Information Technologies - Computer Systems Winter 2010 Capstone Project By:Dale Baziw BJ Brommeland Jamie Scales
2
Goals Project Overview Milestones Budget Problems Lessons Learned Recommendations References & Questions
3
Meet a need identified within industry Showcase interesting technologies Exploration of systems integration Application of ITCS course aspects Leveraging of core competencies
4
Client/Server interaction which employs: Virtualization Solid State Drives Touch Screen Interface Server Side Communications Systems Integration
5
Image 1: Client/Server Network Diagram Image 2: Virtual Machine Server Diagram
6
Virtualization Environment Hypervisor Server Implementation Database Server Web Server File Server Inter-VM Communication
7
Database generation and population Web-based front end Client configuration
8
Estimated Labour Cost Number of Employees3 Hours worked per week9 Length of Project (weeks)14 Cost Per Hour$35 Total Labour Cost$13,230 Total Project Costs Labour$13,230 Total Cost of Hardware$2,232.14 Total Cost of Project$ 15462.14 Table 1: Estimated Labor Cost Table 2: Total Project Costs
9
Software Compatibility Server Communications Advanced Programming Data Formatting User Interface Effectiveness
10
Proper project planning Ensure software compatibilities between components “Sandbox” testing environment Proper data formatting
11
Software compatibilities Front end flash player Advanced search capability Include other media such as: Movie Previews Game Demonstrations
12
[1] Citrix XenServer. www.citrix.com. (Accessed February 2010)www.citrix.com Image 1: Client/Server Network Diagram. Dale Baziw, MS Visio Image 2: Virtual Machine Server System. Dale Baziw, MS Visio Table 1: Estimated Labor Cost. JDB Enterprises Formal Report Table 2: Total Project Cost. JDB Enterprises Formal Report