Download presentation
Presentation is loading. Please wait.
Published byRaymond Norton Modified over 9 years ago
1
Workshop on Achieving Universal Electricity Access in Myanmar
Sector Wide Approach (SWAp) - Organizing, Planning, Implementation and Financing Universal Electricity Access Rwanda National Electrification Program Experience, lessons, implications Arun P. Sanghvi Consultant Workshop on Achieving Universal Electricity Access in Myanmar Naypyitaw, May 31 – June 1, 2013 master may 30 6pm Bongiorno Apologies but my Italian does not go much beyond biongiorno, so this presentation will need to be in English. Introduction – name It is I will give you an overview of the WBG renewable energy interventions.
3
Organization of Presentation
Sector wide approach (SWAp) What is a SWAp? architecture differs from other approaches used to plan, finance and implement development projects Rwanda National Electrification program (NEP) - SWAp experience National context and drivers SWAp building blocks Prospectus - from vision to implementation Key policy and planning issues Implementation results to date Lessons Implications for Myanmar
4
Government leadership and policies make the difference International experience Population without Access to Electricity and poverty prevalence (2008)
5
Anatomy of a SWAp organizing framework
“Many Partners, One Team, One Plan” Stakeholders SWAp Government Development Partners Utility Regulatory Authority Local Government Sector Ministries Private Stakeholders Consumers Country-owned and led, results focused, long-term sector development program Brings together development partners and other stakeholders to coordinate aid effectiveness within the sector Implementation aligned with national development priorities and targets Traditionally used to coordinate investments in schools and health clinics; but now being deployed effectively for scaling up electricity access nationwide (Rwanda, Kenya, Indonesia, SE4ALL) Sustainable and predictable funding anchored by a least cost sector-wide investment plan for national electrification program; integrating technical, financial and implementation. Shift from piecemeal aid delivery, project-by-project, donor-by-donor to programmatic, results-focused implementation framework
6
Rwanda National Electrification Program – clear vision and targets
Post-conflict imperative for rapid scale up of productive infrastructure for powering accelerated growth and social sector services delivery, and meeting basic energy needs 2004 Extremely low electrification rate (65,000 connections = approx. 6% ) Severe drought period led to shortages Low available generation capacity (41MW) 50% peak hour load shedding Electrogaz recorded annual operating losses >US$9.1million Recovering from civil war 2008 110,000 households and enterprises connected (80% of which are in Kigali) 50% Health facilities with access to reliable energy 20% Schools with access to reliable energy 25% Sector offices with access to reliable energy Urgent Electricity Rehabilitation Programme (UERP) invests US$34 million to deliver 20MW of thermal generating capacity 2009- Next Steps: SWAp A programme to increase electricity connections from 110,000 (2008) to 350,000 (2014), and substantially increase access to electricity for social infrastructure
7
Rwanda NEP SWAp – building blocks
July Energy Sector Working Group (SWG) established. MoU signed - Ministers of Finance and Energy, and senior development partners Bankable Prospectus prepared (2009) - high level information document anchored by : Geospatial least-cost national rollout program (grid and off-grid) Integrated with most effective renewable energy supply sources Connection costs based on affordability Explicit cost reduction strategy Transparent and sustainable financing platform agreed jointly with development partners
8
Rwanda Prospectus Scope
Task 1: Rapid appraisal and readiness assessment (Sept – Oct. 2008) institutional framework key institutions Technical, financial, policy, regulatory, capacity Task 2: Geospatial least-cost grid roll-out + off-grid plan fro national electrification Task 3: Review adequacy of bulk power supply system and investment requirements
9
Prospectus Scope ….Rwanda
Task 4: Sector financial analysis & projected financing (balance sheet, sources and uses of funds) Investment and recurrent costs Revenues from tariffs, efficiency improvements, utility self generation Government equity transfers, other committed financing Task 4: Draft Prospectus and first round Donor review (January 2009) Task 5: Final Prospectus and Donor Financing Round Table to address financing gap (March 2009)
10
