Galveston Seawall Boulevard Transit/Pedestrian Access and Beautification Program PHASE 2 IMPLEMENTATION UPDATE PHASE 2 IMPLEMENTATION UPDATE February 12, 2015
2
Seawall Beautification & Pedestrian Access Plan PHASE 2 CONSTRUCTION ITEMS Seawall Boulevard Transit Pedestrian Access & Beautification Improved Bus Stops at 15 Intersections Restrooms at 5 Locations Lighting Demo 19 th to 29 th Gateway Markers at 9 Locations Landscaping Gateways at 5 Locations ADA Beach Access at 35 th ADA Jetty Access at 29 th being evaluated Project SIT – 35 benches
3
Seawall Beautification & Pedestrian Access Plan Seawall Boulevard Transit Pedestrian Access & Beautification IMPROVEMENT ITEMS Landscaping Bus Shelter Public Restroom Gateway Marker
4
Seawall Boulevard Transit Pedestrian Access & Beautification INDIVIDUAL NODE ILLUSTRATIONS
5
Seawall Beautification & Pedestrian Access Plan PHASE 2 CONSTRUCTION PLANS Seawall Boulevard Transit Pedestrian Access & Beautification 90% Complete Awaiting Reviews Corps of Engineers Texas Historical Commission ADA issues Three Procurements Complete Construction/Installation Prefabricated Restrooms Bench Sole Source
6
Seawall Beautification & Pedestrian Access Plan Package to Purchasing -- March 6 Advertise for Bids -- March 15, 22 Prebid Meeting -- March 25 Bid Opening -- April 8 Council Awards Contract -- April 23 Begin Construction -- May 11 Restroom Installation -- August Complete Construction October 30 [Subject to Corps of Engineers Section 408 Review] Seawall Boulevard Transit Pedestrian Access & Beautification UPDATED SCHEDULE
7
Galveston Seawall Boulevard Transit/Pedestrian Access and Beautification Program PHASE 2 IMPLEMENTATION UPDATE PHASE 2 IMPLEMENTATION UPDATE February 12, 2015