Trimble Quantm Haul Road Optimization Presenters Name
2
Overview The haul road problem – what are we trying to solve The Quantm Software Integrated workflows using the Trimble Tablet
3
Haul roads The main consideration is optimal grade –Reduce fuel consumption –Reduce tire wear –Reduce machine wear Two main consideration for haul roads –Maintenance, performing analysis on existing haul roads to maintain or improve haul road grade –Site expansion, preforming analysis to create and select new haul roads
4
Trimble Quantm Alignment Planning System A unique system route alignment optimization Applied by mine and site planners Investigates millions of alignments for: –Faster Project Planning –Reduced Capital Construction and Operating Cost –Better Environmental and Public Outcomes –Thorough Demonstration of Alternatives Analysis
5
Enables the simultaneous consideration of multiple factors during the alternatives analysis phase: –Environmental –Engineering –Economic/Cost –Community Trimble Quantm Alignment Planning System
6
Trimble Quantm Desktop Applications Planning of haul roads for mining and construction Traditional alignment planning Estimation and initial management of project earthworks and mass haul Design construct value engineering Alternative analysis during construction
7
Trimble Quantm Desktop Key feature – Vertical Optimization –Import CAD road design (horizontal only or 3D) If 3D, quantity and construction cost of the alignment is calculated –Manual creation and editing horizontal alignment –Vertical optimization of existing design if 3D alignment imported –Vertical optimization and creation of vertical design for 2D or manual 2D alignment –Study are size, 10km x 10km or 20km x 20km licenses Why buy Desktop? –Entry level solution – scalable to Premium and Service products –Manual creation of geometric alignments with quantities and costs –Vertical-only optimization, horizontal held fixed –Assists earthworks and costs by manipulating vertical of existing alignment
8
Trimble Quantm Desktop Premium Key features – Full Optimization –Full horizontal and vertical optimization capabilities in addition to Desktop version Unseeded - Free to roam optimizations Seeded - Optimize from initial alignment both horizontally and vertically Realignment - optimize based on minimizing deviation from existing centreline –10 x 10, or 20 x 20 km licenses Why buy Desktop Premium? –Proven capabilities of the Quantm service on the users PC –Optimize existing concept designs vertically –Conduct full scoping, feasibility and final alignment studies, from defining corridors to detailed 3D alignments
9
Trimble Quantm Haul Road Optimization How It Works
10
Operator reviews alignments Operator makes changes and resubmits Trimble Quantm Desktop Overview Project Data Digital Terrain Model (DTM) Land Use Constraints Unit Construction Costs Alignment Geometry Road/rail/river Crossing Rules Geology Quantm generates optimized alignments for review
11
Study Area – Mountainous Terrain (5-8km Road) Digital Terrain Model Geometric Parameters Costs Constraints
12
Free to Roam – 100km/h Design Speed Low Cost Corridor Free to Roam Options
13
Initial haul road Option Comparing Quantm Developed existing Comparing Haul Roads
14
Profile view Comparing Two Alternatives - Same Corridor
15
Where are the Major Savings?
16
Trimble Quantm Haul Road Optimization Haul Road Construction
17
Infield Haul road definition Grade Control Business Center- HCE *.svd; *.svl SCS900 *.ttm; *.dc *.tag Quantm Desktop *.ttm; *.pro; *.dxf Alignments, *.ttm; *.pro; *.dxf
18
In field Haul road workflow 1.Use SCS900 to collect existing Topo information and features. 2.Transfer TTM surface and feature data from SCS900 to Quantm Desktop (on Tablet) Maintenance applications collect existing centreline of haul road for vertical optimization, in addition to site features. New haul roads collect any features (streams, water features etc) 3.Switch to Quantm Desktop and perform optimization 4.Transfer resulting haul alignments back to SCS900 for stakeout
19
Haul Road Stakeout Detailed ground survey –Additional updates to the model Staking out the corridor –Export alignment as PRO file –Stake out earthworks footprint with GPS or Total Station
20
Construction Haul road construction –Export alignment via TBC/TCC to a machine for construction of haul roads