February 1, 2012 Casino Facility Progress Report.

Similar presentations


Presentation on theme: "February 1, 2012 Casino Facility Progress Report."— Presentation transcript:

1 February 1, 2012 Casino Facility Progress Report

2 Construction Progress – February 1, 2012 Contract sum to date:164,372,575 Total project completed to date: 85% MBE / WBE awarded to date:$ 35,900,000 * Average daily # of construction workers on-site: 300 Note: * - MBE/WBE amount exceeds original goal by over $14,000,000.

3 Arial View

4 January 26, 2012 Tour Team member Training Room.

5 January 26, 2012 Tour – Team Member Dining Room

6 January 26, 2012 Tour – Epic Buffet

7 January 26, 2012 Tour – Gaming Floor

8 Comparative Photos (Final Cut Steak & Seafood House – photo #1)

9 Comparative Photos (Final Cut Steak & Seafood House – photo #2)

10 Comparative Photos (Epic Buffet)

11 Comparative Photos (Skybox Restaurant & Bar)

12 Comparative Photos (Serpentine Sign)

13 Comparative Photos (Poker Room)

14 Summary Timeline Surveillance: – System Programming/Testing: January 3-15, 2012 – System Turnover to Property: January 16, 2012 Food & Beverage: – Epic Buffet & Final Cut Steakhouse Partial Certificate of Occupancy: December 27, 2011 – Team Member Dining Room Open: January 6, 2012 Slots: – Carpet Installation: December 14, 2011 to February 10, 2012 – Slot Bases Installation: December 19, 2011 to March 2, 2012 – Order/Delivery: All games ordered and ready to ship (awaiting final Commission approval) – Estimated Installation: TBD (30 day duration) Table Games: – Artwork/layouts submitted to Commission for review & approval: December 21, 2011 – Carpet Installation (Pit areas): To be completed by February 29, 2012 – Order/Delivery: All games ordered and ready to ship (awaiting final Commission approval) – Estimated Installation: March 1-5, 2012 Final Inspection/Certificate of Occupancy: – Certificate of Occupancy: March 15, 2012

15 Staffing Update StatusNumber Active Team Members69 Future Dated Offers228 Completed Offers in 2 Weeks700 Total997 All employees identified as key employees to date have submitted a complete key license application (14 in total).

16 Vendor Update StatusNumberPercentage MBE/WBE Vendors2310.50 All Other Vendors19789.50 Total220100.00

17 Public Safety Outreach Most recent meeting held on January 30, 2012 with the following attendees: – Captain Brad Weis – Toledo PD (Strategic Response – Hollywood Contact person for opening – Thomas Wiegand – Toledo PD (Area Commander) – Chief Mark Hetrick – Perrysburg Township PD – Chief Thomas Cairl – Northwood PD – John Altman – Ohio Highway Patrol – Eric Reynolds – Deputy Chief, Wood County – Seven (7) other members of local law enforcement Topics included: Team member & guest safety, Traffic flow, Natural Disasters, Gangs, Miscellaneous crimes & threats. Bi-weekly meetings to occur going forward.