1
Project Estimation: Demystifying the Black Art
2
How good an estimator are you?
3
For the following questions… Give a range (upper and lower bounds) Do not make your ranges either too wide or too narrow Make the range so you believe there is a 90% chance of including the right value
4
What is the surface temperature of the Sun?
5
What is the weight of the heaviest blue whale ever recorded?
6
Quiz Results
7
We stink at estimation.
8
Psychology works against us.
9
Feeling of ignorance Protection of pride Influence from expectations
10
Psychology works against us. We don’t estimate accurately We don’t plan accordingly We don’t execute correctly We don’t reflect properly
11
Psychology works against us. We don’t estimate accurately We don’t plan accordingly We don’t execute correctly We don’t reflect properly
12
Artificially Narrow Ranges
13
Probability of correct estimation 100%
14
Quiz Expectations 90%
15
Business Expectations 25%
16
Single Point Estimations > 1%
17
Under-estimation Reduced effectiveness of project plans Reduced chance of on-time completion Destructive late-project dynamics
18
Over-estimation Parkinson’s Law Student Syndrome
19
Give Probability Ranges
20
My Business Expectations 50% 25%75%
21
We don’t like ranges
22
Put uncertainty into your estimation practices
23
The Golden Spiral
25
Planning Poker
26
Tainting estimates with customer expectations
27
We don’t know what we are estimating
28
“Build me a house.”
29
Find your project’s estimation cornerstones
30
How Many Bedrooms? 2 Bedrooms ~ 800 sq ft., 1 bathroom, 1 stall garage, small or shared yard. 4 Bedrooms ~ 1400 – 2200 sq ft., 2 bathrooms, 2 stall garage, yard
31
How Many Bedrooms? Prioritizing size and complexity will trigger defensive responses Prioritizing details will trigger optimism (i.e. size and complexity will fit inside details)
32
2 Day Crutch Method
33
Forces further exploration of unknown or large features
34
2 Day Crutch Method Forces further exploration of unknown or large features Insists task break downs of lengthy known features
35
2 Day Crutch Method Forces further exploration of unknown or large features Insists task break downs of lengthy known features Teaches the wisdom of knowing when something is really unknown
36
Modifying estimates with “control knobs”
37
Psychology works against us. We don’t estimate accurately We don’t plan accordingly We don’t execute correctly We don’t reflect properly
38
Estimates ≠ Plans
39
Estimation = Planning “Plans are worthless — but planning is everything.” —Dwight D. Eisenhower
40
Psychology works against us. We don’t estimate accurately We don’t plan accordingly We don’t execute correctly We don’t reflect properly
41
Not forcing clarity on project uncertainty
42
“It feels like 20 hours, but let’s put 24 hours to fudge it a little bit…”
43
Cone of Uncertainty
44
$100k 50k 200k 67k 150k80k 125k 25k 400k
45
Hofstadter's Law
46
The Gut Instinct Equation
47
Psychology works against us. We don’t estimate accurately We don’t plan accordingly We don’t execute correctly We don’t reflect properly
48
Estimates are for visibility, not accountability
49
“A good estimate is a estimate that provides a clear enough view of the project reality to allow the project leadership to make good decisions about how to control the project to hit its targets” [Steve McConnell, Software Estimation]
50
Psychology working for us. Be aware we don’t like being uncertain Use estimates to humbly understand unknowns Create team unity that is quick to extinguish unknowns
51
Questions?
52
http://gosquids.com/Estimation.pptx http://gosquids.com/Estimation.mp3