 391 – Central LA Technical Community College Huey P. Long Campus, Winnfield Ribbon Cutting Ceremony October 15, 2012
7
Campus : Project : Const. Dates : Began Substantial Completion Occupied Status : New Main Campus – Houma/Schriever New Campus December 22, 2010 June 7, 2012 30 days following substantial completion 100% Complete Ribbon Cutting occurred July 31, 2012 ACT 391 – L. E. Fletcher Technical Community College
8
ACT 391 – L. E. Fletcher Technical Community College Houma/Schriever Ribbon Cutting Ceremony July 31, 2012
9
Campus : Project : Const. Dates : Began Substantial Completion Final Status : Florida Parishes - Greensburg New campus January 14, 2011 June 18, 2012 30 days following substantial completion 100% Complete, Ribbon Cutting occurred September 5, 2012 ACT 391 – Northshore Technical Community College
10
ACT 391 – Northshore Technical Community College Florida Parishes Campus - Greensburg Ribbon Cutting Ceremony September 5, 2012
11
Campus : Project : Const. Dates : Began Substantial Completion Final Status : Florida Parishes - Greensburg Child Care Facility June 25, 2012 December 15, 2012 30 days following substantial completion 100% Complete Ribbon cutting ceremony occurred on February 7, 2013 ACT 391 – Northshore Technical Community College Ray Smith Memorial Early Learning Center
12
Campus : Project : Const. Dates : Began Substantial Completion Final Status : Minden New campus February 16, 2011 April 16, 2013 30 days following substantial completion 98% Complete ACT 391 – Northwest LA Technical College Administration Building
13
ACT 391 – Northwest Louisiana Technical College Minden Campus Tech Building
14
ACT 391 – River Parishes Community College Campus : New Main Campus - Gonzales Project: New Campus Const. Dates: Began: December 17, 2012 Substantial Completion: March 16, 2014 Status: Ground Breaking Ceremony held on March 21, 2013
15
Campus : Project : Const. Dates : Began Substantial Completion Final Status : Young Memorial – Morgan City Expansion of existing campus July 18, 2011 August 20, 2012 30 days following substantial completion 100% Complete, Ribbon Cutting occurred on August 21, 2012 ACT 391 – South Central LA Technical College
16
ACT 391 – South Central LA Technical College Young Memorial Campus – Morgan City Ribbon Cutting Ceremony August 21, 2012
17
Campus : Project : Const. Dates : Began Substantially Completed Occupied Status: Gulf Area Campus - Abbeville Major renovation of existing campus March 1, 2011 December 7, 2011 January 6, 2012 100% Complete, Ribbon Cutting occurred on October 29, 2012 ACT 391 – South Louisiana Community College
18
ACT 391 – South Louisiana Community College Gulf Area Campus, Abbeville Ribbon Cutting Ceremony October 29, 2012
19
Campus : Project : Const. Dates : Began Substantial Completion : Status : SOWELA – Lake Charles Arts & Sciences Classroom Bldg. March 4, 2011 March 2012 100% Complete Ribbon Cutting Ceremony held on March 7, 2013 ACT 391 – SOWELA Technical Community College
20
ACT 391 – SOWELA Technical Community College Arts & Sciences Classroom Building – Lake Charles Ribbon Cutting Ceremony March 7, 2013
21
ACT 391 Campuses in Preliminary Stages of Design/Construction o Delgado Community College Learning Resources Center Mathes-Brierre Architects selected for design Campus has requested and LCTCS Facilities Corporation has approved relocation of the building Mathes Brierre restarted design phase in mid-November Construction Documents due end of April 2013
22
ACT 391 Campuses in Preliminary Stages of Design/Construction (cont’d.) o Delgado Community College, Sidney Collier Campus Demolition of existing buildings began November 2012 RFQ’s were due January 15, 2013 for Design Build Services RFP’s will be issued April 3, 2013, responses due April 26, 2013
23
ACT 391 Campuses in Preliminary Stages of Design/Construction (cont’d.) o South Louisiana Community College, Evangeline Campus – St. Martinville 100% Construction Documents are being reviewed RFQ’s for a General Contractor received January 8, 2013 Pre-bid meeting tentatively set for April 15, 2013 Construction to begin June 2013 o SOWELA Technical Community College, Allied Health & Nursing Building Architect Selected: Jeff Kudla in joint venture with Washer Hill Lipscomb Plans will be revised to coordinate HVAC systems with Arts and Sciences Project advertised in November 2012 and bid in December 2012 Construction completion estimated at March 2014
24
ACT 391 Campuses in Preliminary Stages of Design/Construction (cont’d.) o Nunez Community College, Administration Building FEMA has agreed to fund slab elevation, additional chill water line support mitigation, existing sign and fiber optics relocation Architect’s Estimate now within FP&C’s funds available for construction Revisions to Final Bid Documents were submitted in July 2012 Project to be advertised and bid in early 2013 Construction completion estimated at Spring 2014
25
ACT 391 Campuses in Preliminary Stages of Design/Construction (cont’d.) o Nunez Community College, Physical Activity Center Construction was planned to begin in March 2013 and scheduled to complete in December 2013 Architect selected is Lachin Oubre & Associates Bids were due March 7, 2013, both were over budget Currently rebidding for construction; bids are due early May 2013