Geospatial least cost national electrification plan Grid extensions and rollout coordinated with off-grid complement Physical plans and investment cost for increasing electricity access for households, health centres, administrative offices and schools, consistent with policy targets and with overall sector growth Comprehensive GIS (Geographical Information System) data base Population density, economic activity areas, priority social institutions (health centers, schools, administrative offices) data from National Bureau of Statistics, National GIS Centre, MINALOC, MINEDUC, MINISANTE, MININFRA, ELGZ Digitization of existing and planned national electricity grid Affordability based on household income and expenditure data Supply options off-grid - Micro-hydro mini grids, diesel grids, solar home size systems, charging products
11
Current Electricity Network
Total Connections 110,00 0 Population Coverage 6% Social Connections Schools 21% Health centres 74% Admin offices 67% More than 60 per cent of population live within 5 km of existing network
12
AFREA Support for Energy Sector SWAps
Transitional off-grid areas shrink as grid rollout expands Rapid spatial planning platform utilized in Rwanda AFREA Support for Energy Sector SWAps
13
Population Density Source: CGIS-NUR, Ministry of Local Government – National ID Project, Ministry of Infrastructure, National Institute of Statistics, Rwanda
14
Health Centers 74 percent of health centers currently have access
Sources: MINALOC, MININFRA, MINISANTE
15
Secondary Schools 21 percent of schools currently have access
Sources: MINALOC, MININFRA, MINEDUC
16
Administrative Offices
67 percent of administrative offices currently have access Sources: MINALOC, MININFRA
17
Affordability of Electricity by District
Percent of population with expenditure of less than US$1.25 per day Source: EICV2 Survey
18
GIS-Based Rapid Spatial Planning Platform
Powerful Planning Tool for National Electrification Program Rollout to meet time bound targets
19
2009 Grid Program Total Connections 146,969 Population Coverage 7%
Social Connections Schools 27% Health centres 82% Admin offices 69%
20
2010 Grid Program Total Connections 204,397 Population Coverage 10%
Social Connections Schools 35% Health centres 88% Admin offices 83%
21
2011 Grid Program Total Connections 270,380 Population Coverage 13%
Social Connections Schools 43% Health centres 93% Admin offices 92%
22
2012 Grid Program Total Connections 350,000 Population Coverage 16%
Social Connections Schools 50% Health centres 100% Admin offices
23
Access Programme to 2020 Total Connections 820,00 0
Population Coverage 36% Social Connections Schools 68% Health centres 100% Admin offices
24
AFREA Support for Energy Sector SWAps
Spatial least cost national electrification rollout in Rwanda grid and off-grid, AFREA Support for Energy Sector SWAps
25
Electricity access planning for national electrification
SWAp - sector-wide national electrification planning platform - Spatial least-cost national grid (and off-grid complement) integrated rollout investment & implementation plan proved to be extremely effective: Seen as a national development plan rather than a electricity sector plan engaging all key stakeholders (in country and external) rallying development Partner contributions Modest cost and frequent updates – resulting in a dynamic planning platform: Classical style “RE Master Plan” overly cumbersome (2-3 years) high cost (1-2 million $) updated less frequently static in representation of changing conditions over time (grid rollout, demand, priority locations); project here and there and now and then approach when donors come “shopping”
26
Planning for affordability Controlling costs
Balancing affordability for new users, improving financial health of national utiltity, and program financing on a sustained basis Planning for affordability The proportion of households that live on less than US$1.25 per day is between 50% and 80% in most areas But affordability analysis showed a relatively high willingness to pay for electricity Controlling costs Technical specifications were revised: Changing from lattice framed steel towers to wooden poles (below) Using single-wire earth return (SWER) lines in rural areas Using local manufacturing for required materials, wherever possible Doubling contract sizes to gain economies of scale Despite low income levels in Rwanda, analysis showed that 370,000 hhs would be willing and able to pay cost of grid connection and recurrent charges Targeted cost reduction per connection: US$1,000 (in 2009) to US$600 (in 2013) due to planned efficiencies
27
Sustainable Financing Policy Platform
Underpinning NEP- SWAp Prospectus time slice Consensus built around “ ” policy for first SWAp Prospectus Concessionary finance from Donors on-granted to ELGZ , with policy to be re-visited for second SWAP time slice post 2014 Programme Costs Financially sound utility - Utility expected to contribute 10% to capital costs (from on-going tariff revenues) - Investments in new generation also funded from tariffs Connection charges based on ability to pay - Consumers expected to pay nominal US$100 connection charge Government and donor support - Needs to meet remaining 80% of costs
