11th meeting of the Steering Committee for Pan-European Corridor X Belgrade, Republic of Serbia 21-22.01.2010.
2
11 састанак Надзорног одбора за Пан-Европски Коридор Х Београд, Република Србија 21-22.01.2010.
3
Government of the Republic of Serbia Ministry of Infrastructure CORRIDOR X On going activities Belgrade, 22. January 2010.
4
The legal framework for the development of railway infrastructure in Serbia AGC Agreement AGTC Agreement High performance network Agreement (SEECP Railway Agreement) European Railway network for high-speed Pan-european transport corridors Signed MoU between Serbia and FYROM (10.9.2009.) and Serbia and Hungary (12.10.2009.) for the mutual participation in the planning and realization of the projects for Corridor X
5
PROGRAMME OF THE MODERNIZATION Corridor X – final goal: - Reconstructed in double track, electrified and equipped with modern signalization - Designed for speed of 160 km/h - Available for all technologies of combine transport Corridor X – final goal: - Reconstructed in double track, electrified and equipped with modern signalization - Designed for speed of 160 km/h - Available for all technologies of combine transport Investment: 4,611 bill Euros Investment: 4,611 bill Euros Finished Transport Master Plan for Serbia, financed by EC. Document is in the process of verification. TMP identified Developing Projects of all modes of transport, in the railway and intermodal sector - 14 projects. Finished Transport Master Plan for Serbia, financed by EC. Document is in the process of verification. TMP identified Developing Projects of all modes of transport, in the railway and intermodal sector - 14 projects.
6
Р. брRailway line Length (км) constra ction expro priati on docume ntation Indirect costsTotal 1 Belgrade - Šid 118,927011829318 2 Belgrade - Subotica 149,6737333481885 3 Belgrade node 218241323278 4 Belgrade - Niš 240,88705140961057 5 Niš - Preševo 156,190032411001073 6 Niš - Dimitrovgrad 103,98502136931000 Total769,338451621824224611 TOTAL ESTIMATED COST OF CONSTRUCTION RAILWAY KORIDOR X (mil euros)
7
Corridor X 4.611 (mill. €) Belgrade –Šid 318 Belgrade –Subotica 885 Belgrade node Belgrade node 278 Belgrade –Niš 1.057 Niš –Preševo Niš –Preševo 1.073 Niš –Dimitrovgrad Niš –Dimitrovgrad1.000 SOURCES OF FINANCING government budget International financial institutions EU funds Private capital 3
8
Phases for modernization Phase 1 – –Single track Belgrade-Novi Sad-Subotica to double track on the Sections: Stara Pazova-Novi Sad, and Novi Sad-Subotica-Border to Hungary – –Single track Belgrade-Niš to double track on the Sections: (Belgrade) Resnik-Klenje-Mali Požarevac-Velika Plana Gilje-Ćuprija-Paraćin (Ćićevac) Stalać-Djunis – –Modernization of the Belgrade and Novi Sad railway nodes – –Reconstruction and modernization of the Single track Niš- Dimitrovgrad-Border to Bulgaria
9
Phases for modernization Phase 2 – –Modernization of the existing double track Belgrade-Šid-Border to Croatia – –Reconstruction of the Single track Niš-Preševo- Border to FYROM – – Modernization of the Niš railway node Phase 3 – –Single track Niš-Preševo-Border to FYROM to double track – –Single track Niš-Dimitrovgrad-Border to Bulgaria to double track
11
Investments in the infrastructure and in the rolling stock EIB I, 70 mill. euro (realised, 2003-2006) ЕBRD I, 57 mill. euro (realised, 2003-2006) EIB II, 80 mill. euro (ongoing, 2008-2011) ЕBRD II, 60 mill. euro (ongoing, 2008 -2011) EIB III, 150 mill. euro (negotiation, 2010-2013) Single track Belgrade-Novi Sad-Subotica to double track, Section Stara Pazova–Novi Sad for speed 160 km/h. Deadline: 2012. ЕBRD III, 100 mill. euro (negotiation, 2010-2013), for purchasing a modern EMU. Tender will be will be announced in March 2010. Deadline : end of 2011. WB, 100 mill. euro (negotiation, 2010-2013) EUROFIMA, 43 mill. CHF (ongoing, 2009-2011) for purchasing a modern DMU. Deadline: end of 2011.
12
Bilateral credit arrangements Credit arrangement with the Czech Republic in the amount of 120 mill. euro, for modernization of the line Nis–Dimitrovgrad in terms of electrification, safety equipment. Deadline: 2011. Credit arrangement with the Russian Federation in the amount of 600 mill. US dollars for: – –Completion of the Belgrade railway node (200 mill. US dollars), – –Completion of the Railway line Valjevo - Loznica (about 160) – –Modernization of the railway line Belgrade - Vrbnica (Bar) (about 240). Negotiations are in progress. Deadline: 2013. Credit arrangement with the Kingdom of Spain in the amount of 37 mill. euro, for purchasing a modern DMU. The tender will be announced in March 2010.
13
Status of works on Corridor X until end 2009 Batajnica – Golubinci (21,5 km) - - All structural and electrical works along the railway line are finished - - Station tracks of the 3 station on this section are repaired, with enlarging platforms and canopies - - The value of works was about 30 mill. euro
14
Status of works on Corridor X until end 2009 Ćele kula – Staničenje - - One segment of the Project of the modernization and reconstruction of railway line Niš–Dimitrovgrad - - From EIB II 30.6 mill. euro were provided (estimated total value of the works is about 50 mill. euro) - - Other works on the modernization and reconstruction of the Niš–Dimitrovgrad railway line, will be financed through Bilateral credit arrangement. Negotiations are in progress - - Expropriation of the land, worth about 200,000 euro, also should be committed in the next period - - At certain intervals, during the works on this line, railway traffic will be suspended
15
Status of works on Corridor X until end 2009 Gilje – Ćuprija – Paraćin (10,5 km) - - From EIB II 27.6 mill. euro were provided (estimated total value of the works is about 46 mill. euro) - - Preparatory activities for building the bridge near Ćuprija (322.5 m long) are started. Tender procedure is ongoing. - - Expropriation of the land, worth about 200,000 euro, is also in progress. Expropriation of the entire Section is estimated at 1.8 million. euro and the time period for implementation of these activities is estimated at one year. - - Construction permit for works on the Section is provided - - Missing funds will be provided by bilateral loan or IFI
16
Government of the Republic of Serbia Ministry of Infrastructure CORRIDOR X On going activities Belgrade, 22. January 2010.