Systems Engineering (SE) for ITS: Using FHWA’s New SE Handbook March 2007
2
2 Presenters Emiliano Lopez –FHWA Office of Transportation Management –(202) 366-2199 –Emiliano.Lopez@fhwa.dot.govEmiliano.Lopez@fhwa.dot.gov Mac Lister –FHWA Resource Center –(708) 283-3532 –Mac.Lister@fhwa.dot.govMac.Lister@fhwa.dot.gov
3
3 Poll 1 (Please reply with the most appropriate answer:) Local/municipal agency State agency Federal agency Education Consultant Other Who’s Participating in this T3?
4
4 Poll 2 (Please reply with the most appropriate answer:) I am not familiar with SE. I have heard of SE. I am familiar with some SE concepts. I have started using some SE methods. Chances are that you already use some form of SE practice, but we would like to know your level of familiarity with SE.
5
5 Poll 3 (Again, please reply with the most appropriate answer:) No I am aware of the Handbook I have glanced at the Handbook I have read portions of the Handbook I have read most of the Handbook Have you looked at or read the FHWA SE for ITS Handbook?
6
6 Overview Learning goals/outcomes New SE for ITS Handbook Benefits of using SE ”V” Model Overview of Handbook chapters Available SE training & resources
7
7 Learning Goals/Outcomes Identify what is in the Handbook Describe the key features of the Handbook List key content chapters in the Handbook including: –technical processes –project management processes –applying SE
8
8 About the Handbook –Developed by FHWA SE Deployment Team –Designed for Federal and public ITS professionals –Provides a basic understanding of SE and how to apply it to ITS projects –Assists those deploying ITS projects –Available via CD and online using the following link: http://ops.fhwa.dot.gov/publications/seitsguide/index.htm http://ops.fhwa.dot.gov/publications/seitsguide/index.htm New SE for ITS Handbook
9
9 Benefits of Using SE Reduced risk of schedule and cost overruns Increased likelihood that the implementation will meet user’s needs Improved stakeholder participation More adaptable and resilient systems Verified functionality and fewer defects Higher level of reuse from one project to the next Better documentation
10
10 Project Success Rates Figure 6: Standish Group Chaos Report, 2004 Page 8 (Ch. 3)
11
11 Architecture and Standards Rule (940.11) The systems engineering analysis shall include, at a minimum: 1) Identification of portions of the regional ITS architecture being implemented (or if a regional ITS architecture does not exist, the applicable portions of the National ITS Architecture) 2) Identification of participating agencies roles and responsibilities 3) Requirements definitions 4) Analysis of alternative system configurations and technology options to meet requirements 5) Procurement options 6) Identification of applicable ITS standards and testing procedures 7) Procedures and resources necessary for operations and management of the system
12
12 ”V” Model FHWA representation of SE methods Representation of system development process Addresses the project lifecycle Aligns with the traditional project development process
13
13 “V” Model Page 11 (Ch. 3) Figure 7: “V” Model
14
14 Traditional Model vs. V Model Page 96 (Ch. 6) Figure 37: SE as an Extension to the Traditional Project Life Cycle
15
15
16
16 Design of the Handbook ● Based on project level efforts ● Focused on 3 primary Activities − Developing the right system Based on user needs − Managing ITS elements on the project Stay on time and on budget − Applying SE to projects ● Modular to address different knowledge needs
17
17 Design of the Handbook (cont.) Navigating the Document Innovative use of icons Tips Cautions Resources Tailoring Tool Rule/Policy Terminology
18
18 Key Sections of the Handbook Page i (Ch.1 -3) Table of Contents
19
19 Key Sections of the Handbook Page i (Ch. 4-7) Table of Contents Building it right On time, on budget
20
20 Chapter 4 of the Handbook Page i (Ch. 4) Technical Processes
21
21 Chapter 4: ITS Technical Processes Explains SE through use of the“V” –Objectives –Inputs (Things needed to begin this step) –Processes (key activities) –Outputs (Deliverables) –Reviews (when it’s safe to move the project forward) Aids in project definition, specification, design and build Includes examples of SE documentation
22
22 “V” Model Page 11 (Ch. 3) Figure 7: “V” Model Lifecycle
23
23 Section 4.3 Chapter 4: ITS Technical Processes Concept of Operations Summary Chart