28
Partner Pledges - Prospectus Donor Financing Round Table (Sum)
Programmed Donor Contribution World Bank+GEF Dutch Government 78.3 45 JICA African Development Bank 25 50 Committed Donor Funding (Off Grid) European Commission 35 New Partners BADEA OFID Saudi fund 10 Government Contribution ($10m/yr.) ELGZ Customers 27 TOTAL financing 357.3
29
Donor financing Roundtable, Kigali, April 2009
Matching NEP investment and TA costs with syndicated financing
30
Key outcomes and implementation results
Rwanda NEP –SWAp Key outcomes and implementation results Donors Round Table April successful syndication (financing) pledges of US$225 million for first slice of the program ( ) identified in program Prospectus. Donors uniformly commented that the Prospectus presented in a consistent, comprehensive and convincing manner: The program is transformative; It is technically sensible; It is economically and financially viable; and it is implementable ELGZ, established the National Electrification Program Management Department integrally within Electrogaz’s corporate structure to oversee planning, design, and implementation, pooling of all funds irrespective of donor, monitoring and evaluation, and Reporting accountability (no more enclave style PMUs ). Commitment to the staged reductions in average unit connection costs - first two years of connections achieved within budgeted unit cost estimates of US$1,000/connection, Substantially lower cost than pre-SWAp program project averages Program implementation early results – On track to achieve objective of 16% electrification by 2013 Programme Connections (Target and Actual) 2008 Actual 2009 2010 2011 (August) 2014 Target New connections < 5,000 32,995 43,733 40,419 Households connected to electricity 110,896 143,891 187,624 228,043 350,000
31
Rwanda lessons – Key Success Factors
Strong country ownership and leadership up and down the chain of accountability Cabinet , MINECOFIN, MININFRA, Other Line Ministries – Health, Education, Environment Committed National Utility (ELGZ) Linkages to comprehensive and inclusive national vision and priorities Ensured that the SWAp is aligned with the policy direction of the Government Key stakeholder consensus and buy-in built from outset, through work by the SWG, led by the Minister on Energy Consultation process, workshops, retreats prepared stakeholders well for the Donor Round Table South-South Cooperation and Training Technical designs, planning, implementation, logistics\ GIS anchored data capture and grid rollout planning Preparation across all key ministries in a coordinated manner Affordable and inclusive Connection charges set at affordable levels Managing the transition from planning to implementation
32
Key benefits of a SWAp framework for national electrification
Increased predictability (and possibly scale) of sector funding Increased transparency and accountability More effective partnerships Increased donor coordination leading to complimentary investments less duplication or wasted resources Lower transaction costs of disbursing and receiving donor funds Ensures an appropriate level of input from development partners into policies, priorities, and sector expenditure
33
AFREA Support for Energy Sector SWAps
Other National Electrification programs utilizing SWAps AFREA Support for Energy Sector SWAps Kenya NEP (population 41 million; access ~ 29 %) Prospectus raised US$1.5 billion to support government target of 1 million new connections over ; implementation rate scaled up from ~40,000/yr. to ~ 250,000 connections/yr. Indonesia Prospectus preparation ongoing (population ~235 million. Access ~ 70 percent) 75 million w/o access; investment required ~ $700m/yr. plus generation; implementation rate ~ 1,000,000 connections/yr. PNG NEP Prospectus preparation ongoing (population 7 million; access ~ 17 percent)
34
Geo (new+ maintenance) 215 Coal (proposed) 391 $565 M
Kenya National Electrification Program Investment Prospectus ( ) - $1.9 Billion Total Cost Breakdown Amt Generation $634 M Hydro upgrade 27 Geo (new+ maintenance) 215 Coal (proposed) 391 Transmission $565 M New transmission lines 360 International Tran lines 195 Distribution $718 M Transformers, Substations 78 PV for schools 29 Isolated Mini grids 90 LV reinforcement 61 Grid Connections 460 4/16/2017
37
Wither Forward - Myanmar's National Electrification Program
39
Myanmar’s - National Electrification Program Towards a Brighter Future for All Within a Generation?
“Yes we can”
40
cè-zù tin-ba-deh thank you
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.