BOND PROGRAM UPDATE Building Tomorrow Today Long Beach Community College District The Long Beach Rotary Flex Day,March 28, 2007 Flex Day, March 28, 2007.

Similar presentations


Presentation on theme: "BOND PROGRAM UPDATE Building Tomorrow Today Long Beach Community College District The Long Beach Rotary Flex Day,March 28, 2007 Flex Day, March 28, 2007."— Presentation transcript:

1 BOND PROGRAM UPDATE Building Tomorrow Today Long Beach Community College District The Long Beach Rotary Flex Day,March 28, 2007 Flex Day, March 28, 2007

2 AGENDAAGENDA  Completed Construction Projects  Current & Upcoming Construction Projects ­South Quad Complex – Bid #2 ­LAC Central Plant Structure ­LAC Learning Resources Center – Interim ­LAC Learning Resources Center - Structure ­South Quad Complex Structure ­PCC Central Plant & Utilities ­PCC Learning Resources Center ­PCC Industrial Tech Phase 1 ­PCC Industrial Tech Phase 2  What’s Next?  Q & A

3 PCC CDC – 4/06 District Facilities & Warehouse Complex – Opened 1/17/06 Men’s Gym Boiler Replacement – 4/06 PCC MM/NN Lighting Upgrade – 4/05 LAC Athletic Field – 3/06 South Quad Complex Bid Pkg. #1 – 12/05 LAC/LRC Utilities–6/06 LAC Men’s Gym Façade Replacement (FEMA & Insurance Funded) East Campus Demolition Various Projects COMPLETED CONSTRUCTION PROJECTS

4 LAC Construction Phasing

5 Construction 98.5% Complete Relocation of Water Main and Reclaimed Water Lines Coordinated with Central Plant Relocates Major Utilities Out of Golf Mall Clears Way for Structures South Quad Complex – Bid Package #2 CURRENT & UPCOMING CONSTRUCTION PROJECTS

6 Part of Infrastructure Master Plan Improvements Early Utility Package Under Construction Awarded to Siemens on DBOM Contract Construction Starts April; Contractor Mobilizing Completion Anticipated Summer 2008 LAC Central Plant – Structure CURRENT & UPCOMING CONSTRUCTION PROJECTS

7 Construction 50% Complete Anticipate Completion June 2007 Modular Buildings to be Installed Saturday 3/31/07 Utility Installation Complete Under Previous Phase (Bid Pkg. #1) Includes Retrofit of Building E Basement LAC/Learning Resources Center – Interim Facilities CURRENT & UPCOMING CONSTRUCTION PROJECTS

8 Re-Bid Opening 3/29/07 First Bids Rejected Move Planning Underway Utility Installation Complete Under Previous Phase (Bid Pkg. #1) Anticipate Start in June 2007; Completion in December 2008 LAC/Learning Resources Center – Structure CURRENT & UPCOMING CONSTRUCTION PROJECTS

9 Construction Begun; Approx. 35% Complete Overlaps Central Plant Early Piping Due to Utility Conflicts Additional Modern Classrooms, Multi- purpose Rm., Offices, etc. Shifts Campus Center South of Carson off Lew Davis South Quad Complex Structure (Bid Pkg. #3) CURRENT & UPCOMING CONSTRUCTION PROJECTS

10 PCC Construction Phasing

11 Part of Infrastructure Master Plan Improvements Early Utility Package Under Construction; Approx. 98.5% Complete. Allows Utility Installation while Structure is in Plan Check Clears Way for Structure Structure in Plan Check DBOM Contract Awarded to Siemens; Anticipate NTP April (NOI Issued) PCC Central Plant & Utilities CURRENT & UPCOMING CONSTRUCTION PROJECTS

12 Awarded to Soltek Pacific Construction Start in April Pending State Authorization Modern Facility with Computer Lab and Multimedia Expanded Facility Bridge to Bldg. EE Art Deco Style PCC Learning Resources Center CURRENT & UPCOMING CONSTRUCTION PROJECTS

13 Replaces Existing Antiquated Structures DSA Reviewing Changes; Out to Bid; Start in July 2007 Modern Facility Houses Machine Tools and Welding Depts. New Campus “Bookend” S.E. Interim Bungalow Construction In Close Out Phase to Clear Tech 1 Site PCC Industrial Technology Center Phase 1 CURRENT & UPCOMING CONSTRUCTION PROJECTS

14 Replaces Existing Antiquated Structures Construction Underway; Approx. 53% Complete PCC Industrial Technology Center Phase 2 CURRENT & UPCOMING CONSTRUCTION PROJECTS Modern Facility Houses Aviation and Automotive Depts. Impacted by DF&WC Completion in Summer 2007

15 Student Services Centers –LAC Planning Underway; Construction to Start at End of South Quad Complex –PCC Awaiting State Funding; Will Start Construction in 2009/2010 –Centralizes Student Support Services (Admissions, Financial Aid, Cashier, Counseling, Job Placement, etc.) Secondary Projects LAC & PCC WHAT’S NEXT? Multi-Disciplinary Academic Buildings (AA, BB, DD, EE) –Awaiting State Approval to Start Design; Antic. August 2007 –Construction 2009 –Retrofits Most of Existing Occupants in More Efficient Facility –Classrooms and Offices –Labs Including Computer, Art, Foreign Language, English, and Science Labs –Absorbs Some Portable Occupants New Building M Gym (Q & R) Projects Building E & F

16 QUESTIONS & ANSWERS March 28, 2007 Prepared By: Bond Management Team BUILDING  TOMORROW  TODAY