24
24 Chapter 4: ITS Technical Processes Sampling of ConOps Summary Chart (Section 4.3) Input –Feasibility Study –Stakeholder input and review Processes –Develop an initial ConOps –Define stakeholder needs –Develop an initial validation plan Output –System Validation Plan –ConOps Review –Approved ConOps and Validation Plan
25
25 Outline 1. Scope 2. Referenced Documents 3. The Current System or Situation 4. Justification for and Nature of Changes 5. Concepts for the Proposed System 6. Operational Scenarios 7. Summary of Impacts 8. Analysis of the Proposed System Chapter 4: ITS Technical Processes Example Concept of Operations Operational Scenarios Figures 13 and 15 ConOps Section 4.3.4 Marcel, a StarTran bus operator, usually begins his work shift with administrative activities. After receiving supervisory direction, he boards the bus and prepares the AVL system. He begins by logging into the system. The system then prompts Marcel for the route to be followed. He enters the planned route number, and the AVL system retrieves the appropriate route and schedule information from the AVL system server. The bus’ AVL system then asks Marcel to verify the appropriate route and schedule information were properly retrieved. Once he provides verification, the bus’ head sign is automatically updated to reflect the appropriate route information. The fare payment schedule is automatically adjusted to reflect the verified route, modified as necessary by the system clock to reflect any applicable time-differential rates. The system then loads the appropriate bus stop announcements for the chosen route. These prerecorded announcements are consistent regardless whether Marcel or another bus operator is driving the route, and have been verified as ADA compliant. These announcements are then broadcast at the appropriate bus stop throughout the route. Based on IEEE 1362
26
26 Chapter 4: ITS Technical Processes System Requirements Summary Chart Section 4.4 From previous step
27
27 Chapter 4: ITS Technical Processes Sampling of System Requirements Chart (Section 4.4) Input –Concept of Operations (stakeholder needs) Processes –Develop requirements from user needs –Review and refine user needs –Trace requirements to user needs Output –System Requirements Document –Traceability Matrix Review –Approve system requirements
28
28 Chapter 4: ITS Technical Processes Example Validating Quality Attributes of Requirements Table 7 Requirements Section 4.4.2
29
29 Chapter 4: ITS Technical Processes System Design Summary Chart Section 4.5 From previous step
30
30 Chapter 4: ITS Technical Processes SE Design Tailoring Advice (Section 4.5.1) Leverage and optimize prior work –Reuse and build on existing design documentation –Update old documentation with new functionality or interfaces Do not reinvent the wheel for each project
31
31 Chapter 4: ITS Technical Processes System Verification Summary Chart Section 4.7 From previous step
32
32 Chapter 4: ITS Technical Processes Sampling of System Verification Chart (Section 4.7) Input –Design specifications –Verification Plans Key Activities –Perform verification –Perform integration Output –Integration testing and analysis results –Verification results including problem resolutions Review –Documented evidence that the system meets requirements
33
33 Chapter 4: ITS Technical Processes System Verification Policy and Terminology (Section 4.7.2) The systems engineering analysis requirements identified in FHWA Rule 940.11/FTA Policy Section VI require identification of testing procedures; verification procedures described in the Handbook cover this. Verification Techniques –Inspection –Demonstration –Test –Analysis
34
34 Table 15: ODOT TripCheck 2.0 System Test Results (Excerpt) Table 13: Verification Procedure Example: ODOT TripCheck Functional Test Plan (Excerpt) Table 14: CHART II Integration Test Plan (Excerpt) System Verification Examples (Section 4.7.4) Chapter 4: ITS Technical Processes System Verification Plans & Procedures
35
35 Chapter 5 of the Handbook Page i (Ch. 5) Project Management Processes
36
36 Chapter 5 Project Management Processes Cross-cutting/project-wide processes –Project Planning –Project monitoring and control Risk management Configuration management
37
37 Chapter 5: Project Management Processes Excerpts of Project Planning Activities (Chapter 5.1) Project Plan (Section 5.1.1) –Accounts for project activities, resources & budget –Includes project time-line –A “how-to” implementation manual SE Management Plan (Section 5.1.3) –Top level plan for the SE activities –Includes technical planning and control
38
38 Chapter 5: Project Management Processes Excerpts of Project Monitoring/Control (Section 5.2) Project Tracking (Section 5.2.1) –Methods for measuring progress against the plans/contract –Serves as a trend indicator for meeting budget and schedule Project Reviews (Section 5.2.2) –Structured and organized communication of progress and product development Formal or informally done Typically conducted at the end of a V phase and before beginning the next phase
39
39 Document Maintenance and Operations Activities Develop and Maintain a Cost Database for Maintenance and Operations Analyze Maintenance and Operations Requirements Analyze Staffing Requirements for Maintenance and Operations Develop a Training Program for Maintenance and Operations Personnel Prioritize Maintenance Needs Develop and Maintain a Spare Parts Inventory Develop a Maintenance Plan Develop an Operations Manual (Table 10) Traceability of Work Products (Table 19) Risk Prioritization (Figure 33) Operations & Maintenance Planning Chapter 5: Project Management Processes Example Project Monitoring/Control (Section 5.2)
40
40 Chapter 6 of the Handbook Page i (Ch. 6) Applying Systems Engineering
41
41 Chapter 6 Applying Systems Engineering ● Tailoring SE for your project − Enhances current project delivery practices − Helps focus on risky project steps − Allows selection of “as-needed” project deliverables and processes − Not an opportunity to skip steps! − Even the small projects need documented expectations
42
42 Chapter 6: Applying Systems Engineering Applying SE in Your Organization (Section 6.3) ● Include experienced Systems Engineers on each ITS project ● Adopt a defined organizational process for SE ● Acquire SE tools to help manage the process
43
43 Chapter 6: Applying Systems Engineering SE Process Improvement (Section 6.3) ● Develop repeatable processes ● Incorporate SE into existing business processes and practices ● Hold post project reviews to assess the application of SE (what worked – what needs to be refined) ● Modify processes based on lessons learned
44
44 Page 96 (Ch. 6) Figure 37: SE as an Extension to the Traditional Project Life Cycle Traditional and V Relationship
45
45 Traditional and V Relationship Page 96 (Ch. 6) Figure 37: SE as an Extension to the Traditional Project Life Cycle
46
46 Page i (Ch. 7) Chapter 7 of the Handbook SE Resources
47
47 Chapter 7: Resources ITS-Specific Publications (Section 7.1) Checklists & Templates
48
48 CA SEGB Requirements Document Checklist CA SEGB Section 8.4.6
49
49 CA SEGB System Requirements Template CA SEGB Section 8.4.6 Based on the IEEE Std. 1233
50
50 Chapter 7: Resources SE General SE References (Section 7.2)
51
51 Chapter 7: Resources Selected SE Standards (Section 7.3)
52
52 Chapter 7: Resources Systems Engineering Training (Section 7.4)
53
53 Available SE Resources for ITS Contact FHWA Resource Center/Division Offices Systems Engineering Web Page (FHWA) http://www.ops.fhwa.dot.gov/int_its_deployment/sys_eng.htm Lessons Learned Knowledge Resource (ITS JPO) http://www.itslessons.its.dot.gov/its/benecost.nsf/LessonSystem sEng Solutions Center (ITS JPO) -- Coming Soon Archived T3 http://www.pcb.its.dot.gov/T3/archives.asp http://www.pcb.its.dot.gov/T3/archives.asp California SE Guide Book http://www.fhwa.dot.gov/cadiv/segb http://www.fhwa.dot.gov/cadiv/segb Guide to Contracting ITS Projects (NCHRP) http://www.trb.org/nchrp/its/index.htm http://www.trb.org/nchrp/its/index.htm
54
54 Relationship to the California SE Guide Book Read the HQ SE for ITS Handbook first to get a solid foundation on what SE is and how to apply it If needed, reference the CA Guide Book for specific details In some cases, states/locals will only need to read the HQ SE for ITS Handbook in order to manage a project consultant/contractor The CA Guide Book will be an additional reference for managing the consultant/contractor and cross- checking and validating the consultants’ work
55
55 Contact Information & Thank You Emiliano Lopez –FHWA Office of Transportation Management –(202) 366-2199 –Emiliano.Lopez@fhwa.dot.govEmiliano.Lopez@fhwa.dot.gov Mac Lister –FHWA Resource Center –(708) 283-3532 –Mac.Lister@fhwa.dot.govMac.Lister@fhwa.dot.gov Thank You!